Resolved
Resolved :- That the attached programme of work for the capital funded projects as part of the LTP Maintenance Programme and the Revenue programme be approved.
Regeneration and Environment (to approved this item on Tuesday 21 June 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved :- That the attached programme of work for the capital funded projects as part of the LTP Maintenance Programme and the Revenue programme be approved.
ROTHERHAM BOROUGH COUNCIL – REPORT TO MEMBERS
1. Meeting: REGENERATION AND ENVIRONMENT
2. Date: 4 April 2011
3. Title: HIGHWAYS MAINTENANCE SCHEMES PROGRAMME 2011/2012 4. Directorate: ENVIRONMENT AND DEVELOPMENT SERVICES
5. Summary The report outlines the proposed programme of works to utilise the LTP Highways Maintenance Capital allocation received from the Department for Transport (DfT), the Councils Revenue Highway Maintenance Scheme allocation and the Revenue Surface Treatment allocation.
6. Recommendations To approve the attached programme of work for the Capital funded projects as part of the LTP Maintenance Programme and note the Revenue programme. 7. Proposals and Details In line with the Rotherham Highway Asset Management Plan (HAMP) an advanced programme of works has been developed and the programmes proposed for 2011/2012 are contained in the following appendices. • LTP Schemes. • Revenue Schemes. • Revenue Surface Treatments.
8. Finance The programmes attached are based on the following: Programme Funding Allocation LTP Schemes LTP Highways £2,080,000 (Appendix 1) Maintenance Capital allocation from DfT. Revenue Schemes Rotherham Revenue £521,565 (Appendix 2) Highway Maintenance Schemes budget. Revenue Surface Treatments Rotherham Revenue £282,928 (Appendix 3) Highway Surface Treatment budget.
The LTP allocation has been confirmed and the Revenue allocations have been based on 2010/2011 allocation allowing a cash standstill for 2011/2012.
9. Risks and Uncertainties The proposed programmes of work are based on assumed allocations and will be subject to review as and when allocations are confirmed. The programmes may also be affected by other influences such as: • Statutory Undertakers works. • Other Council operations. • Scheme out turn costs. • Winter weather damage. • Treatment changes.
10. Policy and Performance Agenda Implications The draft Corporate Plan indicates a commitment to make sure roads and footpaths meet at least national average standards with an outcome for safe and well maintained roads.
11. Background Papers and Consultation Not applicable.
Contact Name : Stephen D Finley, Network Senior Engineer, Streetpride, Tel. ext. 2293, [email protected]
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Highways Maintenance Schemes Programme 2011/2012Report | 2 pages | DownloadRead as text |
PDF |
Item 3: Appendix 1Appendix | 2 pages | Download |
PDF |
Item 3: Appendix 3Appendix | 2 pages | Download |
PDF |
Item 3- Appendix 2Appendix | 1 pages | Download |
Follow Regeneration and Environment (to at Rotherham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Jun 2011 | Duke of Norfolk estate - Proposed No Waiting At Any Time RestrictionsResolved :- (1) That the proposal as currently advertised be implemented and then monitored for 2 months. (2) That th... | Decided | Open |
| 21 Jun 2011 | Minutes of a meeting of the Local Development Framework Members' Steering Group held on 15th April, 2011Resolved :- That the content of the minutes be noted. | Noted | Open |
| 21 Jun 2011 | Opening of offers and e-tenders- That the action of the Cabinet Member on 31 st May, 2011 in opening offers and e-tenders for the following be recor... | Decided | Open |
| 21 Jun 2011 | Minutes of a meeting of the Transport Liaison Group held on 16th March, 2011Resolved :- That the contents of the minutes be noted. | Noted | Open |
| 21 Jun 2011 | Petition requesting re-surfacing of carriageway on Chapel Walk, RawmarshResolved :- That the lead petitioner be informed that resurfacing of Chapel Walk, Rawmarsh , will be assessed for pri... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.