Resolved :- (1) T hat the report be received and the contents noted. (2) That an exemption from Standing Order 48.2.1 (requirement to obtain at least 3 written quotations for contracts with an estimated value of between £50K and £500K) be approved. (3) That the supplier 3M carry out the Radio Frequency Identification implementation at the new Library at Riverside House.
Word for word from the decision Rotherham published for this meeting.Source: moderngov.rotherham.gov.uk
This paper provides a progress update on the proposed implementation of Radio Frequency Identification (RFID) technology required to deliver and improve library services in Riverside House.
Recommendations
a) That the Cabinet Member notes the progress to date
b) That the Cabinet Member gives approval to enable an exemption from Standing Order 48.2.1 (requirement to obtain at least 3 written quotations for contracts with an estimated value of between £50K and £500K).
c) That the supplier - 3M are approved to carry out the RFID implementation at the new Library at Riverside House
Page 1 7. Proposals and Details
The relocation of the Central Library to Riverside House in 2012 presents us with the ideal opportunity to implement RFID technology, which will help to improve library processes, customer services and also push forward the Library & Information Service’s ‘new ways of working’ agenda.
The proposal for implementation (including all financial arrangements) was approved at the Corporate ICT and Information Governance Board meeting on 26 September 2011 (‘Technology upgrade in the new Central Library, Riverside House’ - Option 2: Implement RFID technology to replace existing barcode system).
Reasons for Request
We are requesting an exemption from Standing Order 48.2.1 so that we can award the RFID contract to one of our existing library suppliers, 3M, instead of going through a formal tendering process with 3 suppliers (although it should be noted that we have discussed our requirements with another supplier). On the evidence we have seen, 3M remain our preferred supplier as they offer certain technologies not currently available from other providers (e.g. the mobile workstations and printers for more effective on- the-spot enquiry work).
The financials in the Corporate ICT and Information Governance Board meeting paper were based on a quote for implementation from our current supplier, 3M, after extensive consultation on our business requirements. This was compared with the costings submitted by other suppliers in the ESPO Contract 350 – RFID for Libraries (Equipment & Tags).
3M also provide our current barcode self service units, and therefore would provide us with the most cost effective option for upgrading these units to RFID in the future. Changing to another RFID supplier would incur extra charges relating to equipment and configurations of existing systems.
As with all new technology implementations, time is of the essence, with RFID documentation recommending a 6 month implementation process (including staff training and familiarisation). Current timescales state that the new Library will open in April 2012, so it is crucial the project begins as soon as possible; a tendering process would delay the start of the project even further.
Other elements of the implementation are currently being held up: we need to order RFID tags from the library book suppliers, begin the process of re- tagging all current stock in the Central Library and instruct suppliers to RFID-tag new stock. None of this is possible until a RFID supplier is appointed.
Other partners also require adequate notice of our intention to implement RFID so that they can make changes to our system configurations (e.g. Capita, the providers of the library management system.)
Page 2 8. Financials
The financials in the Corporate ICT and Information Governance Board meeting paper were based on a quote for implementation from our current supplier, 3M, after extensive consultation on our business requirements. On the evidence we have seen they are our preferred supplier as they offer certain technologies not currently available from other providers (e.g. the mobile workstations and printers for more effective on-the-spot enquiry work).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Date and time of the next meeting: -- That the next meeting of the Cabinet Member for Culture and Tourism take place on Tuesday 17 th June, 2014, to star...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.