Rotherham Metropolitan Borough Council

Maltby Academy - Procurement of Maltby Academy Capital Project

Noted Committee 1 paper

Town Centres, Economic Growth and Prosperity (from July, 2011 to May, 2012) noted this item on Wednesday 2 November 2011. Below is the council's own wording, with the papers it was decided on.

Item58

Resolved

Resolved :- That the update on the Procurement of the Maltby Academy Project and the Local Authority’s role as the Procuring Agent be noted.
Word for word from the decision Rotherham published for this meeting. Source: moderngov.rotherham.gov.uk

Follow this further

Built from Rotherham's papers

What the report saysPro

Report to Town Centres, Economic Growth and Prosperity (from July, 2011 to May, 2012), 7 pages

Summary

As part of the Rotherham BSF programme of work there were plans to co-locate Maltby Lilly Hall Primary School with Maltby Hilltop Special School and the Maltby Academy as part of a campus, which were to be sited on the existing Academy site.

Following the cessation of the BSF programme on the 5th July 2010, the Maltby Academy development was placed on a list of academy projects for further discussion. The Authority continued to work with the Academy Sponsor, the Department for Education (DfE) and their agent the Partnership for Schools (PfS) on the development and scale of the Academy project.

On the 20th December 2010, Maltby Academy received written confirmation from the Parliamentary Undersecretary of State for Schools, Lord Hill, that the Academy had received a capital allocation of £11,101,823 to develop Maltby Academy using the PfS Contractors Framework to procure the capital works.

This report provides an update on the procurement of the Maltby Academy project and the Authorities role as the Procuring Agent on the Project.

Recommendations

It is recommended that:

The Cabinet Member notes the update on the Procurement of the Maltby Academy Project and the Authorities role as the Procuring Agent.. 7. Proposals and Details:

Background

Following the cessation of the BSF programme on the 5th July 2010, the Maltby Academy development was placed on a list of academy projects for further discussion. The Authority continued to work with the Academy Sponsor, the Department for Education (DfE) and their agent the Partnership for Schools (PfS) on the development and scale of the Academy project.

On the 20th December 2010, Maltby Academy received written confirmation from the Parliamentary Undersecretary of State for Schools, Lord Hill, that the Academy had received a capital allocation of £11,101,823 to develop Maltby Academy using the PfS Contractors Framework to procure the capital works.

Procurement

The PfS confirmed they expected the Academy to use the PfS Academies Contractors Framework to procure the Academy project and that they had re- negotiated the rates with the Contractors on the framework.

The project would be procured via a design and build competition.

Maltby Academy geographically comes under the PfS Academies Contractors framework for the northern region, (North West, North East, Yorkshire and the Humber, East Midlands, West Midlands). The 12 contractors are:

Balfour Beatty Construction Ltd BAM Construction Ltd Bovis Lend Lease Ltd Carillion Construction Ltd Clugston Construction Interserve Project Services Ltd Kier Regional Ltd Shepherd Construction Sir Robert McAlpine Ltd Vinci Construction UK Wates Construction Ltd Willmott Dixon Construction Ltd

The Framework Agreement provides the basis of the participation of the 12 contractors on individual schemes through a mini-competition call-off process initiated by the Framework User, in the Maltby Academy project it would be Rotherham MBC as the Authority would be the procuring agent and would sign the contract with the PfS Academy Contractor.

The PfS provide the funding allocation model – the £11.1m budget. The framework contractor provides the design solution via the Design and Build contract. The procurement delivery time table is over is over a period of 28 weeks and illustrated below:

12-16 weeks Funding Agreement Feasibility Study

Preliminary 2 Weeks Invitation to tender (PTT)

From 12 to 2 framework contractors

Invitation to 6 - 8 Weeks Tender (ITT) Maximum 28 weeks

2 Weeks Evaluation

Selected Panel Member

Final Business 16 weeks Case/Contract Award

From the above diagram the stages of procurement are as follows:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Maltby Academy: Procurement of Maltby Academy Capital ProjectReport 7 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Rotherham

Search all
  1. Maltby Academy - Procurement of Maltby Academy Capital ProjectThis decision
  2. Visit of Inspection - Proposed extensions, alteration and part demolition of existing buildings including alterations to car park and external areas at Maltby Academy Ltd., Braithwell Road, Maltby (RB2012/0543)Approved
  3. Proposal to Close the Maltby Community School and replace it by opening a new Academy on the School SiteNoted
  4. Proposal to Open the Maltby Academy, to Amalgamate Two Primary Schools and to Co-locate a Special SchoolNoted
  5. Expression of Interest for the Proposed Maltby AcademyAgreed

More from Rotherham Town Centres, Economic Growth and Prosperity (from July, 2011 to May, 2012)

All decisions
MeetingDecisionOutcome
28 May 2012 Proposed cycling improvements in and towards Rotherham town centre.- (1) That the Director of Planning and Regeneration, in accordance with delegated powers, promote a Traffic Regulati... Decided Open
28 May 2012 Proposed 20 miles per hour zone within Rotherham Town Centre.- (1) That detailed design and consultation on the introduction of a 20 miles per hour zone in the Rotherham Town Cen... Decided Open
28 May 2012 Petition relating to the Withdrawal of Free Transport Assistance to Aston Fence Junior & Infant School and Aston Academy.- (1) That the concerns raised by Orgreave Parish Council be noted. (2) That the decision taken on 23 rd January (Min... Noted Open
28 May 2012 Proposed Temporary Offer of Reduced Parking Charges for Council Employees to Ease Parking Pressure on the Masbrough Area.- (1) That the report be received and its content noted. (2) That the proposal to offer a three month reduced cost pa... Noted Open
23 Apr 2012 Minutes of the Previous Meetings- That the minutes of the previous meetings of the Cabinet Member for Town Centres, Economic Growth and Prosperity be... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies