Resolved :- (1) That the progress that had been made in projects, plans and the Section 75 Agreement for the Rotherham Better Care Fund, including closer and more integrated joint working between health and social care and revised and strengthened governance for the BCF, be noted. (2) That the quarterly report submitted to NHS England relating to the performance of the plan for Rotherham during the last quarter of 2014/15, as set out in Appendix 1 to the submitted report, be noted. (3) That the reporting timelines for future submissions of returns to NHS England, as set out in Appendix 2 to the submitted report, be noted.
Word for word from the decision Rotherham published for this meeting.Source: moderngov.rotherham.gov.uk
1.1The purpose of this report is to provide Board Members with an update on the performance of the Section 75 agreement and Better Care Fund Plan for Rotherham
Recommendations
It is recommended that:
2.1Members note the progress that has been made in projects, plans and the section 75 agreement for the Rotherham BCF, including closer and more integrated joint working between health and social care, and revised and strengthened governance for the BCF.
2.2Members note the quarterly report submitted to NHS England relating to the performance of the Better Care Fund plan for Rotherham during the last quarter of 2014/15, as set out in Appendix 1. This return was authorised by the BCF executive, as agreed by the Health and Wellbeing Board on 22nd April 2015.
2.3Members note and agree the reporting timeline for future submissions of returns to NHS England, as set out in Appendix 2.
3. INTRODUCTION / BACKGROUND
3.1On 22nd April 2015 Rotherham’s section 75 agreement, setting out the plans for integration and operation of the BCF plan, was approved by the Health and Wellbeing Board, subject to minor amendments. These minor amendments were promptly completed, and both the CCG and Rotherham Council each have a signed copy of the final agreement.
3.2The section 75 agreement contained revised governance arrangements for the BCF plan, constituting a new operational group and a new strategic executive group. A reporting and monitoring timetable has been developed, which includes reporting to the Health and Wellbeing Board to ensure the BCF national conditions for BCF accountability are fully met, and ensures the authority meets the NHS England requirements and timescales for submitting quarterly returns. 3.3 The Section 75 agreement set out two pooled funds, comprising a total of 72 separate schemes. Some but not all of the schemes are fully operational, with the BCF Operational Group ensuring progress is being made to implement the few remaining schemes still in the planning stage.
3.4A joint review is underway on BCF scheme 13. This is the largest of the 16 schemes, and contains some projects which may need to be refocused to more closely relate to BCF strategic priorities. Currently some major projects receive just a small portion of BCF funding; yet such projects have a major impact on the delivery of the BCF targets. It may be that reprioritising existing projects could see a simplified, streamlined and more effective way of reporting and monitoring how Rotherham is focusing on BCF metrics, and especially on reducing non-elective admissions, and increasing patient and customer satisfaction.
3.5The review of services focuses on: the appropriateness for BCF funding, patient and customer satisfaction, monitoring and metrics, accountability and reporting, value for money, and on service delivery.
3.6The service review should be completed by early autumn, and a report will be prepared for the Health and Wellbeing Board.
3.7Quarter 4 ( 2014/15) monitoring report for the BCF was submitted to NHS England, according to the timetable discussed and agreed in April 2015 by the Health and Wellbeing Board. This report is attached at Appendix 1. It shows performance was in line with expectations. Although the target for reducing non-elective admissions was not reached, this was anticipated as the BCF plan was not fully implemented in this quarter.
4. CONCLUSION / NEXT STEPS
4.1The Health and Wellbeing Board is asked to note the format, and the timetable, for submitting the quarterly returns to both the board and then to NHS England.
Further reports will be brought to the board on the detail of the schemes funded within the BCF plan, according to the timetable in Appendix 2,
Financial implications
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.