- (1) That the inclusion of the Riverside House LED lighting upgrade in the Capital Programme (2016-2021) be approved. (2) That the funding of the project through a combination of £262,000 prudential borrowing, over a period of 20 years and a loan of £78,000 from the Salix Local Authority Energy Financing ( LAEF ) fund be approved. (3) That the investment, which would achieve savings of £863,924 over this period (£47,748 per year from 2019/20), be noted. (As this was a Commissioner decision, it is not subject to ‘call in’)
Word for word from the decision Rotherham published for this meeting.Source: moderngov.rotherham.gov.uk
Report to Cabinet and Commissioners' Decision Making Meeting (during Government Intervention
Executive summary
This report is looking at the feasibility of replacing the existing Riverside House lighting with more energy efficient LED technology lighting, resulting in an estimated 69% saving on the annual lighting cost for the building.
Recommendations
Commissioner Kenny is asked to:- 1.1 Approve the inclusion of the Riverside House LED lighting upgrade in the Capital Programme (2016-2021). 1.2 Approve the funding of the project through a combination of £262,000 prudential borrowing, over a period of 20 years and a loan of £78,000 from the Salix Local Authority Energy Financing (LAEF) fund. 1.3 Note that this investment will achieve savings of £863,924 over this period (£47,748 per year from 2019/20). List of Appendices Included
Appendix A - Calculation - Riverside LED
Appendix B – Annual Revenue Savings
Background Papers - None
Consideration by any other Council Committee, Scrutiny or Advisory Panel No
Council Approval Required No
Exempt from the Press and Public - No Main Report Riverside House LED Lighting Upgrade
Commissioner Kenny is asked to:- 1.1 Approve the inclusion of the Riverside House LED lighting upgrade in the Capital Programme (2016-2021). 1.2 Approve the funding of the project through a combination of £262,000 prudential borrowing, over a period of 20 years and a loan of £78,000 from the Salix Local Authority Energy Financing (LAEF) fund. 1.3 Note that this investment will achieve savings of £863,924 over this period (£47,748 per year from 2019/20).
Background
2.1The current energy efficient compact fluorescent lighting in Riverside House has now been superseded by more efficient LED technology. It is proposed that the existing lighting is replaced point for point with new LED lighting, resulting in energy efficiency and carbon savings. This will equate to an overall 69% reduction in lighting consumption, saving approximately £68,000 per year on electricity costs. See Appendix A for detailed calculations.
Replacement of:
Amount Current Light Replacement Light 1,153 4 x 24W recessed luminaires 25W LED 381 4 x 24W emergency luminaires 25W LED 1,253 2 x 26W down lights 20W LED down lights 503 2 x 26W emergency down lights 20W LED
3. Key Issues
3.1RMBC corporately has adopted a target of reducing CO2 emissions by 2% year on year. Energy efficiency is a key contributor to achieving this target, alongside the financial benefit of reducing energy costs.
4. Options considered and recommended proposal
4.1Various light fittings have been sampled and installed in Riverside House to consider their stability and suitability. The manufacturers tested were Thorlux Lighting, Apollo Lighting, Profile Lighting, Luceco Lighting, Whitecroft Lighting and ASD Lighting.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet and Commissioners' Decision Making Meeting (during Government Intervention at Rotherham and we tell you when its next papers are published, before the meeting rather than after it.
Questions from Members of the Public.Decision Making Meeting had been published on 19 May 2016, complying the access to information rules within the Counc...
Questions from Members of the PublicDecision Making Meeting held on 26 May 2016, regarding his compliance with the council’s Constitution and whether adv...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.