Environment and Development Services - Revenue Budget Monitoring 2014/15
NotedCommittee1 paper
Environment (October 2014-February 2015) noted this item on Monday 20 October 2014. Below is the council's own wording, with the papers it was decided on.
Resolved :- (1) That the report be received and its contents noted. (2) That the latest financial projection against budget for 2014/15, based on actual income and expenditure to 31st August, 2014, as outlined in the submitted report, be noted. (3) That the submitted report be referred to the Self Regulation Select Commission for information.
Word for word from the decision Rotherham published for this meeting.Source: moderngov.rotherham.gov.uk
Report to Environment (October 2014-February 2015), 6 pages
Summary
To report on the performance against budget for the Environment and Development Services Directorate Revenue Accounts at the end of August 2014 and to provide a forecast outturn for the whole of the 2014/15 financial year.
Members are asked to note the forecast outturn position of an over-spend of £219k for the Environment & Development Services Directorate based on expenditure and income as at August 2014.
Recommendations
That the Cabinet Member notes the latest financial projection against budget for the year based on actual income and expenditure to the end of August 2014, as outlined in the Briefing Note already circulated (as agreed there will be no Officer to present this report). This report is referred to the Self Regulation Overview and Scrutiny Select Commission for information. 7 Proposals and Details
7.1.1 Cabinet Members receive and comment upon budget monitoring reports on a monthly basis. This report reflects the position against budget for the period 1 April 2014 to 31 August 2014.
7.1.2 The table below summarises the forecast outturn against approved budgets for each service division:
Division of Service Net Forecast Variation Variation Budget Outturn
£000 £000 £000 % Asset Management, Audit 8,230 8,125 -105 and Insurance Business Unit 401 401 0 Communications 783 789 +6 Regeneration, Planning 6,937 6,979 +42 and Cultural Services Streetpride 28,878 29,154 +276
Total Environmental and 45,229 45,448 +219 0.48% Development Services
Following the August cycle of budget monitoring the Directorate has identified that it is likely to be overspent by +£219k (0.48%) against its total net revenue budget of £45,229k. All possible actions to mitigate this are being taken.
7.1.3 The details below are as offered in the Briefing Note already circulated to relevant Cabinet Members: CABINET MEMBER BRIEFING NOTE
For Cabinet Members: Cllrs Beck, Godfrey, Hoddinott, Hussain.
SUBJECT: EDS REVENUE BUDGET MONITORING
1. Update on the current projections for EDS Revenue Budget Monitoring at the end of August 2014.
The table below shows the monitoring figures for April – August with narratives explaining the current projections.
April - August Service £000 Asset Management, -105 Audit and Insurance Business Unit 0 Communications +6 Regeneration, Planning, Customer & +42 Cultural Services Streetpride +276
TOTAL +219
Asset Management, Audit and Insurance -£105k
There are some small pressures across the Asset Management service: Health and Safety (+£8k) for the cost of barriers for the first English Defence League rally, and due to staffing costs and under recovery of income (+£10k) All Saints toilets, and Riverside Café and Hospitality (+£5k) CENT has some residual costs (+£2k). Internal Audit (+£6k) pressure which is staffing related.
There are a number of underspends which are mainly building related. Commercial Properties (-£35k) due to additional rental income, and (-£59k) from Facilities Management of all council buildings. Further savings (-£42k) are being reported from the Corporate Environment Team and the Capital Team.
Business Unit £0k
The Service is currently reporting a balanced budget, and work is ongoing to identify any savings which could contribute to the current position. Communications +£6K
This small pressure is around staffing and marketing events, and work is ongoing to mitigate this pressure.
Regeneration, Planning, Customer and Cultural Services +£42k
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment (October 2014-February 2015) at Rotherham and we tell you when its next papers are published, before the meeting rather than after it.
Exclusion of the Press and PublicResolved :- That, under Section 100A(4) of the Local Government Act 1972, the press and public be excluded from the m...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.