Resolved
Resolved :- That the proposed policy for the management of salt bins be agreed.
Regeneration and Environment (to agreed this item on Tuesday 21 June 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved :- That the proposed policy for the management of salt bins be agreed.
The report summarises how Streetpride salt bins are provided and maintained and sets out proposals to change the way they are managed. The proposed salt bin policy is attached in Appendix A.
That the proposed policy for the management of salt bins is agreed. 7. Proposals and Details
Streetpride currently provides salt bins at known and anticipated trouble spots off the precautionary salting network and at very steep locations on the salting routes. A risk assessment is undertaken at sites where a salt bin has been requested although the current policy does not define specific criteria for this assessment.
A review of Winter Service has been undertaken following the experiences of the severe weather between December 2009 and March 2010. The provision and management of salt bins formed part of this review.
The new policy defines six specific criteria that will need to be assessed for each salt bin application. For a bin to be provided the proposed site must meet one or more of these. The new criteria are:
• Gradients steeper than 1 in 10 • Approaches to junctions that are on an incline • Sharp bends • Sites that are sheltered from sunlight for prolonged periods • Heavily pedestrianised areas and footways such as town centres and busy shopping areas • Locations that are commonly used by vulnerable users
Each bin will remain on site throughout the year and not be collected and returned to the depot at the end of the winter season as in previous years.
The savings produced by not taking in bins are proposed to be used to fund the provision of additional bins meeting the criteria up to a maximum of twenty five new bins per annum (currently 314). Salt bins will not be provided for use on unadopted highways, private properties, residential parking areas and garage sites and should a bin become misused or vandalised then it will be removed.
Any sites meeting the criteria but not able to be funded will be reconsidered for future years.
8. Finance
Winter Service is financed from the Streetpride Revenue budget.
9. Risks and Uncertainties
During the severe weather of the 2009/ 2010 winter season we received an unprecedented number of salt bin requests over this period. It is extremely difficult to predict how many salt bin requests we will receive each year and therefore how many extra bins we will need to provide in the future. 10. Policy and Performance Agenda Implications
Rotherham Safe – Winter services are designed to meet the legal duty to ensure, so far is reasonably practicable, that the safe passage along a highway is not endangered by snow or ice.
11. Background Papers and Consultation
Copy of proposed salt bin policy is attached to the report.
12. Contact Name: Neil Ayrton, Streetpride UKPMS Engineer, ext 22826, [email protected] APPENDIX A
Salt Bin Policy
Salt bins are provided and filled before the start of the winter season and they are to remain on site throughout the year. They are provided and maintained for "self-help" so that highway users can treat adopted roads and footways themselves. The siting of a salt bin is dependant upon there being a suitable location available which does not obstruct pedestrians.
Sites for salt bin provision will meet one or more of the following:
• Gradients steeper than 1 in 10 • Approaches to junctions that are on an incline • Sharp bends • Sites that are sheltered from sunlight for prolonged periods • Heavily pedestrianised areas and footways such as town centres and busy shopping areas • Locations that are commonly used by vulnerable users
Where salt bins are not provided
Salt bins are not provided for use on unadopted highways, private properties and any residential parking areas or garage sites.
Removal of salt bins
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Salt Bin PolicyReport | 4 pages | DownloadRead as text |
Follow Regeneration and Environment (to at Rotherham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Jun 2011 | Duke of Norfolk estate - Proposed No Waiting At Any Time RestrictionsResolved :- (1) That the proposal as currently advertised be implemented and then monitored for 2 months. (2) That th... | Decided | Open |
| 21 Jun 2011 | Minutes of a meeting of the Local Development Framework Members' Steering Group held on 15th April, 2011Resolved :- That the content of the minutes be noted. | Noted | Open |
| 21 Jun 2011 | Opening of offers and e-tenders- That the action of the Cabinet Member on 31 st May, 2011 in opening offers and e-tenders for the following be recor... | Decided | Open |
| 21 Jun 2011 | Minutes of a meeting of the Transport Liaison Group held on 16th March, 2011Resolved :- That the contents of the minutes be noted. | Noted | Open |
| 21 Jun 2011 | Petition requesting re-surfacing of carriageway on Chapel Walk, RawmarshResolved :- That the lead petitioner be informed that resurfacing of Chapel Walk, Rawmarsh , will be assessed for pri... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.