Resolved :- (1) That detailed design be undertaken and that the scheme be implemented in the 2010/ 11 financial year. (2) That the footways shown in blue on the attached Drawing No. 126/17/TT127 be removed under the power conferred by section 66 (4) of the Highways Act 1980 and constructed as a cycle track under the power conferred by section 65 (1) of the same Act.
Word for word from the decision Rotherham published for this meeting.Source: moderngov.rotherham.gov.uk
Report to Regeneration and Environment (to, 3 pages
Recommendations
It is recommended Cabinet Member resolve that:
i) detailed design is undertaken and that the scheme be implemented in the 2010/ 11 financial year.
ii) the footways shown in blue on the attached drawing number 126/17/TT127 be removed under the power conferred by section 66 (4) of the Highways Act 1980 and constructed as a cycle track under the power conferred by section 65 (1) of the same act.
Created by Neevia Document Converter trial version http://www.neevia.com Created by Neevia Document Converter trial version Proposals and Details
The large volume and speeds of vehicles negotiating Mushroom roundabout creates an uncomfortable environment for less experienced cyclists to ride around the roundabout on the carriageway. This can create a barrier to cyclists when trying to access local facilities and services.
Detailed design is currently being undertaken to signalise Mushroom Roundabout. This scheme will include toucan-crossing facilities on all arms of the roundabout, allowing both pedestrians and cyclists to cross the A6123 and A630. It is therefore proposed to change the legal status of the footways surrounding the roundabout to shared use, which legally permits cyclists and pedestrians to use the footway. This will allow cyclists to ride on the footway around the roundabout and use the toucan- crossing facilities provided.
Where possible, it is proposed to widen the footways to 3m, this is in accordance with the suggested width for shared use footways in the Department for Transport’s Cycle Infrastructure Design guidance. Where it is not possible to widen the footway, these widths will be retained at a minimum width of 2m.
Please find attached drawing number 126/17/TT127 displaying the proposed extents of the shared use footway.
8. Finance
This scheme is estimated to cost £ 75, 000 and will form part of the A630 Rotherham to Thrybergh Smart Route Proposed Improvements which have been included in the LTP strategic fund programme, and the South Yorkshire Passenger transport Executive’s Programme.
9. Risks and Uncertainties
Failure to provide the shared use facilities may reduce the benefits of the proposed crossings and will reduce local accessibility.
10. Policy and Performance Agenda Implications
This scheme will improve sustainable access, for local residents in regeneration areas to local facilities and services such as shops, supermarkets, bus stops and employment destinations, such as Eastwood Trading Estate and Corus. This will be achieved by extending the current cycle network in the local area and providing improved crossing opportunities of major roads for pedestrians and cyclists. This is in line with the Accessibility Planning shared priority within the Local Transport Plan.
11. Background Papers and Consultation
As part of the local Accessibility Planning process for Dalton and East Herringthorpe, (which also linked into the HMR master planning process for this area), a workshop was held with members of the local community in the summer of 2008 to identify accessibility issues and barriers to accessing facilities and
Created by Neevia Document Converter trial version http://www.neevia.com services. Mushroom roundabout was seen as a major barrier to pedestrians and cyclists, particularly across Aldwalke Lane, as there are currently no crossing facilities on this arm. The roundabout was also seen as dangerous to use by cyclists.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Opening of offers and e-tenders- That the action of the Cabinet Member on 31 st May, 2011 in opening offers and e-tenders for the following be recor...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.