Resolved
- That the minutes of the previous meeting held on 24 th February, 2014, be agreed as an accurate record.
Communities and Cohesion agreed this item on Friday 21 March 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
- That the minutes of the previous meeting held on 24 th February, 2014, be agreed as an accurate record.
COMMUNITIES AND COHESION - 24/02/14 27E
CABINET MEMBER FOR COMMUNITIES AND COHESION 24th February, 2014
Present:- Councillor Hussain (in the Chair) and Councillor Wallis.
Apologies for absence were received from Councillor Burton.
E45. DECLARATIONS OF INTEREST.
No Declarations of Interest were made.
E46. MINUTES OF THE PREVIOUS MEETING HELD ON 27TH JANUARY, 2014.
The minutes of the previous meeting of the Cabinet Member for Communities and Cohesion held on 27th January, 2014, were considered.
Resolved: - That the minutes of the previous meeting be agreed as an accurate record.
E47. INTEGRATED YOUTH SUPPORT SERVICE - IT REQUIREMENTS.
Consideration was given to the report presented by the Operational Commissioner (Commissioning, Neighbourhood and Adult Services Directorate) that outlined the need to create a single information system that would meet the needs of the whole Integrated Youth Support Service (IYSS), which included Youth Offending, Connexions and Youth Services. The report detailed the existing information system arrangements in the Service.
The IYSS currently ran two information systems, CareWorks, used by the Youth Offending Service for care planning and contributing to local and national performance management, and Cognisoft, used by Connexions and Youth Services to record interventions, along with information management and national reporting requirements. The contract relating to Cognisoft was due to end on 31st March, 2014.
Minute No. E30 (Exemption from Standing Orders – Integrated Youth Support Service – IT Systems) of the Cabinet Member for Communities and Cohesion held on 19th November, 2012, refers. The original Exemption from Standing Orders had been granted in order that the market could develop and products that would incorporate all required information technology requirements of the IYSS. The Operational Commissioner reported that the market had not significantly developed during this period.
In order to fully complete the integration of the IYSS, it was crucial for one information system to be in place. The Cabinet Member was presented with three proposed options for the future operation of the Service. 28E COMMUNITIES AND COHESION - 24/02/14
The three options were fully costed and the benefits and risks of each approach were included. A bid had been made for capital funding associated with developing the information system.
Option One: - Undertake a full tendering exercise for an Integrated Youth Support information system commencing in April, 2015, for a period of five years;
Option Two: - Continue to contract with Cognisoft for a period of five years from April, 2015, with a module developed for Youth Offending information that provided an integrated system for IYSS;
Option Three: - Continue with the Cognisoft and Careworks systems for a period of five years from April 2015.
Option One, to undertake a full tendering exercise, was the recommended option, and if it was approved, would require the Exemption of Standing Order 38.2 (the requirement to invite between three and six written quotations for contracts between £50,000 - £500,000) to extend the contract with Cognisoft until 31st March, 2015, in order that the tendering exercise could take place.
Discussion ensued on the proposal and the following points were made: -
• Did the proposed options satisfy the Youth Justice Board’s expectations? – Yes, all options had been drawn-up to satisfy the statutory information reporting and management requirements across the workforce.
The Cabinet Member expected that robust project management would be applied to the software development process to prevent rising costs.
Resolved: - (1) That Standing Order 48.2 (the requirement to invite between three and six written quotations for contracts between £50,000 - £500,000) be exempted in order that the existing contract with Cognisoft be extended for a further year from 1st April, 2014 – 31st March, 2015.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Minutes of the previous meeting held on 24th February, 2014.Minutes | 52 KB | DownloadRead as text |
Follow Communities and Cohesion at Rotherham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Jul 2014 | Minutes of the previous meeting held on 23rd June, 2014.- That , subject to the above amendments being made, the minutes of the previous meeting be agreed as an accurate rec... | Agreed | Open |
| 22 Jul 2014 | Asylum/Migration update.- That the update information provided be noted. | Noted | Open |
| 22 Jul 2014 | Joint Working Charter between Parish and Town Councils and RMBC.- (1 ) That the report be received and its content noted. (2) That a review of the Joint Working Charter between Pari... | Noted | Open |
| 22 Jul 2014 | Communications update.- That, in the absence of the Communications Manager, this item be deferred to the next meeting of the Cabinet Member... | Deferred | Open |
| 22 Jul 2014 | Petition - Play Area for Children - Highfield View estate, Catcliffe- (1) That the petition be referred to the Transportation and Highways Section for investigation of matters relating ... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.