ROTHERHAM BOROUGH COUNCIL – REPORT TO AUDIT COMMITTEE
1. Meeting: Audit Committee
2. Date: 16 December 2009
3. Title: KPMG progress report
4. Directorate: Financial Services
5. Summary KPMG periodically produces a report identifying progress against its audit plan activities for presentation to the Audit Committee in accordance with the Committee’s terms of reference. This report refers to the latest KPMG progress report.
6. Recommendations The Audit Committee is asked to note the progress made by KPMG against its audit plan activities.
1 7. Proposals and Details
Attached at Appendix 1 is KPMG’s latest update report on progress made against its audit plan. The update is produced periodically for submission to the Audit Committee, in accordance with the Committee’s terms of reference.
The progress report refers to KPMG’s planned and completed activity for both 2008/09 and 2009/10. Of the seven pieces of work scheduled for 2008/09:
• 4 have been completed • Reviews of Waste Management and the Town Centre Redevelopment are ongoing • A report following the review of the Maltby Joint Service Centre is expected to be produced in the near future. This is a joint audit being completed by KPMG for Rotherham MBC and the Audit Commission for NHS Rotherham. KPMG has finished its work and provided details of its findings and conclusions to officers. The Audit Commission is expected to complete its work shortly, which will then enable a consolidated report to be presented to officers and Members.
Of the 2009/10 programme (7 pieces of work):
• Two ongoing items (Waste Management and Town Centre Redevelopment) having been brought forward from 2008/09 • Work on the Work Smart review has commenced and is expected to be completed by February 2010 • Initial work on Value for Money, Internal Control and the Use of Resources has commenced • Work on the statement of accounts will start in the Spring 2010.
There are no critical issues arising out of the work completed so far.
The Audit Committee is asked to note the progress made by KPMG against its audit plan activities.
8. Finance
There are no direct financial implications arising from this report.
9. Risks and Uncertainties
In the event of a KPMG Audit report being returned which contains recommendations for improvement, these will then be entered onto the Chief Executive’s Recommendation database. Progress against each recommendation is then monitored and recorded and reported on a quarterly basis by an officer from the Chief Executive’s Performance & Quality team, to the Corporate Management Team, Audit Committee and PSOC.
2 10. Policy and Performance Agenda Implications
Implications will vary depending on the recommendations that are proposed by the auditors. KPMG may suggest a range of proposals which will impact swiftly on the respective area once the report is made final. The Council’s ability to monitor recommendations has been commended in the previous Audit Commission reports.
11. Background Papers and Consultation
KPMG Audit Plans, 2008/09 and 2009/10 KPMG completed audit reports.
Contact Names: Stuart Booth, Director of Central Finance, ext 22034
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
KPMG Progress ReportReport | 3 pages | DownloadRead as text |
PDF |
KPMG Progress Statement as at 16 December 09Report | 3 pages | Download |
Follow Audit Committee at Rotherham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 24 Sep 2026 | Exclusion of the Press and Public- That, under Section 100A(4) of the Local Government Act 1972, the press and public be excluded from the meeting for... | Decided | Open |
| 24 Sep 2026 | Minutes of the previous meeting held on 28th July, 2026- That the minutes of the previous meeting of the Audit Committee be approved as a correct record of proceedings. | Approved | Open |
| 24 Sep 2026 | External Audit Progress Report and Sector Update- That the progress and sector updates be noted. | Noted | Open |
| 24 Sep 2026 | Code of Corporate Governance- That the refreshed version of the be received and noted. | Noted | Open |
| 24 Sep 2026 | Anti-Money Laundering Policy Review- (1) That the revised Anti-Money Laundering Policy be received and noted. (2) That the actions being undertaken to r... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.