External Stock Condition Survey of HRA Dwellings

Noted Committee 1 paper

Safe and Attractive Neighbourhoods (August 2010-February 2015) noted this item on Monday 15 July 2013. Below is the council's own wording, with the papers it was decided on.

Item24

Resolved

- (1) That the report be received and its contents noted. (2) That the requisite funding be allocated for the external stock condition survey, as described in the report now submitted, from the Housing Revenue Account reserve, as identified by the Director of Finance. (3) That, due to the nature of the requirements and the timescales within which this survey and data were required, external resources be engaged for delivery of the survey.
Word for word from the decision Rotherham published for this meeting. Source: moderngov.rotherham.gov.uk

Follow this further

Built from Rotherham's papers

What the report saysPro

Report to Safe and Attractive Neighbourhoods (August 2010-February 2015), 5 pages

Summary

This report outlines the urgent need to commission a 10% external stock condition survey to: • Inform the 2014/15 30 Year HRA Business Plan refresh and the subsequent budget. • Provide meaningful data for input into the new Keystone Asset Management System • Inform the development of the Housing Investment Strategy • Aid planning of works packages and reduce risk around cost due to in adequate and inaccurate information.

The report considers options and costs for delivery of this work looking at appropriate timescales, capacity and skills required. The basis of the report has been developed with the NAS Finance Team and the Strategic Asset Management team.

Recommendations

That Cabinet Member approve:

Requisite funding from the HRA reserve as identified by the finance team.

That due to the nature of the requirments and the timescales within which this data is required external resources is engaged for delivery. 7. Proposals and details

Background

The Strategic Asset Management team within NAS are being requested by NAS Finance Team to provide information to support a refresh of the HRA 30 year Business Plan.

The implementation of Housing Revenue Account (HRA) Self-Financing, from April 2012 transferred all risks from the DCLG to the Council in respect of Council houses. Changes in inflation, local rent policy, interest rates and investment and debt management decisions, will impact on the financial viability of the Business Plan. Robust, proactive management of all aspects of the Plan will be essential throughout the 30 year period.

Self-Financing requires long-term planning and asset management. Major investment decisions will be made based upon the forecast resources available with the Business Plan. It is therefore imperative that the key data used to formulate the Plan is based upon sound knowledge, which is robustly challenged, monitored and updated on an on-going basis.

The Business Plan assumption for the 30 year investment requirements on current stock, to maintain them in line with the Decent Homes Standard, is currently informed from the APEX asset management system. Any inaccurate, incomplete, duplicate or missing property or survey data will have an impact on the viability of the Business Plan.

To satisfy the need to ensure that the business plan is based on sound up-to-date information the data needs to be revised in order to inform future investment requirements, and to ensure that adequate budgets are set for 2014/15. Following the first year of self- financing it is timely to undertake a full refresh to ensure that assumptions made are still relevant.

The Council’s information is held on the Apex Asset Database; set up by the previous ALMO organisation 8 years ago and a number of issues have emerged: • The system was only partially commissioned • Previous stock condition surveys used to populate the database were not quality controlled and have been found lacking particularly in respect of external works surveys. Internal data is somewhat more robust due to the level of activity carried out and recorded during Decent Homes Works. • The available core data was not fully transferred into Apex • Investment made since the database set up has not been systematically fed back into Apex

As a result, the information held in Apex in respect of external stock condition is fundamentally flawed and cannot be relied upon to: • inform the 30 year Business Plan which is due for refresh • guarantee the quality of data being transferred to Keystone/Civica • create a sound platform to develop an Asset Investment Strategy • determine adequate resources to tackle repairs and maintenance e.g. of structural elements, that subsequently leads to the need for replacement at much higher cost Proposal

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
External Stock Condition Survey of HRA DwellingsReport 5 pages DownloadRead as text

At this meeting

Whole meeting

More from Rotherham Safe and Attractive Neighbourhoods (August 2010-February 2015)

All decisions
MeetingDecisionOutcome
13 Feb 2015 Local Plan Evidence Base - Joint Sheffield and Rotherham Employment Land ReviewResolved :- (1) That the report be received and its contents noted. (2) That the proposed appointment of Nathaniel Li... Noted Open
2 Feb 2015 Minutes of the previous meeting held on 12th January, 2015- That the minutes of the previous meeting be agreed as a correct record. Agreed Open
2 Feb 2015 Housing Investment Programme 2014/15 update- That the report be received and its content noted. Noted Open
2 Feb 2015 Housing Revenue Account Budget Monitoring Report 2014/2015- That the report be accepted and the latest financial projected outturn based on forecasts to end of December, 2014,... Noted Open
2 Feb 2015 Neighbourhoods General Fund Revenue Budget Monitoring 2014/2015- That the report be received and the latest financial projection to the end of December, 2014, against the budget fo... Noted Open