ROTHERHAM BOROUGH COUNCIL – REPORT TO AUDIT CABINET
1. Meeting: Cabinet
2. Date: 9th June, 2010
3. Title: Annual Governance Statement 2009/10
4. Directorate: Financial Services
5 Summary: The attached Annual Governance Statement (AGS) for 2009/10 outlines the Council’s view of the application of good governance standards in Rotherham MBC. The overall picture presented is positive, although three significant issues have been identified for inclusion in the AGS. The Statement also provides an update on the significant issues reported in the 2008/09 AGS.
In line with last year, the draft AGS will be presented to the Audit Committee (on 2 June) to enable the Committee to carry out a review of the AGS and supporting evidence, before the Statement is presented to the Cabinet for agreement. In accordance with proper practice, the Leader of the Council and the Chief Executive will be asked to sign the statement after agreement by Cabinet. The agreed statement will then be presented to the Audit Committee on 30 June for adoption along with the Statement of Accounts.
The Corporate Governance Group and Audit Committee will monitor progress on actions to improve areas included in the 2009/10 AGS and will review the effectiveness of governance arrangements during 2010/11.
6 Recommendations The Cabinet is asked:
• To agree the draft 2009/10 Annual Governance Statement
• To note the requirement for the Leader and the Chief Executive to sign the statement after it has been considered by Cabinet and prior to its formal presentation to the Audit Committee on 30 June.
1 7 Proposals and Details
7.1General principles The Council is responsible for ensuring that its business is conducted in accordance with the law and proper standards, and that public money is safeguarded, properly accounted for and used economically, efficiently and effectively.
In discharging these responsibilities, the Council must ensure that there is good governance and a sound system of internal control in place, which facilitate the effective exercise of the Council’s functions and which include arrangements for the management of risk.
The Council’s governance arrangements in place during 2009/10 have been reviewed and an Annual Governance Statement (AGS) has been drafted and is attached to this report at Appendix A.
7.2Procedure The AGS outlines the Council’s view of the application of good governance and internal control in Rotherham MBC in 2009/10.
Proper practice requires the Leader and the Chief Executive to sign the statement to confirm their satisfaction with the governance framework and the procedures for reviewing it, and their acceptance of the significant issues highlighted in the statement, along with actions for tackling the issues raised. The Statement must then be presented to the Audit Committee for its adoption in accordance with the Accounts and Audit (Amendments) (England) Regulations 2006.
Additionally, in line with last year, the draft AGS will be presented to the Audit Committee to enable the Committee to carry out a review of the AGS and supporting evidence, before the Statement is presented to the Cabinet for agreement.
Even though the AGS is incorporated into the Council’s Statement of Accounts which is presented to the Audit Committee, the Use of Resources criteria requires the AGS to be considered separately.
7.3Structure of the Annual Governance Statement The attached AGS is laid out in accordance with proper practice as set out by CIPFA. There are 5 sections:
• Section 1: Scope of the Council’s responsibility • Section 2: Purpose of the Governance Framework • Section 3: The Council’s Governance Framework which identifies the governance arrangements in place at the Council. • Section 4: Review of effectiveness. This looks at the process that has been applied in maintaining and reviewing the effectiveness of the governance framework
2 • Section 5: Significant governance issues. These are the main issues that require improving.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.