CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Rotherham Metropolitan Borough Council

Pedestrian Crossing Assessment Method and Costs

Noted Scrutiny 2 papers

The Former Regeneration Scrutiny Panel noted this item on Wednesday 23 March 2011. Below is the council's own wording, with the papers it was decided on.

Item118

Resolved

- (1) That a scrutiny review take place on this subject and that a scoping meeting take place as soon as possible. (2) That the contents of the report be noted.
Word for word from the decision Rotherham published for this meeting. Source: moderngov.rotherham.gov.uk

Follow this further

Built from Rotherham's papers

What the report saysPro

Report to The Former Regeneration Scrutiny Panel, 5 pages

Recommendations

The Scrutiny panel is asked to note the contents of this report. 7. Proposals and Details

Assessment of crossing requests The Council has a policy, based on current national guidance produced by the Department for Transport, of only providing controlled pedestrian crossing facilities when the value of vehicle (V) and pedestrian (P) flows multiplied together (using the formula PV2/108 and adjusted for certain factors) exceeds 1.0. In order to consider requests where the criteria is almost met the Cabinet Member for Regeneration and Environment will make a decision on each case where this value is between 0.85 and 1.0.

The first stage in the assessment of a request for a controlled pedestrian crossing is to do a pedestrian and vehicle survey. This survey is done for the 12 hour period from 07:00 to 19:00 and covers 50m either side of the site where the crossing has been requested. This survey is then used as the basis for the detailed assessment.

For each of the twelve hours of the survey the number of pedestrians crossing (P) is multiplied by the square of the traffic flow (V) to give the unmodified PV2 value. This is then multiplied by the site specific adjustment factors to give the modified PV2 value. Adjustment factors are used to take into account the proportion of elderly, blind/partially sighted and mobility impaired pedestrians, the proportion of unaccompanied children, the proportion of pedestrians with prams and pushchairs, the carriageway width, the time pedestrians spend waiting to cross and crossing the road, vehicle speed and any improvement in accessibility as a result of providing the crossing.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Pedestrian Crossing Assessment Method and CostsReport 5 pages DownloadRead as text
PDF
Pedestrian crossings Appendix AAppendix 1 pages Download

At this meeting

Whole meeting

On this subject at Rotherham

Search all
  1. Pedestrian Crossing Assessment Method and CostsThis decision
  2. Fenton Road, Greasbrough - Petition Requesting a Controlled Pedestrian CrossingDecided
  3. Fenton Road, Bradgate - Proposed Controlled Pedestrian Crossing and Cycle Improvement SchemeNoted
  4. A630 Rotherham to Dalton - Pedestrian Crossing AmendmentsDecided
  5. Application for realignment and dual carriageway improvements to the A57, including controlled pedestrian crossings, and roundabout at Todwick crossroads at land at Sheffield Road, Todwick for RMBC (Design and Engineering Service) (RB2011/0628)Approved
  6. Proposed Pedestrian Crossing on Worksop RoadDeferred

More from Rotherham The Former Regeneration Scrutiny Panel

All decisions
MeetingDecisionOutcome
23 Mar 2011 Minutes of the previous meeting of the Regeneration Scrutiny Panel held on 23rd February, 2011Resolved :- That the minutes be approved as a correct record. Approved Open
23 Mar 2011 Road Safety Education, Training and Publicity updateResolved :- (1) That the Senior Engineer be congratulated for his informative report and concise presentation. (2) Th... Noted Open
23 Mar 2011 Environment & Development Services Performance Report 3rd Quarter 2010 - 2011- That the content of the report be noted. Noted Open
23 Mar 2011 Minutes of the Performance and Scrutiny Overview Committee- That the content of the minutes be noted. Noted Open
23 Mar 2011 Minutes of meetings of the Cabinet Member for Town CentresResolved :- That the content of the minutes be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies