Resolved
Resolved :- That the minutes of the previous meeting be approved as a correct record for signature by the Chairman.
Barnsley, Doncaster and Rotherham Joint Waste Board approved this item on Friday 14 June 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved :- That the minutes of the previous meeting be approved as a correct record for signature by the Chairman.
BARNSLEY, DONCASTER AND ROTHERHAM JOINT WASTE BOARD - 15/03/13 8K
BARNSLEY, DONCASTER AND ROTHERHAM JOINT WASTE BOARD 15th March, 2013
Present:- Councillor R. S. Russell (Rotherham MBC) (in the Chair); Councillor R. Miller (Barnsley MBC) and Councillor C. Ransome (Doncaster MBC)
together with:-
David Burton Rotherham MBC Beth Clarke BDR Joint Waste Manager David Finnegan Barnsley MBC Ann Todd Rotherham MBC Gill Gillies Doncaster MBC Steve Noble DEFRA
Apologies for absence were received from Councillor Ali and from [name removed] (Rotherham MBC) and from [name removed] (Barnsley MBC).
D29. DECLARATIONS OF INTEREST
There were no declarations of interest made at this meeting.
D30. MINUTES OF THE PREVIOUS MEETING HELD ON 14TH DECEMBER, 2012
Consideration was given to minutes of the previous meeting of the Barnsley, Doncaster and Rotherham Joint Waste Board, held on 14th December, 2012, were considered.
Resolved:- That the minutes of the previous meeting be approved as a correct record for signature by the Chairman.
D31. BDR MANAGER'S REPORT
The Barnsley, Doncaster and Rotherham Joint Waste Manager submitted a report updating the progress of the following issues:-
(a) details were reported of the recommendations of the Waste Infrastructure Development Programme (WIDP) Contract Management Review; the recommendations focused on knowledge management, including the completion of the contract manuals and work instructions, communications between the collection managers and the BDR PFI team and reviewing the organisational structure of the team to ensure it remains fit for purpose in the various phases of the contract. The Department of Environment, Food and Rural Affairs is confident about the robust quality of the contract.
Agreed :- the Joint Waste Board expressed its preference for the partnership approach to the management of the contract. 9K BARNSLEY, DONCASTER AND ROTHERHAM JOINT WASTE BOARD - 15/03/13
(b) The Bolton Road facility – the permit is deemed as being satisfactory, the Judicial Review period having ended on 6th January 2013; Section 73 applications will be submitted in order to obtain planning consent for minor material amendments to the application, as a consequence of detailed design work.
(c) Good progress overall continues to be made with the Ferrybridge site; the judicial review period for the S.S.E. Environmental Permit has now ended
(d) Health and Safety – there were no issues of concern to report;
(e) an information sharing protocol has been drafted for the three local authorities;
(f) Finance – operational management costs are projected to be within budget for the current, 2012/13, financial year;
(g) Communications – the ground-breaking photo-call with Elected Members, on Monday, 18th February, 2013, had been very well publicised, some minor inaccuracies in the press reporting had now been corrected; discussions continued with the liaison group to provide information about traffic issues around the Bolton Road facility; the importance of providing regular information bulletins was acknowledged; details would shortly be available about the forthcoming project partnership awards for the Best Waste Project;
(h) Preparation of the Contract Manuals is continuing.
Resolved:- That the report be received and its contents noted.
D32. RISK REGISTER
The Barnsley, Doncaster and Rotherham Joint Waste Board considered the updated Waste PFI transition phase risk register. It was noted that the ‘Permitting Delay’ risk is now closed, as both the Bolton Road and the Ferrybridge sites have been granted permits.
The Joint Waste Board agreed that the budget and financial risks should be included within the register, as a consequence of the severe pressures upon central Government and local authority finances.
Resolved:- That the updated information on the risk register be received.
D33. MEETING DATES
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Minutes of the previous meeting held on 15th March, 2013.Minutes | 3 pages | DownloadRead as text |
Follow Barnsley, Doncaster and Rotherham Joint Waste Board at Rotherham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Feb 2026 | Minutes of the previous meeting held on 7 October 2025 (copy attached) and any matters arising- That the minutes of the meeting held on 7 October 2025, be approved as a true and correct record of the proceedings. | Approved | Open |
| 3 Feb 2026 | Any Other Business- The next meeting of the Barnsley, Doncaster and Rotherham Joint Waste Board will be held on Monday 6 July 2026, com... | Decided | Open |
| 7 Oct 2025 | Minutes of the previous meeting held on 24 June 2025 (copy attached)- That the minutes of the meeting held on 24 June 2025, be approved as a true and correct record of the proceedings. | Approved | Open |
| 7 Oct 2025 | Date and Time of Next Meeting- The next meeting of the Barnsley, Doncaster and Rotherham Joint Waste Board will be held on Tuesday 3 February 2026... | Decided | Open |
| 24 Jun 2025 | Appointment of Chair and Joint Waste Board Update- 1. That Councillor James Higginbotham of Barnsley MBC be appointed as Chair of the Barnsley, Doncaster and Rotherha... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.