Item99
Resolved
Resolved :- (1) That the report be received and its contents noted. (2) That detailed design work and construction be undertaken to provide a new cycle path from Centurion Street, Templeborough to the Rotherham to Sheffield canal towpath, as shown on drawing number 126/17/TT274 submitted, incorporating a three metres wide, waterproof surface constructed of tarmacadam or similar material. (3) That appropriate cycle signage be provided for a new cycle route between Templeborough and Kimberworth, as described in the report now submitted.
Word for word from the decision Rotherham published for this meeting.
Source: moderngov.rotherham.gov.uk