- (1) That the cessation of maintenance at the RMBC -owned and managed bowling greens, as outlined within the submitted report, be approved. (2) That invitations be issued to bowling clubs and/or other suitable and interested parties to express an interest in taking over the responsibility for maintenance of affected greens at their own expense.
Word for word from the decision Rotherham published for this meeting.Source: moderngov.rotherham.gov.uk
This report seeks approval, subject to consultation with bowling green users, to cease maintenance of all of the Council’s remaining bowling greens, with the exception of those at Clifton Park, in order to make savings needed to help meet budget targets for 2013/14.
Recommendations
1. That Cabinet Member approves the cessation of maintenance of the following RMBC owned and managed bowling greens
Barkers Park Bradgate Park (x2) Greasbrough Park Maltby Coronation Park Valley Park (x2)
2. That Cabinet Member approves the issue of invitations to bowling clubs or other suitable and interested parties, to express interest in taking over responsibility for maintenance of affected greens at their own expense. 7. Proposals and Details
2013/14 budget savings proposals for EDS include a reduction in the number of crown green bowling greens that RMBC maintain across the Borough, from 11 to 4. This is necessary to achieve a budget savings target of £30,000.
The greens that would be affected are as follows:-
Barkers Park Bradgate Park (x2) Greasbrough Park Maltby Coronation Park Valley Park (x2)
As reported in February 2011 a strategic review of Bowling Green provision was undertaken in December 2010. Consequently, a decision was taken to cease maintenance of 8 Council-owned bowling greens, leaving 12. At Wath upon Dearne, it was proposed that maintenance cease on one of the two greens. However, an agreement was reached with the local bowls club for them to take on responsibility for the maintenance and management of both greens, and thus the total number of Council-owned greens being maintained by the Council fell to 11.
The current proposal would mean that the only Council-run bowling greens available for use would be the 4 greens at Clifton Park. However bowling greens continue to be provided by others, including Parish Councils and CISWO, at various sites around the Borough.
If the proposal is approved the decision would be communicated with all groups / clubs using RMBC operated greens as quickly as possible. Each would be invited to submit expressions of interest should they believe themselves to be in a position to take on responsibility for the maintenance of greens at their own expense, or to pay the full cost of maintenance.
Cessation of maintenance may put staff at risk of redundancy but it will not be possible to determine this until the full extent of fine turf work required from the Council in 2013/14 by external parties is confirmed later this year.
Consultation: If necessary, appropriate consultation will be carried out with Unions and staff. Discussions will take place with relevant user groups.
This has been discussed with the Council’s Community Engagement Officer and the appropriate F1 form and Equality Analysis has been undertaken.
8. Finance
The projected saving from the above proposal is estimated at £30,000. This assumes that seasonal games attendants would no longer be employed at affected sites. The saving would contribute to overall savings that need to be made by the Council in the light of reduced funding from central government. 9. Risks and Uncertainties
There is likely to be considerable public concern at a further loss of bowling greens.
In the event that any other body wishes to take on responsibility for the maintenance of any of the greens, then the Council would not be in a position to make any contribution towards green preparation and continued maintenance after May 2013.
Cessation of maintenance from affected bowling greens will mean that seasonal games attendants are no longer required. This may increase the risk of vandalism and anti-social behaviour at the sites concerned.
10. Policy and Performance Agenda Implications
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Date and time of the next meeting: -- That the next meeting of the Cabinet Member for Culture and Tourism take place on Tuesday 17 th June, 2014, to star...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.