- (1) That approval be given to the revised layout in accordance with Drawing Number 122/A57(T).51A/DM7 attached as Appendix A to the submitted report, which replaces the previously proposed underpass with at-grade signalised crossing facilities, and provides for a 50mph speed limit. (2) That the Secretary of State be requested to modify the Side Roads Order entitled ‘The Rotherham Borough Council (A57 Worksop Road – Sheffield Road Improvement M1 Junction 31 to Todwick Crossroads)(Classified Road)(Side Roads) Order 2009’ to accommodate the changes to the scheme, subject to confirmation of the Order by the Secretary of State.
Word for word from the decision Rotherham published for this meeting.Source: moderngov.rotherham.gov.uk
Report to Regeneration and Environment (to, 3 pages
Summary
The report details the revised scheme proposals for the A57 Worksop Road / Sheffield Road Major Highway Scheme, and the subsequent required amendments to the associated Side Roads Order following the Department for Transport’s (DfT) decision to continue its support for the project. It seeks to gain Cabinet Member’s approval to replace the previously proposed underpass, near to the junction of Goosecarr Lane with at-grade signalised crossing facilities, support the proposal to promote a 50mph speed limit on the new highway and request the Secretary of State to amend the Side Roads Order entitled ‘The Rotherham Borough Council (A57 Worksop Road – Sheffield Road Improvement M1 Junction 31 to Todwick Crossroads)(Classified Road)(Side Roads) Order 2009’ in order that the revised scheme may be implemented.
Recommendation
i) Cabinet Member approves the revised layout in accordance with drawing number 122/A57(T).51A/DM7 attached as Appendix A, which replaces the previously proposed underpass with at-grade signalised crossing facilities, and provides for a 50mph speed limit.
ii) Cabinet Member requests the Secretary of State to modify the Side Roads Order entitled ‘The Rotherham Borough Council (A57 Worksop Road – Sheffield Road Improvement M1 Junction 31 to Todwick Crossroads)(Classified Road)(Side Roads) Order 2009’ to accommodate the changes to the scheme, subject to confirmation of the Order by the Secretary of State. 7. Proposals and Details
Following the Comprehensive Spending Review, in late October 2010 the A57 scheme was confirmed as being one of only ten schemes nationally, and the only scheme in South Yorkshire, that the DfT had identified within a ‘Supported Pool’ of major schemes.
The DfT required the Council to undertake a scoping review of the scheme in order to reduce costs of scheme delivery before submitting an offer for funding to the DfT by the end of 2010.
On 15 December 2010 Cabinet approved the submission of a ‘best and final offer’ to the DfT for the implementation of an amended A57 (M1 Junction 31 to Todwick Crossroads) major highway improvement scheme. (Minute Number C134 refers)
The DfT further contacted the Council to seek an additional local contribution of £900,000, which was required to ensure continued support for the scheme. Cabinet Member resolved to approve the increase to the local contribution at the meeting held on 24 January 2011. (Minute Number G97 refers.)
Previously the scheme provided for a dual carriageway designed for the National Speed Limit with a subway to the west of the junction with Goosecarr Lane. In order to reduce costs and satisfy the DfT’s requirements, the scheme was re-scoped. This reduction in scope includes the retention of a dual carriageway scheme designed for a 50mph speed limit including an at-grade signalised crossing to replace the subway. This reduction in scope has now been approved by the DfT and is accepted with regard to their funding allocations, as it has been demonstrated the revised scheme continues to offer good value for money.
A revised planning permission is currently being sought in order to address the changes to the scheme design. Subject to a satisfactory outcome with regard to the Planning Process, the scheme is likely to proceed to public inquiry in autumn 2011 to consider objections made through the Compulsory Purchase and Side Roads Orders procedures.
8. Finance
All financial considerations were considered by the Cabinet Member at the meeting of 24 January 2011. (Minute Number G97 refers)
9. Risks and Uncertainties
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Opening of offers and e-tenders- That the action of the Cabinet Member on 31 st May, 2011 in opening offers and e-tenders for the following be recor...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.