Resolved
Resolved :- (1) That the performance of the Internal Audit Service during the period be noted. (2) That the key issues arising from the work done in the period be noted.
Audit Committee noted this item on Wednesday 17 September 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved :- (1) That the performance of the Internal Audit Service during the period be noted. (2) That the key issues arising from the work done in the period be noted.
ROTHERHAM BOROUGH COUNCIL – REPORT TO AUDIT COMMITTEE
1. Meeting: Audit Committee
2. Date: 17th September 2014
Review of Progress Against the Internal Audit Plan 3. Title: for the four months ending 31st July 2014
4. Directorate: Environment and Development Services
5. Summary. This report contains a summary of Internal Audit work and performance for the four months ending 31st July 2014. Progress on our Audit Plan is slightly below target at this stage of the year for various reasons including the voluntary severance of one member of staff, maternity leave, additional responsive work and the extended scope of some pieces of work. Management actions to bring coverage back into line are being considered. Based upon the work we have undertaken in the period, we were able to confirm that the Council’s control environment was adequate and was operating satisfactorily.
6. Recommendations.
The Audit Committee is asked to:
• note the performance of the Internal Audit Service during the period • note the key issues arising from the work done in the period 7. Proposals and Details.
7.1Background This report summarises the main activities of the Internal Audit service for the first four months of 2014/15. The report is presented to the Audit Committee to enable the Committee to fulfil its responsibility to oversee the work of Internal Audit. The report summarises: • performance against key service benchmarks • planned audit reports issued during the period, highlighting the overall conclusion/opinion for each audit • the number of high priority recommendations made • the proportion of recommendations agreed / not agreed • a summary of responsive work undertaken • an analysis of use of audit resources • a summary of key service developments during the period.
7.2Performance Indicators. 7.2.1 Our performance against a number of indicators is summarised in the table below: Performance 2012/13 2013/14 2014/15 Apr to Jul Indicator Actual Actual Target 2014 Draft reports issued within 93% 95% 95% 92% 15 days of field work being completed. Percentage of 3 star 100% 100% 100% 100% (fundamental control weakness) recommendations agreed. Chargeable Time/Gross 65% 63% 63% 61% Time. Audits completed within 93% 95% 95% 73% planned time. Percentage of Audit Plan 78% 85% 85% ** completed. Cost per Chargeable Day. £275 £265 £265 £273 Client Satisfaction Survey. 100% 100% 100% 100%
** The % of audit plan completed is a full year indicator.
7.2.2 Progress on most indicators is close to or on target and we anticipate these will be achieved by the year end. 7.2.3 Exceptions at this stage are in relation to ‘Audits completed within planned time’ and ‘Percentage of Audit Plan completed’. The scope on some jobs has been extended causing some jobs to be completed outside of target time. The % of audit plan completed is a full year indicator but at this stage we do not expect to achieve 85%. This is partly because of the overrun on some jobs, but also due to the voluntary severance of one member of staff, maternity leave, additional responsive work. Options for improving the performance in these areas are being considered. 7.2.4 It is pleasing to note that agreement of critical recommendations and client satisfaction with our service continue to be excellent. 7.2.5 Other factors affecting our performance to date are outlined at Appendix C – Analysis of Use of Audit Resources.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Review of Progress Against the Internal Audit Plan for the four months ending 31st July 2014Report | 9 pages | DownloadRead as text |
Follow Audit Committee at Rotherham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 24 Sep 2026 | Exclusion of the Press and Public- That, under Section 100A(4) of the Local Government Act 1972, the press and public be excluded from the meeting for... | Decided | Open |
| 24 Sep 2026 | Minutes of the previous meeting held on 28th July, 2026- That the minutes of the previous meeting of the Audit Committee be approved as a correct record of proceedings. | Approved | Open |
| 24 Sep 2026 | External Audit Progress Report and Sector Update- That the progress and sector updates be noted. | Noted | Open |
| 24 Sep 2026 | Code of Corporate Governance- That the refreshed version of the be received and noted. | Noted | Open |
| 24 Sep 2026 | Anti-Money Laundering Policy Review- (1) That the revised Anti-Money Laundering Policy be received and noted. (2) That the actions being undertaken to r... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.