Resolved
Resolved :- That the schools photovoltaic project be approved.
Cabinet (Pre-Intervention approved this item on Wednesday 2 June 2004. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved :- That the schools photovoltaic project be approved.
In partnership with Nationwide Solar, Rotherham Council intends to fit large arrays of photovoltaic panels on 8 schools in Rotherham:
Projected Energy Output School PV Size (kW) (kWh / yr)
Anston Greenlands Primary 33 27,000 Anston Hillcrest Infants 15 12,300 Anston Hillcrest Junior 19 15,500 Thrybergh Primary 16 13,100 Rawmarsh Sandhill Primary 26 21,300 Rockingham Primary 33 27,000 Greasbrough Junior & Infant 33 27,000 St Bedes Primary 22 18,000
The capital costs will covered by Low Carbon Building Grants (50%) and Nationwide Solar (50%). Nationwide Solar will claim the Feed in Grants (set for 25 years by Government) for total kWh generated. Schools will receive free electricity and 10% of the Feed in Tariff.
6. Recommendations 1. Cabinet approve the schools PV project. 7. Proposals and Details
Feed in Tariff (FITS) was introduced in April 2010 to incentivise small scale low carbon electricity generation (less than 5MW). The scheme guarantees a set amount that can be claimed for every kW generated over the next 25 years. The tariff up to 2013 for PV panels are:
Yr 1: 1/4/10 – 31/3/11 Yr 2: 1/4/11 – 31/3/12 Yr 3: 1/4/12 – 31/3/13 31.4 p/kWh 31.4 p/kWh 28.7 p/kWh
The Low Carbon Buildings Grant scheme allowed public organisations to apply for up to 50% of the installation costs for renewable micro-generation systems. Applications were submitted for 62 Rotherham Schools before the scheme closed on 24 May 2010. Of the 62 applications 8 schools succeeded in securing grants:
School Low Carbon Building Grant
Anston Greenlands Primary School £85,892.41 Anston Hillcrest Primary School £39,768.82 Anston Hillcrest Junior School £50,051.84 Thrybergh Primary School £42,189.58 Rawmarsh Sandhill Primary School £67,897.12 Rockingham Primary School £85,892.41 Greasbrough Junior & Infant School £85,890.91 St Bedes Primary School £57,614.11
Projects must be complete and grants claimed by 28 February 2011. Department of Energy and Climate Change announced in September 2010 that Low Carbon Building Grants and FITS could be utilised on the same project.
Nationwide Solar will install, maintain, insure and monitor the PV systems at no cost to the school or RMBC. Capital costs will be re-claimed by Nationwide Solar by claiming the FITS.
Agreement for the project will be sought through Head Teachers; Governors; Education; Capital Strategy, Strategic Leadership Team and Cabinet. All lease documents will be checked by the Legal Department and signed by Assistant Director of Legal Services.
8. Finance
Projected figures show a substantial annual saving on electricity bills:
Average Projected Projected Energy PV Size p/kWh Utility Saving School Output (kW) Rate (Av. 20010/11 (kWh / yr) (p/kWh) contract price) Anston Greenlands Primary 33 8.719 27,000 £2354.13 Anston Hillcrest Primary 15 7.308 12,300 £898.88 Anston Hillcrest Junior 19 10.131 15,500 £1570.30 Thrybergh Primary 16 10.131 13,100 £1327.16 Rawmarsh Sandhill Primary 26 10.131 21,300 £2157.90 Rockingham Primary 33 10.131p 27,000 £2735.37 Greasbrough Junior & Infant 33 7.720 27,000 £2084.40 St Bedes Primary 22 10.131p 18,000 £1823.58
The capital costs will be covered by Low Carbon Building Grants (50%) and Nationwide Solar (50%). Nationwide Solar will claim the Feed in Grants (set for 25 years by Government) for total kWh generated. Schools will receive free electricity and 10% of the Feed in Tariff.
9. Risks and Uncertainties
There is a risk that Government will cancel the Feed in Tariff. The risk is primarily taken by Nationwide Solar who is investing the capital in the project.
Projections of kWh output and potential financial savings are based on light level analysis carried out by Nationwide Solar engineers and are to be taken with caution. Actual output is weather/light level dependant.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Photovoltaic Panels on Eight Rotherham SchoolsReport | 3 pages | DownloadRead as text |
Follow Cabinet (Pre-Intervention at Rotherham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Jun 2004 | IntroductionResolved :- (1) That a variation to the Standing Orders to allow for filming in the Council Chamber be approved. (2) ... | Approved | Open |
| 2 Jun 2004 | Questions from Members of the Public.It was agreed to provide a detailed answer in writing. | Agreed | Open |
| 2 Jun 2004 | Awards- That Members and staff involved be congratulated on these achievements. | Decided | Open |
| 2 Jun 2004 | John GomersallResolved :- That the best wishes of the Council be forwarded to John for a speedy recovery . | Decided | Open |
| 2 Jun 2004 | Wath Comprehensive SchoolResolved :- (1) That everyone involved in developing the new premises be congratulated on this outstanding success an... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.