Minded to Grant Decision :- (1) That the forecast overspend and the need to maintain continuous close scrutiny of spend to significantly mitigate the current forecast overspend be noted. (2) That any 2016/17 budget savings proposals be implemented at the earliest appropriate opportunity (i.e. subject to clearance through appropriate approval mechanisms) to both guarantee full year effect of the saving in 2016/17 and contribute to mitigating the forecast overspend in 2015/16. (3) That any further measures which may be implemented to help mitigate the current forecast overspend for 2015/16 be proposed. Reason :- To consider the November Revenue Budget Monitoring report which currently showed a forecast outturn of £8.619m (+4.2%) above budget. The forecast outturn position had improved by £675k since the October monitoring report. Date of Publication of the Minded to Grant Decision :- Monday, 12 th January, 2015. Representations upon the decision are invited from Councillors, members of the public, partner agencies and any interested body or individual within five working days from the date of publication and must be received by Debbie Pons [email protected] no later than 5.00 p.m. on Tuesday, 19 th January, 2016. Date Representations Received :- None. Representations Received :- None. Date of Commissioner Manzie’s Final Decision :- 20 th January, 2016.
Word for word from the decision Rotherham published for this meeting.Source: moderngov.rotherham.gov.uk
The November Revenue Budget Monitoring report currently shows a forecast outturn of £8.619m (+4.2%) above budget. The forecast outturn position has improved by £675k since the October monitoring report.
There is £5.326m one-off funding (detailed in previous budget monitoring reports) which could be made available, subject to Commissioner approval, to help mitigate the current forecast overspend. If this £5.326m one-off funding is used to support the forecast overspend in 2015/16 the revised forecast overspend as at 30th November 2015 would reduce to £3.293m.
Key pressures contributing to the forecast overspend (£8.619m) are: • The continuing service demand and agency staffing cost pressures for safeguarding vulnerable children across the Borough and the strengthening of Social Work and management capacity; and
• Demand pressures for Direct Payments within Older People and Physical and Sensory Disability clients and clients with Mental Health needs.
The recommendation in the October revenue monitoring report to impose a moratorium on all ‘non-essential’ spend has now been implemented. Managers are closely scrutinising orders to ensure they meet the ‘essential spend criteria’ before orders are placed. These criteria are:
• The proposed spend must already be contractually committed; • It must be essential for the safeguarding of vulnerable children and adults; • It must be required to meet essential health and safety requirements; • The spend is required to in order to avoid a false economy (something which will cost more in the longer term); • The spend is highly sensitive to local Members or local communities.
To assist with managing this spend moratorium Managers are closely scrutinising the daily spend analysis reports which provide details of orders placed the day prior. This gives the opportunity for orders to be challenged, reprioritised or rejected before the contractual commitment is incurred.
Staff within the procurement team (P2P), are also closely reviewing orders being placed, and where appropriate, making further enquiries to ensure spend does meet the ‘essential’ criteria.
A number of 2016/17 budget savings proposals have already been agreed (some only requiring Officer approval through delegated powers) which will also contribute towards in-year savings in 2015/16. As these materialise their impact on the forecast outturn will be reflected in future revenue budget monitoring reports.
Additionally, the financial impact of any decisions to release staff through voluntary severance or voluntary early retirement will be factored into future budget monitoring reports at the earliest opportunity. It is expected that these decisions will also reduce the current forecast overspend.
Recommendations
• Note the forecast overspend and the need to maintain continuous close scrutiny of spend to significantly mitigate the current forecast overspend.
• Implement any 2016/17 budget savings proposals at the earliest appropriate opportunity (i.e. subject to clearance through appropriate approval mechanisms) to both guarantee full year effect of the saving in 2016/17 and contribute to mitigating the forecast overspend in 2015/16. • Propose any further measures which may be implemented to help mitigate the current forecast overspend for 2015/16.
List of Appendices Included
Appendix 1 – Detailed analysis of forecast under and overspends
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.