Resolved
Resolved :- (1) That the report be received and its contents noted. (2) That the approval of the updated 2012/13 to 2014/15 Capital Programme by full Council be noted.
The Former Self Regulation Select Commission noted this item on Thursday 22 November 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved :- (1) That the report be received and its contents noted. (2) That the approval of the updated 2012/13 to 2014/15 Capital Programme by full Council be noted.
The purpose of this report is to provide details of the current forecast outturn for the 2012/13 programme and enable the Council to review the capital programme for the financial years 2013/14 and 2014/15.
Self Regulation Select Commissions is asked to note:-
THE CONTENTS OF THIS REPORT; AND
THE APPROVAL OF THE UPDATED 2012/13 TO 2014/15 CAPITAL PROGRAMME BY FULL COUNCIL. 7 Proposals and Details
7.1Background - The Capital Programme 2012/13 to 2014/15
The budget process that led to the original Capital Programme for 2012/13 to 2014/15 ensured that the Council’s capital investment plans were aligned with its strategic priorities and vision for Rotherham.
In order to maintain that strategic link, and make best use of the capital resources available to the Council, it is important that the programme is kept under regular review and where necessary revisions are made. This programme was initially reviewed in July 2012, following the finalisation of the 2011/12 outturn capital expenditure and financing and has now been the subject of a further review, the results of which are reflected in the Directorate summary table presented below. A detailed analysis of the programme for each Directorate is attached at appendices 1 to 4.
2012/13 2013/14 2014/15 Revised Estimate Estimate Estimate
Directorate £m £m £m Children & 21.186 10.119 3.725 Young People’s Service Environment & 18.624 15.898 7.170 Development Services Neighbourhoods 25.426 32.063 28.984 & Adult Services Resources 10.779 1.275 1.275
TOTAL 76.015 59.355 41.154
7.2Children and Young People’s Services Capital Programme 2012/13 to 2014/15
The revised proposed spend for 2012/13 is £21.186m, with a further £13.844m of investment in the following years of the current programme. The Council has recently been notified of a further £0.208m of unringfenced capital grant funding being allocated to it by the DfE. This funding is intended to help local authorities and their health partners to create better access to short break provision by providing new equipment, adaptations and facilities for disabled children and young people. Proposals on how the funding will be used are currently being worked up.
A copy of the current full programme is attached to this report at Appendix 1. Commentary on the main aspects of the programme and the nature of the spend is given below. Primary Schools
Spend on Primary Schools is expected to be £5.858m in 2012/13, with a further £1.322m of planned spend in 2013/14 to 2014/15. The major investments to note in this area are:
• Work is underway on the Maltby Lilly Hall new school project (£4.000m) which will create six new classrooms together with associated facilities and external play areas. In addition re-roofing work is being carried which also requires the removal of asbestos.
• The Council is providing Wentworth C of E School (£0.228m) with a two storey extension, including disabled toilets, an additional class room, store rooms and other resource facilities.
• Work is continuing on the Thornhill Primary School (£0.831m) extension designed to create Special Educational Needs facilities and a dining room extension to accommodate increased pupil numbers.
• The provision of additional classroom facilities and improved dining room facilities is underway at Flanderwell Primary School (£0.100m) in order to facilitate increased pupil numbers.
• Three new projects have been introduced which will see the installation of modular classrooms at Catcliffe Primary (£0.100m), Treeton C of E (£0.200m) and Aston Hall Junior and Infants (£0.047m) schools to address rising pupil numbers in their respective catchment areas.
Secondary Schools
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Capital Programme Monitoring 2012/13 and Capital Programme Budget 2013/14 to 2014/15Report | 10 pages | DownloadRead as text |
PDF |
Capital monitoring appendices, 17/10/2012 CabinetReport | 8 pages | Download |
Follow The Former Self Regulation Select Commission at Rotherham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 Feb 2015 | Revenue Budget Monitoring for the period ending 31st December 2014Resolved :- That the current forecast outturn and the continuing financial challenge for the Council to deliver a bal... | Noted | Open |
| 19 Feb 2015 | RMBC "Facing the Cuts, Delivering Rotherham's Priorities" 2015/16/2016/17 - Public/Employee Consultation FindingsResolved :- (1) That the headline messages arising from the analysis of the budget consultation be noted. (2) That th... | Noted | Open |
| 19 Feb 2015 | Date and Time of Next MeetingResolved :- That the next meeting of the Self Regulation Select Commission take place on Thursday, 26th March, 2015 a... | Decided | Open |
| 8 Jan 2015 | Minutes of the previous meeting held on 23rd October, 2014Resolved :- (1) That the minutes of the previous meeting held on 23 rd October, 2014 be agreed as a correct record fo... | Agreed | Open |
| 8 Jan 2015 | Corporate Plan OutcomesResolved :- That the Interim Chief Executive be thanked for her explanation on the reason for the delay of the report. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.