Town Centres, Economic Growth and Prosperity (from July, 2011 to May, 2012) decided this item on Friday 9 December 2011. Below is the council's own wording, with the papers it was decided on.
Resolved :- (1) That detailed design and consultation be carried out on the proposed scheme as shown on drawing number 126/17/TT168. (2) That, subject to no objections being received to the proposals, that the scheme be implemented during the 2011-2012 financial year. (3) That the scheme be funded from the Local Transport Plan (LTP) Integrated Transport Capital Programme for 2011/12.
Word for word from the decision Rotherham published for this meeting.Source: moderngov.rotherham.gov.uk
Report to Town Centres, Economic Growth and Prosperity (from July, 2011 to May, 2012), 2 pages
Recommendations
Cabinet Member resolves that:
i) Detailed design and consultation be carried out on the proposed scheme as shown on drawing number 126/17/TT168.
ii) Subject to no objections being received to the proposals that the scheme be implemented during the 2011-2012 financial year.
iii) The scheme be funded from the Local Transport Plan (LTP) Integrated Transport Capital Programme for 2011/12.
Page 1 7. Proposals and Details Currently access for pedestrians and cyclists from Brinsworth to the north east of Canklow bidge is limited due to the lack of footway on the north side of A631 Bawtry Road under the bridge and a suitable crossing point. This lack of facilities acts as a barrier to any one wishing to access the frequent bus service, footpaths into the town centre or the Trans Pennine Trail.
A proposal has been developed that would provide a refuge which would assist pedestrians and cyclists to cross Bawtry Road, improving access to the above facilities. Details of this proposal is shown on drawing number 126/17/TT168, which is attached as Appendix A.
The proposed refuge is wide enough to allow a cyclist to wait on it and still allow all vehicles to safely pass. The refuge will also tie into the existing central island and prevent vehicles from turning the wrong way out of the adjacent petrol filling station.
8. Finance The proposed scheme is estimated to cost £25,000
9. Risks and Uncertainties Subject to design and consultation there is a risk that it may not be implemented / finished by end of 11/12 in which case findings will have to be allocated from 12/13 LTP budgets
The design of the refuge will be carefully considered as it is located on the bridge deck. This may require the use of a bolt down refuge and prefabricated kerbs.
10. Policy and Performance Agenda Implication The proposals are in line with objectives set out in the Sheffield City Region Transport Strategy (Local Transport Plan 3), Public Transport, Quality of Life and Safer Roads investment themes.
11. Background Papers and Consultation The South Yorkshire Accident data base, shows that there has been one child pedestrian injury accident in this location during the last five years.
Contact Name: Richard Pardy, Assistant Engineer, Ext. 2959, [email protected]
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Town Centres, Economic Growth and Prosperity (from July, 2011 to May, 2012) at Rotherham and we tell you when its next papers are published, before the meeting rather than after it.
Minutes of the Previous Meetings- That the minutes of the previous meetings of the Cabinet Member for Town Centres, Economic Growth and Prosperity be...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.