Resolved
- That the latest financial projection against budget for 2013/14 be noted.
Safe and Attractive Neighbourhoods (August 2010-February 2015) noted this item on Monday 2 December 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
- That the latest financial projection against budget for 2013/14 be noted.
This budget monitoring report presents the forecast outturn position on the 2013/14 Housing Revenue Account (HRA) based upon actual income and expenditure to the end of October 2013.
The overall forecast is that the HRA will outturn on budget with a transfer from working balance (reserves) of £1.845m which is a reduction of £754k against the approved budget.
• That cabinet member receives and notes the latest financial projection against budget for 2013/14. 7. Proposals and Details
7.1This budget report is based upon actual income, expenditure and known commitments as at the end of October 2013 forecast to the end of the financial year to give a projected outturn position, compared to budget.
7.2Appendix A of this report provides the Budget Operating Statement for 2013/14 which shows the various income and expenditure budget lines which make up the net cost of delivering the service. The latest forecast net cost of service is £6.567m which, together with Revenue Contribution to Capital (RCCO) costs of £8.437m and interest received (-£25k) will result in an overall deficit of £1.845m to be transferred from Working Balance.
7.3Within the Operating Statement are several budget heads which are either year end adjustments (for example debt management costs £222k) or are subject to external influence and therefore outside direct control (for example cost of capital charges £14.602m).
7.4Budget Monitoring is therefore mainly focussed upon expenditure and income which is within control, i.e. income of £78.904m, the repair and maintenance budget of £17.996m and supervision and management of £20.065m. Other budget heads as seen within Appendix A are currently being forecast to outturn in line with budget.
7.5Budget Monitoring
7.5.1 Appendix A, column B demonstrates the projected outturn based upon activity to the end of October 2013.
7.5.2 Overall it can be seen that the net cost of service (before RCCO and interest received) is forecast to be £6.567m, a surplus of £754k as shown in the table below.
Budget Forecast Variance £000 £000 £000 Expenditure 73,090 73,125 35 Income -78,903 -79,692 -789
Net Cost of Service -5,813 -6,567 -754
7.5.3 Several of the budget lines within income and expenditure are forecasting to outturn with a variance to budget. The table below highlights these budgets Budget Forecast Variance £000 £000 £000 Expenditure: Supervision and 20,065 20,300 235 Management Cost of Capital 14,602 14,402 -200 Charge
Income: Dwelling Rents -74,245 -74,330 -85 Non Dwelling Rents -792 -798 -6 Charges for Services -3,602 -4,197 -595 Other Fees and -214 -317 -103 Charges
Net Variance -754
7.5.4 It can be seen that there is a forecast under spend on both income and expenditure budgets.
7.5.5 The balance of this report will focus on the main variations to budget.
7.6Expenditure
Column B of Appendix A demonstrates that based upon expenditure and commitments to date, total expenditure is forecast to outturn at £73.125m compared to a budget provision of £73.090m, an increase in spend of £35k. The main variations are as follows:
7.6.1 Contributions to Housing Repairs
Appendix A demonstrates that the forecast year-end spend on Repairs and Maintenance is currently forecasting to budget at £17.996m.
7.6.2 The empty homes budget is difficult to forecast as this is a very responsive service. The original budget has been set around an estimated 1,500 minor voids in year. At the end of quarter 2 there were 123 more completions than budgeted. The main reason for the increase is the impact of the Welfare Reform as more tenants requested a transfer to smaller properties.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
HRA AppendixAppendix | 1 pages | Download |
PDF |
Housing Revenue Account Budget Monitoring 2013-14Report | 6 pages | DownloadRead as text |
Follow Safe and Attractive Neighbourhoods (August 2010-February 2015) at Rotherham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 13 Feb 2015 | Local Plan Evidence Base - Joint Sheffield and Rotherham Employment Land ReviewResolved :- (1) That the report be received and its contents noted. (2) That the proposed appointment of Nathaniel Li... | Noted | Open |
| 2 Feb 2015 | Minutes of the previous meeting held on 12th January, 2015- That the minutes of the previous meeting be agreed as a correct record. | Agreed | Open |
| 2 Feb 2015 | Housing Investment Programme 2014/15 update- That the report be received and its content noted. | Noted | Open |
| 2 Feb 2015 | Housing Revenue Account Budget Monitoring Report 2014/2015- That the report be accepted and the latest financial projected outturn based on forecasts to end of December, 2014,... | Noted | Open |
| 2 Feb 2015 | Neighbourhoods General Fund Revenue Budget Monitoring 2014/2015- That the report be received and the latest financial projection to the end of December, 2014, against the budget fo... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.