Resolved :- (1) That the report be received and its contents noted. (2) That the specific allocation of funding for Integrated Transport and highways maintenance for 2013/14 including the Local Sustainable Transport Fund and the Better Bus Area Fund be noted. (3) That the principle of the proposed programme of highways capital works, as included in Appendices A, B and C to the report now submitted, be approved as the basis ... view the full minutes text for item 117.
Word for word from the decision Rotherham published for this meeting.Source: moderngov.rotherham.gov.uk
This report outlines the proposed Highways Capital works programme for 2013/14.
Recommendations
That Cabinet Member resolves to: -
(a) note the specific allocation for Integrated Transport and highways maintenance for 2013/14 including the Local Sustainable Transport Fund (LSTF) and Better Bus Area Fund.
(b) Agree the principle of the proposed programme as identified in Appendices A, B and C as the basis for detailed design and implementation during 2013/14.
7. Proposals and Details
This report seeks to outline the proposed areas of work for the forthcoming financial year; 2013/14, that are to be delivered from Department for Transport (DfT) grants. The primary grant funding being the capital funding made available from Central Government for Integrated Transport and maintenance as part of the third Local Transport Plan (LTP3). The table below shows the LTP funding made available across South Yorkshire:
2011/12 2012/13 2013/14 2014/15 £000’s £000’s £000’s £000’s Integrated Transport 11,252 12,002 12,002 16,877 Maintenance 15,932 15,723 9,910(14,959)* 9,206(13,896) * * Note the figure in brackets is the indicative allocation to South Yorkshire prior to Sheffield Council entering into the Private Finance Initiative agreement
As previous reports have outlined central government funding has been considerably reduced in recent years. In the forthcoming year funding for integrated transport has stayed the same as in 2012/13 whilst funding for maintenance activity is reduced; the unbracketed figure to be shared between Barnsley, Doncaster and Rotherham. The Rotherham allocations are: £1,534,000 for integrated transport (IT) and £3,010,000 for maintenance (The maintenance funding is further then divided between highway maintenance, highway structures maintenance and street lighting). In the Governments’ autumn statement local highway authorities were awarded additional funding for highway maintenance, Rotherham received £546,000 for 2013/14 to be split between highway maintenance, structural maintenance and street lighting.
With the confidence of knowing the next 2 years IT funding Rotherham has chosen to bring forward some funding from our 14/15 IT allocation to fund works on the major scheme at the A57. This in effect means the IT allocations for 13/14 and 14/15 are roughly the same, around £1.9 million. The other funding for the A57 major scheme is made up of £500,000 from LTP maintenance grant in 13/14, £2,000,000 RMBC capital funding and £11,300,000 DfT major scheme grant.
As identified in previous reports to Cabinet Member (Council Minute No.G98 of 20 February 2012 refers) the Council with South Yorkshire partners has been successful in securing additional funding in the form of ‘Better Bus Area Fund (BBAF)’ and ‘Local Sustainable Travel Fund (LSTF)’ as with LTP funding these additional grants have to be completed and claimed by March 2015, there is no mechanism to continue works in financial year 2015/16.
Better Bus Area Fund (BBAF), LTP Integrated Transport (IT) and Local Sustainable Travel Fund (LSTF)
Appendix ‘A’ is a summary of the proposed programme of works for Rotherham in 2013/14.
The BBAF is granted to South Yorkshire Passenger Transport Executive rather than South Yorkshire Integrated Transport Authority. Within Rotherham the funding is identified as contributory funding for improvements at Oldgate Lane and Whinney Hill in Dalton the remaining funding being LTP allocations from the Council and South Yorkshire Passenger Transport Executive (PTE). Works are progressing well and completion is expected in August 2013. Once complete the scheme will provide further bus priority on the A630 Doncaster Road between Thrybergh and Mushroom roundabout.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.