Resolved
Resolved :- (1) That the report be received and the contents noted. (2) That the recommendation to approve the updated 2013/14 to 2016/17 Capital Programme be noted.
The Former Self Regulation Select Commission noted this item on Thursday 27 March 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved :- (1) That the report be received and the contents noted. (2) That the recommendation to approve the updated 2013/14 to 2016/17 Capital Programme be noted.
The purpose of this report is to provide details of the current forecast outturn for the 2013/14 programme and enable the Council to review the capital programme for the financial years 2014/15 to 2016/17.
SELF REGULATION IS ASKED TO NOTE:-
THE REQUEST TO CABINET TO NOTE THE CONTENTS OF THIS REPORT; AND
THE REQUEST TO CABINET TO RECOMMEND THE APPROVAL OF THE UPDATED 2013/14 TO 2016/17 CAPITAL PROGRAMME BY FULL COUNCIL. 7 Proposals and Details
7.1Background - The Capital Programme 2013/14 to 2016/17
The budget process that led to the original Capital Programme for 2013/14 to 2016/17 ensured that the Council’s capital investment plans were aligned with its strategic priorities and vision for Rotherham.
In order to maintain that strategic link, and make best use of the capital resources available to the Council, it is important that the programme is kept under regular review and where necessary revisions are made. This programme was initially reviewed in July 2013, following the finalisation of the 2012/13 outturn capital expenditure and financing, and has now been the subject of further reviews, the result of which is reflected in the Directorate summary table presented below. A detailed analysis of the programme for each Directorate is attached at appendices 1 to 4.
2013/14 2013/14 2014/15 2014/15 2015/16 2015/16 2016/17 2016/17 Revised Variance Estimate Variance Estimate Variance Estimate Variance Estimate from from from from Last Last Last Last Report Report Report Report
Directorate £m £m £m £m £m £m £m £m Children & Young 22.301 +1.193 11.143 +0.195 6.134 -0.173 3.084 -0.173 People’s Service Environment & 19.607 -5.365 22.019 +7.780 8.159 +0.920 1.200 +0.550 Development Services Neighbourhoods 33.017 -1.461 35.885 +2.681 28.014 0.000 28.062 0.000 & Adult Services Resources 2.859 +1.022 1.380 +0.423 0.470 0.000 0.470 0.000
TOTAL 77.784 -4.611 70.427 +11.079 42.777 +0.747 32.816 +0.377
7.2Children and Young People’s Services Capital Programme 2013/14 to 2016/17
The revised proposed spend for 2013/14 is £22.301m, with a further £20.361m of investment in the following years of the programme.
A copy of the current full programme is attached to this report at Appendix 1. Commentary on the main aspects of the programme and the nature of the spend is given below.
Primary Schools
Spend on Primary Schools is expected to be £9.432m in 2013/14, with a further £9.124m of planned spend in 2014/15 to 2016/17. The major investments to note in this area are: • The extension and refurbishment at Maltby Lilly Hall Primary school is now complete (£2.070m in 2013/14). The work has created six new classrooms together with associated facilities and external play areas. Budget, previously expected to not be required, has had to be reinstated to enable the subsequent discovery of asbestos to be properly managed as well as delays to roofing works caused by the recent adverse weather conditions.
• Work to build five new classrooms was completed in December 2013 at Herringthorpe Infant and Junior Schools (£1.979m in 2013/14). However, external problems with a wall, drainage and paths during the build, together with a requirement for extra landscaping and furniture, has resulted in additional investment being necessary.
• The new 4 classroom block at Aston Hall Junior and Infant School (£0.899m in 2013/14) was completed in September 2013. Additional, unforeseen, landscaping was required to deal with the changes in level of the buildings.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Capital Programme Monitoring 2013/14 and Capital Programme Budget 2014/15 to 2016/17Report | 113 KB | DownloadRead as text |
PDF |
Capital monitoring appendices: March: For CabinetReport | 22 KB | Download |
Follow The Former Self Regulation Select Commission at Rotherham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 Feb 2015 | Revenue Budget Monitoring for the period ending 31st December 2014Resolved :- That the current forecast outturn and the continuing financial challenge for the Council to deliver a bal... | Noted | Open |
| 19 Feb 2015 | RMBC "Facing the Cuts, Delivering Rotherham's Priorities" 2015/16/2016/17 - Public/Employee Consultation FindingsResolved :- (1) That the headline messages arising from the analysis of the budget consultation be noted. (2) That th... | Noted | Open |
| 19 Feb 2015 | Date and Time of Next MeetingResolved :- That the next meeting of the Self Regulation Select Commission take place on Thursday, 26th March, 2015 a... | Decided | Open |
| 8 Jan 2015 | Minutes of the previous meeting held on 23rd October, 2014Resolved :- (1) That the minutes of the previous meeting held on 23 rd October, 2014 be agreed as a correct record fo... | Agreed | Open |
| 8 Jan 2015 | Corporate Plan OutcomesResolved :- That the Interim Chief Executive be thanked for her explanation on the reason for the delay of the report. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.