Resolved :- That the minutes of the previous meeting be approved as a correct record for signature by the Chairman. Arising from Minute No. C6 (Heritable Bank PLC), it was noted that the 15 th interim dividend had been received (approximately £72,000) at the end of August, 2015. This now totalled 98.2% of the original investment recovered with an expectation still of 100% recovery. Arising from Minute No. C13 (Internal Audit Progress Report), it was noted that Internal Audit had almost completed a piece of work on the Integrated Housing Management System. It was also confirmed that the issue with Records Management had now been resolved.
Word for word from the decision Rotherham published for this meeting.Source: moderngov.rotherham.gov.uk
Present:- Councillor Wyatt (in the Chair); Councillors Alam, Evans and Hughes.
Tim Cutler and Debra Cunningham, KPMG were also in attendance.
An apology for absence was received from Councillor Cowles.
C1. QUESTIONS FROM THE PRESS AND PUBLIC
A member of the public stated that the Council had been criticised for not being able to demonstrate that it had used all its resources economically and effectively and asked if all the new Plans had been resilience tested and benchmarked? Had the interface and interdependency been built into the resilience test and cost of the Children and Young People’s Services Plan? Had it fed through into financial planning?
The Chairman stated that it was not the Committee’s role to manage risk but to be reassured that it was being managed. The risk work in the past had not been as robust as it should have been – that had been identified in the Improvement Plan and other reports – and it was the Audit Committee’s task to reassure the Government appointed Commissioners and the Civil Services that that had changed.
A complete refresh of the risk management arrangements was underway ensuring that they met the requirements of the Authority. The new Policy and Strategy was to be considered by the Strategic Leadership Team shortly and would include the requirement of the Advisory Cabinet Member and respective Strategic Director to attend the Audit Committee and report on how they managed risk. The Committee would be able to test out that risk management was being applied in practice.
C2. MINUTES OF THE PREVIOUS MEETING HELD ON 5TH MAY, 2015
The minutes of the previous meeting of the Audit Committee held on 5th May, 2015, were noted.
C3. CORPORATE AND CHILDREN AND YOUNG PEOPLE'S SERVICE IMPROVEMENT PLANS GOVERNANCE ARRANGEMENTS
Sue Wilson (CYPS Improvement Plan) and Justin Homer (“A Fresh Start” Rotherham Improvement Plan) reported on the arrangements that had been put into place in respect of the governance of the Improvement Plans for both the Council-wide (the Corporate Improvement Plan) and Children and Young People’s Services (CYPS). AUDIT COMMITTEE - 22/07/15
The governance of the CYPS Plan was through the Children’s Improvement Board, Chaired by the Children’s Commissioner, and attended by the Directors of Children’s Services and key partners which included Health and the Police.
Evidencing improvements on a weekly and monthly basis was used to determine impact and improved outcomes. The evidence presented to the Board was quantitative as well as qualitative and was critically assessed and challenged to ensure that it was robustly implemented. In addition, an evidence bank was in place for the Plan to capture outcomes which demonstrated the impact on each area identified.
The Corporate Improvement Plan (“A Fresh Start”) was approved at the 22nd May Council meeting and submitted to the Secretaries of State for Communities and Local Government (DCLG) and Education (DfE) on 26th May.
The Plan set out its headline governance arrangements primarily through a “Joint Board” of Commissioners and leading Elected Members (representing the Majority and Opposition Groups) supported by an officer Corporate Improvement Plan Group linked to the Strategic Leadership Team. The Joint Board would hold its first meeting on 28th July.
Discussion ensued on the Improvement Plans with the following issues raised/clarified:-
− Need for stability in the CYPS Senior and Middle Management Team in order to move forward
− Need to ensure the Audit Committee’s work plan linked with and referenced in the Improvement Plans when they were submitted to the Secretaries of State
− Once work was complete, as part of the CYPS Quality Assurance Framework, project officers would be requested to submit evidence for quality assurance testing before sign off
− As part of Ofsted’s Improvement Offer there would be bi-monthly improvement visits
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Exclusion of the Press and Public- That, under Section 100A(4) of the Local Government Act 1972, the press and public be excluded from the meeting for...
Anti-Money Laundering Policy Review- (1) That the revised Anti-Money Laundering Policy be received and noted. (2) That the actions being undertaken to r...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.