Housing Investment Programme P6 September 2014

Noted Committee 2 papers

Safe and Attractive Neighbourhoods (August 2010-February 2015) noted this item on Monday 3 November 2014. Below is the council's own wording, with the papers it was decided on.

Item62

Resolved

- ( 1) That the report be received and its content noted. (2) That the budget virements and carry-over as detailed in the report be approved: - 1. £100k from HRA Enabling works (HRA Land) to fund Lady Oak Flats; 2. Opportunity/Strategic Acquisitions - £1,299,000 carried forward into 2015-16; 3. Doe Quarry Lane, Dinnington - £46,492 transfer to reserves for future projects; 4. Bellows Road - £192,343 carried forward to 2014/2015.
Word for word from the decision Rotherham published for this meeting. Source: moderngov.rotherham.gov.uk

Follow this further

Built from Rotherham's papers

What the report saysPro

Report to Safe and Attractive Neighbourhoods (August 2010-February 2015), 9 pages

Summary

The purpose of this report is to update the Cabinet Member for Safe & Attractive Neighbourhoods on the status of the Housing Investment Programme at Period 6 September 2014.

Recommendations

It is recommended that the Cabinet Member for Safe & Attractive Neighbourhoods:

Receives and notes the contents of this report

Approves budget virements and carry over as detailed in the report 7.0 Proposals and Details

7.1HIP Programme & Revisions

The budget process that led to the original Capital Programme for 2014/15 to 2016/17 ensured that the Council’s capital investment plans were aligned with its strategic priorities and vision for Rotherham.

In order to maintain that strategic link, and make best use of the capital resources available to the Council, it is important that the programme is kept under regular review and where necessary revisions are made.

The following table provides an overview of the approved HIP programme for the period 2014-15 and previously approved revisions.

Description Original Original Revised Revised Budget Budget + Budget Budget 2014-15 £ Approved 2014-15 £ 2014-15 Slippage (approved (approved 14 July 1 2014) September 2014) Refurbishments 11,995,000 12,626,687 13,197,786 13,197,786 Other Capital 13,563,000 13,318,239 13,143,239 13,143,239 Projects Fair Access to 3,389,000 3,389,000 3,389,000 4,093,660 All (Adaptations) Regeneration/ 2,250,000 2,250,000 2,050,000 2,050,000 Neighbourhood Renewal – Public Sector Regeneration/ 971,000 1,314,074 1,484,074 1,484,074 Neighbourhood Renewal – Private Sector HCA New build 2,836,000 2,836,000 2,836,000 2,836,000 Total 35,004,000 35,734,000 36,100,099 36,804,759

7.2Details

7.2.1 Housing Improvement Programme 2014-15 Capital Works

Appendix A provides a detailed budget breakdown by scheme for 2014-15 based on the current approved HIP Programme for 2014-15 and it should be read in conjunction with the following explanations for works in 2014-15 7.2.2 Refurbishment

Budget £13,197,786 Forecast £13,740,157 Variance £ 542,371

This budget is to fund works for internal and external refurbishments to properties. Internal works will include elements such as new kitchen and bathrooms. External elements include re-roofing, external render, fascia’s, soffits & bargeboard replacements and outhouse improvements.

Total spend to the end of September 2014 was £4,394,866. To date 940 properties have received works through this programme. The reason for increased forecast spend is a result of:

1. Increase forecast spend of £600,000 on External pointing and rendering following tenders being higher than original budget estimates. 2. Increase forecast of £60,000 on Fascia’s, soffits and bargeboard replacement programme due to revisions to specification mid-way through works. 3. Increased costs of £82,000 for windows and doors replacement programme following receipt of tender.

Some of these increased costs have been off-set by other schemes now forecasting lower spend than originally budgeted.

At the current time there are risks associated with the forecast spend as detailed below:

• External Pointing and Rendering

There have been delays in tendering 3 schemes at Thrybergh, Aston/ Aughton/ Swallownest and Treeton/ Brinsworth with a total estimated value of £1.5m. At the time of reporting all schemes have been approved and due to start on site by the beginning of November 2014. There is now potential risk that bad weather may impact on forecast spend given we are now entering the winter period.

• East Dene and Harthill Re-roofing

Both schemes have now commenced on site. At the current time there are no know issues with roosting bats as anticipated. Works continue to be monitored and any delays to the programme and subsequent spend as a result of ecological issues will be reported at Quarter 3.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
P6Appendix A 1 pages Download
PDF
Housing Investment Programme P6 September 2014Report 9 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Rotherham

Search all
  1. Housing Investment Programme P6 September 2014This decision
  2. Housing Investment Programme 2016/17Approved
  3. Housing Investment Programme 2014/15 updateNoted
  4. Housing Investment Programme 2014/15 Budget VirementsApproved
  5. Housing Investment Programme P5 August 2014.Noted
  6. Housing Investment Programme (Period 4, July 2014)Noted

More from Rotherham Safe and Attractive Neighbourhoods (August 2010-February 2015)

All decisions
MeetingDecisionOutcome
13 Feb 2015 Local Plan Evidence Base - Joint Sheffield and Rotherham Employment Land ReviewResolved :- (1) That the report be received and its contents noted. (2) That the proposed appointment of Nathaniel Li... Noted Open
2 Feb 2015 Minutes of the previous meeting held on 12th January, 2015- That the minutes of the previous meeting be agreed as a correct record. Agreed Open
2 Feb 2015 Housing Investment Programme 2014/15 update- That the report be received and its content noted. Noted Open
2 Feb 2015 Housing Revenue Account Budget Monitoring Report 2014/2015- That the report be accepted and the latest financial projected outturn based on forecasts to end of December, 2014,... Noted Open
2 Feb 2015 Neighbourhoods General Fund Revenue Budget Monitoring 2014/2015- That the report be received and the latest financial projection to the end of December, 2014, against the budget fo... Noted Open