Resolved
Resolved :- That the inclusion of Swinton Community School, St. Pius X Catholic High, Oakwood Technology College, Wath Victoria Junior and Infant School in the submission to the Department for Education be approved.
Culture and Tourism approved this item on Tuesday 4 October 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved :- That the inclusion of Swinton Community School, St. Pius X Catholic High, Oakwood Technology College, Wath Victoria Junior and Infant School in the submission to the Department for Education be approved.
The Department for Education (DfE) announced on the 19th July a new school building programme called the Priority School Building Programme (PSBP). The programme is intended to address those schools whose buildings are in the worst condition.
It is anticipated the programme will cover the equivalent of building or rebuilding approximately 100 secondary schools. However the programme is not limited to secondary schools; it will also include primary and special schools and sixth form colleges.
Local Authorities are responsible for co-ordinating and submitting applications from all maintained schools and voluntary aided and controlled schools. Academies can either be included in the LA submission or apply on their own behalf.
The deadline for submission is the 14th October 2011. A decision on applications is expected in December 2011.
• That support is given for the inclusion of Swinton Community School, St. Pius X Catholic High, Oakwood Technology College, Wath Victoria Junior and Infant School in the submission to the DfE. 7. Proposals and Details:
Local Authorities and schools who access the PSBP must accept that they will be part of a long term private finance arrangement (Approximately 27 years) where building maintenance and soft services (e.g. cleaning, pest control, caretaking, grounds maintenance) will be provided by a third party.
Edibility
Schools which are put forward to the scheme must pass a number of criteria;
• The schools should have received no major investment in the last 15 years. • The programme is only suitable to schools which have to be substantially rebuilt. Extensions to current schools would not eligible for this programme. • There should be a sufficient long term pupil demand for the school. • Schools must demonstrate that they are in a poor condition. The application form will calculate whether the cost of addressing the current condition of the school will exceed 30% of the notional rebuilding cost. For example if it would cost £10 million to rebuild a school it must have £3 million of priority condition work outstanding.
Determination of Schools for Consideration
It is clear that the secondary schools which are not part of the current Rotherham School’s PFI contract and were awaiting investment from the Building Schools for the Future (BSF) programme have significant condition priorities. Those schools were;
BSF Phase 1 Aston Academy Oakwood Technology College Swinton Community School St. Pius Catholic High
BSF Phase 2 Dinnington Comprehensive Brinsworth Academy Rawmarsh Community School St. Bernard’s Catholic High Wales Academy
In the primary school sector, the next school identified in the Primary Capital Programme is Wath Victoria Primary School. Prioritisation of Schools
Using the knowledge gained through BSF, the Asset Management Plan (AMP) and the time and cost constraints of undertaking the condition surveys, it was decided that the following schools would be surveyed to determine whether they exceeded the 30% of notional build cost criteria;
• Swinton Community School • St. Pius X Catholic High School • Oakwood Technology College • Dinnington Comprehensive • Wath Victoria Junior and Infant School
Table 1 below indicates the results of the condition surveys of the schools together with an analysis to determine if they reached the required target. The condition surveys determine what element of the building requires work and then how much it would cost to carry out that work;
Table 1
School Condition Survey Notional Build Cost Figure Swinton £3,973,950 39.73% St. Pius X £2,121,633 30.30% Oakwood £4,544,050 43.27% Dinnington £1,964,413 14.44% Wath Victoria £712,168 41.89%
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Priority School Building Programme: Submission to Department for EducationReport | 5 pages | DownloadRead as text |
Follow Culture and Tourism at Rotherham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Apr 2014 | Minutes of the previous meetings held on 18th and 25th March, 2014.- That the minutes of the previous meetings be agreed as accurate records. | Agreed | Open |
| 22 Apr 2014 | Date and time of the next meeting: -- That the next meeting of the Cabinet Member for Culture and Tourism take place on Tuesday 17 th June, 2014, to star... | Decided | Open |
| 25 Mar 2014 | Minutes of the previous meeting held on 18th February, 2014Resolved :- That the minutes of the previous meeting be approved as a correct record. | Approved | Open |
| 25 Mar 2014 | Tour de France - Communications PlanResolved :- That the details of the communications plan be noted. | Noted | Open |
| 25 Mar 2014 | Customer and Cultural Services - Fees and Charges 2014-2015Resolved :- (1) That the report be received and its contents noted. (2) That, subject to resolution (3) below, the re... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.