Capital Programme Outturn 2013/14 and Updated Estimates 2014/15 to 2016/17

Noted Committee 2 papers

The Former Self Regulation Select Commission noted this item on Friday 27 June 2014. Below is the council's own wording, with the papers it was decided on.

Item8

Resolved

Resolved :- (1) That the unaudited 2013/14 capital outturn position be noted. (2) That the recommendation to Council to approve the updated 2014/15 to 2016/17 capital programme be noted.
Word for word from the decision Rotherham published for this meeting. Source: moderngov.rotherham.gov.uk

Follow this further

Built from Rotherham's papers

What the report saysPro

Report to The Former Self Regulation Select Commission, 14 pages

Summary

The purpose of this report is to report the capital outturn position for the 2013/14 financial year and recommend for approval changes to the programme for the financial years 2014/15 to 2016/17. These changes have resulted from the 2013/14 outturn and scheme changes since the overall programme was agreed in March 2014, as part of the budget setting process.

Recommendations

That Self Regulation note the request to Cabinet to:-

NOTE THE 2013/14 CAPITAL OUTTURN POSITION; AND

RECOMMEND THE APPROVAL OF THE UPDATED 2014/15 TO 2016/17 CAPITAL PROGRAMME BY FULL COUNCIL. 7 Proposals and Details

7.1Background - The Capital Programme

The finalisation of the 2013/14 capital expenditure and financing outlined in this report, provides an opportunity to reflect and update the future years’ programme that was previously approved by Council in March, for the financial years 2014/15 to 2016/17.

The current economic climate and the on-going impact of the Government’s austerity measures require that the capital programme is subject to continual oversight, and if necessary, revision, to ensure that the Council’s capital investment plans are aligned with strategic priorities and maximise the value from the limited capital resources available.

The financial implications of the Programme are reflected in the Council’s Medium Term Financial Strategy (MTFS) and Treasury Management and Investment Strategy.

For 2013/14 the Council’s capital investment into the regeneration and enhanced infrastructure of the Borough was £71.769m. The profile of this investment and the updated future expenditure plans are reflected in the Directorate summary table presented below. A detailed copy of the programme for each Directorate is attached at Appendices 1 to 4.

2013/14 2013/14 2014/15 2014/15 2015/16 2015/16 2016/17 2016/17 Outturn Variance Estimate Variance Estimate Variance Estimate Variance from from from from Last Last Last Last Report Report Report Report

Directorate £m £m £m £m £m £m £m £m Children & Young 20.961 -1.340 13.899 +2.756 5.334 -0.800 2.694 -0.390 People’s Service Environment & 18.446 -1.161 28.746 +6.727 8.159 0 1.200 0 Development Services Neighbourhoods 30.305 -2.712 37.330 +1.445 28.014 0 28.062 0 & Adult Services Resources 2.057 -0.802 2.142 +0.762 0.470 0 0.470 0

TOTAL 71.769 -6.015 82.117 +11.690 41.977 -0.800 32.426 -0.390

The updated programme has been prepared in light of the capital resources known to be available to the Council over these financial years, and estimated on a prudent basis.

The Council is continuing to undertake a comprehensive review of its assets and buildings portfolio, with the aim to rationalise both its operational and non- operational asset holdings, which may contribute both a future capital receipt and a revenue saving. 7.2 Children and Young People’s Services Capital Programme 2013/14 to 2016/17

The 2013/14 outturn was £20.961m, with total proposed expenditure over the period of the future programme of £21.927m, including new schemes at several schools across the Borough required to address the increase in pupil numbers, including the central Rotherham catchment areas where the problem is particularly acute.

For 2013/14 the major capital investments into the Council’s educational and learning facilities across the borough were:

Primary Schools

• The extension and refurbishment at Maltby Lilly Hall Primary school is now complete (£1.992m in 2013/14). The work has created six new classrooms together with associated facilities and external play areas. Budget, previously expected to not be required, has had to be reinstated to enable the subsequent discovery of asbestos to be properly managed as well as delays to roofing works caused by the wet winter weather conditions. £54k of outstanding invoices will be settled in 2014/15.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme Outturn 2013/14 and Updated Estimates 2014/15 to 2016/17Report 14 pages DownloadRead as text
PDF
Capital monitoring appendices: June: Base Data (v1)Report 11 pages Download

At this meeting

Whole meeting

On this subject at Rotherham

Search all
  1. Capital Programme Outturn 2013/14 and Updated Estimates 2014/15 to 2016/17This decision
  2. Asset Management Estimates and Capital Programme Audit UpdateNoted
  3. Recommendation from cabinet - financial outturn 2020/21 and capital programmeNoted
  4. Transportation Capital ProgrammeAgreed
  5. Highways Capital ProgrammeAgreed
  6. Highways Capital ProgrammeAgreed

More from Rotherham The Former Self Regulation Select Commission

All decisions
MeetingDecisionOutcome
19 Feb 2015 Revenue Budget Monitoring for the period ending 31st December 2014Resolved :- That the current forecast outturn and the continuing financial challenge for the Council to deliver a bal... Noted Open
19 Feb 2015 RMBC "Facing the Cuts, Delivering Rotherham's Priorities" 2015/16/2016/17 - Public/Employee Consultation FindingsResolved :- (1) That the headline messages arising from the analysis of the budget consultation be noted. (2) That th... Noted Open
19 Feb 2015 Date and Time of Next MeetingResolved :- That the next meeting of the Self Regulation Select Commission take place on Thursday, 26th March, 2015 a... Decided Open
8 Jan 2015 Minutes of the previous meeting held on 23rd October, 2014Resolved :- (1) That the minutes of the previous meeting held on 23 rd October, 2014 be agreed as a correct record fo... Agreed Open
8 Jan 2015 Corporate Plan OutcomesResolved :- That the Interim Chief Executive be thanked for her explanation on the reason for the delay of the report. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies