Children and Young People's Services - Capital Budget Monitoring 2010/2011
NotedCommittee1 paper
Children, Young People and Families' Services noted this item on Wednesday 19 January 2011. Below is the council's own wording, with the papers it was decided on.
Resolved :- (1) That the report be received and its contents noted. (2) That it be noted that the Children and Young People’s Services’ Capital Programme for 2010/11 was £21.370 million and expenditure to 15th November, 2010 was £9.458 million and that the Capital Programme was expected to spend to budget by 31st March, 2011.
Word for word from the decision Rotherham published for this meeting.Source: moderngov.rotherham.gov.uk
Report to Children, Young People and Families' Services
Summary
The 2010/11 Children and Young People’s Services’ Capital Programme is £21,730m. The programme is forecast to be fully spent by 31st March 2011. This capital report shows the capital programmes actual expenditure to 15th November 2010 and projected expenditure to 31st March 2011.
Recommendations
Cabinet Member is asked to note:
- The Capital Programme for 2010/11 is £21,370m. Expenditure to 15th November 2010 is £9,458m.
- The Capital Programme is expected to spend to budget by 31st March 2011. 7. Proposals and Details
7.1Below is the summarised budget, actual costs to 15th November 2010 and projections for 2010/11.
Actual Revised Projected Expenditure Capital Expenditure Scheme Blocks 01/04/2010 Programme to to 2010/11 31/03/2011 15/11/2010 £ 000 £ 000 £ 000
Primary Schools 7,494 2,915 7,494
Secondary Schools 1,975 716 1,975
Special Schools 79 22 79
City Learning Centres 1,758 698 1,758
Capitalised Major Repairs - All Schools 900 499 900
7.2Primary Schools Under the Governments Primary Capital Programme Funding, Cabinet has approved a number of key projects including:
A New Junior and Infant School at Swinton Queen. The building will comprise of one foundation, two reception, two infant and six junior classrooms as well as the main foyer and reception, hall and community room. Work commenced in April 2010. The full cost of the build is expected to be £5.440m. The poor weather has restricted progress and the project is now three weeks behind schedule so has a revised completion date of 29th April 2011.
Rawmarsh Monkwood Primary School’s new single storey Infant School building comprising of two foundation and two infant classrooms, main entrance foyer and reception was opened to pupils on the return from October half term. The total scheme cost is expected to be £2.410m. The main building was finished in October and work is now being completed on the new playing field. The project is on budget with a cost in year of £1.841m. 7.3 Building Schools for The Future Following the cessation of the BSF programme in July of this year, the Maltby Academy development was placed on a list of academy projects for further discussion. The Authority continues to work with the Academy Sponsor, the Department for Education (DfE) and their agent, Partnership for Schools (PfS) on the development and scale of the Academy project. The DfE have confirmed that it will be early in 2011 before they can advise on the level of funding available.
7.4City Learning Centre Winterhill City Learning Centre has commenced with plans for an Extension. Work started on site on the 22nd November 2010 with hand over scheduled for the 15th July 2011. Contracts have been signed with Balfour Beatty the PFI provider and the contractor R H Fullwoods & Co Ltd. The profile costs are £689k in 10/11 and £345k in 11/12.
7.5Sure Start Centres All capital works are complete on the phase 3 Children’s Centres at Listerdale and Thurcroft with both centres fully operational. The extension at Rockingham Children’s Centre, the reception at Catcliffe and IT improvements at the Arnold Centre are also complete.
Current 2010-11 Sure Start funded projects include:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Children, Young People and Families' Services at Rotherham and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.