A630 Doncaster Road - Oldgate Lane Junction Signalisation and Whinney Hill Bus Lane
ApprovedCommittee2 papers
Town Centres, Economic Growth and Prosperity (from July, 2011 to May, 2012) approved this item on Monday 20 February 2012. Below is the council's own wording, with the papers it was decided on.
- (1) That the scheme be approved for detailed design and appropriate consultations to begin in the 2011/12 financial year. (2) That, subject to consultation responses, the scheme as outlined in the submitted report and appendices, be approved to commence in the 2012/13 financial year. (3) That the scheme be joint funded by the Better Bus Area Bid and the South Yorkshire Local Transport Plan Integrated Transport Programme for 2012/13. 4. That if the Better Bus Area bid was not successful, that the Oldgate Lane signalisation scheme be funded from the South Yorkshire Local Transport Plan Integrated Transport Programme for 2012/13, and additional funding be pursued for the bus lane on Whinney ... view the full minutes text for item 98.
Word for word from the decision Rotherham published for this meeting.Source: moderngov.rotherham.gov.uk
Report to Town Centres, Economic Growth and Prosperity (from July, 2011 to May, 2012)
Recommendations
Cabinet Member is asked to resolve that:
i) The scheme is approved for detail design and the appropriate consultations start in the 2011/12 financial year.
ii) Implementation of the scheme, as shown on drawing number 126/17/TT191-A1, (subject to the outcomes of the consultations) commences in the 2012/2013 financial year.
iii) The scheme be joint funded from the Better Bus Area Bid (if successful) and the South Yorkshire Local Transport Plan Integrated Transport Capital Programme for 2012/13 (RMBC and SYPTE co-funded).
iv) If the Better Bus Area Bid is unsuccessful, that the Oldgate Lane signalisation scheme be funded from the South Yorkshire Local Transport Plan Integrated Transport Capital Programme for 2012/13 (RMBC and SYPTE co-funded) and additional funding is sought for the bus lane. 7. Proposals and Details The A630 Key Route Rotherham to Thrybergh forms a significant part of the main cross county bus service the X78 from Sheffield to Doncaster via Rotherham and the Don Valley. This is one of the most popular bus services in South Yorkshire and accordingly investment on the route has been extensive to date with major infrastructure improvements on Balby Road in Doncaster and the signalisation of Mushroom Roundabout, College Road roundabout and St Ann’s Roundabout in Rotherham. Further route improvements between Rotherham and Meadowhall with improvements to M1 Junction 34(N) and in Sheffield around the Wicker have further improved bus journey times and reliability. This route; A630 is also the main key arterial into Rotherham.
The Dalton area of Rotherham suffers from social deprivation and public transport forms a key part of people’s mobility. The junction of Oldgate Lane and the A630 Doncaster Road suffers significant delays which adversely affects journey times and journey time reliability. The junction also forms an access into one of the major employers in the area; TATA steels at its Aldwarke plant. Queuing traffic in the morning peak on the inbound approach to Rotherham frequently stretches to the top of Whinney Hill and this is caused mainly by the merging of traffic from Oldgate Lane (a minor arm) onto the A630 Doncaster Road. Oldgate Lane also forms part of a scheduled service bus route which similar to the key route suffers poor journey time reliability.
Scheme proposals, as shown on Drawing No.126/17/TT191-A1 (Appendix A):
• Signalise the junction of Doncaster Road, Oldgate Lane and TATA steels access.
This would introduce a control of traffic flows, ensure queues on the A630 are kept to a minimum, address accident issues and improve journey time reliability. Signalising the junction in this manner would include the prohibiting of the left turn from Oldgate Lane to Doncaster Road and the right turn from Oldgate Lane to Doncaster Road in order to facilitate efficient traffic signal timings and allow the provision of pedestrian crossing facilities. Traffic surveys at the junction show that these manoeuvres are virtually redundant with only single figures making these turns in a 12 hour period.
• Implement a full time bus lane on Doncaster Road, Whinney Hill (If the Better Bus Fund Bid is successful)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Town Centres, Economic Growth and Prosperity (from July, 2011 to May, 2012) at Rotherham and we tell you when its next papers are published, before the meeting rather than after it.
Minutes of the Previous Meetings- That the minutes of the previous meetings of the Cabinet Member for Town Centres, Economic Growth and Prosperity be...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.