- That the contents of this report be noted. (2) Recommended:- That the updated 2014/15 to 2016/17 Capital Programme be approved, in particular noting the following major additions to the Capital Programme and supplementary approvals to existing schemes:- · New Central Primary School, Eldon Road. (Additional cost of £1.050m, Minute F5 Cabinet Member for Children and Education Services, 16th September 2014). · Rawmarsh St. Mary’s PRU (Cost of £0.069m. Works approved by the former Strategic Director of Children and Young People’s Services, Joyce Thacker, 23rd July 2014). · Thrybergh Country Park Phased Improvements (Cost of £0.136m. Works approved by the Director of Internal Audit and Asset Management, Colin Earl, 5th November 2014 and reported to CSART , 27th November 2014). · Aston, Aughton and Swallownest Phase 2 Drainage Works (Cost of £0.145m. Grant funding allocated by the Environment Agency.). · Bailey House Renovation project (Additional cost of £0.034m approved by CSART , 23rd October 2014. Original project approval, Minute C34 Cabinet, 21st July 2010). Where not funded by grant or by the service, the revenue implications from these schemes has been built into the Council’s MTFS assumptions.
Word for word from the decision Rotherham published for this meeting.Source: moderngov.rotherham.gov.uk
The purpose of this report is to provide details of the current forecast outturn for the 2014/15 programme and enable the Council to review the capital programme for the financial years 2015/16 and 2016/17.
Recommendations
CABINET IS ASKED TO:
NOTE THE CONTENTS OF THIS REPORT; AND
RECOMMEND THE APPROVAL OF THE UPDATED 2014/15 TO 2016/17 CAPITAL PROGRAMME BY FULL COUNCIL. IN PARTICULAR, NOTING THE FOLLOWING MAJOR ADDITIONS TO THE CAPITAL PROGRAMME AND SUPPLEMENTARY APPROVALS TO EXISTING SCHEMES.
• New Central Primary School, Eldon Road. (Additional cost of £1.050m, Minute F5 Cabinet Member for Children and Education Services, 16th September 2014) • Rawmarsh St. Mary’s PRU (Cost of £0.069m. Works approved by the former Strategic Director of Children and Young People’s Services, Joyce Thacker, 23rd July 2014) • Thrybergh Country Park Phased Improvements (Cost of £0.136m. Works approved by the Director of Internal Audit and Asset Management, Colin Earl, 5th November 2014 and reported to CSART, 27th November 2014) • Aston, Aughton and Swallownest Phase 2 Drainage Works (Cost of £0.145m. Grant funding allocated by the Environment Agency.) • Bailey House Renovation project (Additional cost of £0.034m approved by CSART, 23rd October 2014. Original project approval, Minute C34 Cabinet, 21st July 2010).
Where not funded by grant or by the service, the revenue implications from these schemes has been built into the Council’s MTFS assumptions. 7 Proposals and Details
7.1Background - The Capital Programme 2014/15 to 2016/17
The budget process that led to the original Capital Programme for 2014/15 to 2016/17, ensured that the Council’s capital investment plans were aligned with its strategic priorities and vision for Rotherham.
In order to maintain that strategic link, and make best use of the capital resources available to the Council, it is important that this programme is kept under regular review and where necessary revisions are made. This programme was last reviewed in September 2014, and has now been the subject of a further review, the results of which are reflected in the Directorate summary table presented below. A detailed analysis of the programme for each Directorate is attached at Appendices 1 to 4.
The financial implications of the Programme are reflected in the Council’s Medium Term Financial Strategy (MTFS) and Treasury Management and Investment Strategy.
2014/15 2014/15 2015/16 2015/16 2016/17 2016/17 Revised Variance Estimate Variance Estimate Variance Estimate from from from Last Last Last Report Report Report
This updated programme has been prepared in light of the capital resources known to be available to the Council over these financial years, and estimated on a prudent basis.
The Council is continuing to undertake a comprehensive review of its assets and buildings portfolio, with the aim to rationalise both its operational and non- operational asset holdings, which may contribute both a future capital receipt and a revenue saving. 7.2 Children and Young People’s Services Capital Programme 2014/15 to 2016/17
The revised proposed spend for 2014/15 is £11.896m, with a further £11.957m of investment in the remaining two years of the current programme.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.