Business Growth and Regeneration (July 2014-February 2015 noted this item on Friday 20 February 2015. Below is the council's own wording, with the papers it was decided on.
Resolved :- (1) That the report be received and its contents noted. (2) That, after due consideration of the financial implications of this issue, the operational budget for the shall be reinstated from 1st April 2015 and be funded by other budget savings within the Leisure and Green Spaces service.
Word for word from the decision Rotherham published for this meeting.Source: moderngov.rotherham.gov.uk
Report to Business Growth and Regeneration (July 2014-February 2015
Summary
This report proposes that the necessary operational budget for Herringthorpe Athletics Stadium is reinstated from 1st April 2015 and that the identified saving can be met by other areas of the Leisure & Green Space service. This will facilitate the continued operation of the Stadium under the current opening hours. It will also mean the facilities and opportunities afforded to the Rotherham Harriers Athletics club, schools and all the other user groups and individuals can be sustained and ideally developed.
Recommendations
It is recommended that the operational budget for Herringthorpe Athletics Stadium is reinstated from 1st April 2015, funded by other savings within Leisure & Green Spaces. 7. Proposals and Details
Background
Due to the continued need for the Council to make savings, as a result of reduced funding from central government, the Herringthorpe Athletics Stadium has been subject to budget reductions of £60,000 in 2013/14 and £18,000 in 2014/15. Following the second budget reduction it was agreed that the Stadium would operate reduced opening hours for a trial period. This would allow time for alternative methods of management to be explored before final closure would be necessary at the end of March 2015.
Current Situation
The Stadium is performing well in terms of meeting current user needs but it has not been possible to increase income sufficiently to fully cover the £18,000 that is needed to sustain the operation under the current reduced opening hours.
With regard to alternative management arrangements, there have been some expressions of interest from third parties, but these have not led to any sustainable option being identified therefore, under the existing decision by members, the Stadium is due to close at the end of March 2015 and the impact of this this would be:
• Rotherham Harriers Athletics Club, a key partner on site, along with the other groups, teams, schools and individuals identified in previous reports would no longer have access to the facilities. This would make continued participation in their chosen activities very difficult as there is no other athletics track in the borough.
• Teams using Herringthorpe Playing Fields may no longer have access to changing facilities and therefore alternative arrangements would need to be explored which will have associated costs.
• The site could become a target for vandalism which may incur further costs that cannot be calculated at this point.
• 3 part-time staff employed at the stadium would be at risk of redundancy
• The Active Rotherham (formerly Sports Development) Service would be relocated to Riverside House and there would be some loss of the wider sports development activity that takes place at the stadium (e.g. the ‘Active Always’ walking group and Chronic Obstructive Pulmonary Disease class).
• It would be necessary to demolish and / or remove all of the buildings within 3 months of closure in order to remove the cost of rates associated with the property (approximately £9,000 per year), otherwise this would be an ongoing budget pressure. This work would have an associated, one-off cost. • Contact has been made with Sport England in order to establish their position in respect of funding provided by them for track refurbishment in 2004. They have stated that it is possible they would seek compensation for their investment.
Proposed Way Forward
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Business Growth and Regeneration (July 2014-February 2015 at Rotherham and we tell you when its next papers are published, before the meeting rather than after it.
Exclusion of the Press and Public- That, under Section 100A(4) of the Local Government Act 1972, the press and public be excluded from the meeting for...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.