Implementation of a new Social Care IT System and Request for Exemption to Standing Orders for the Liquid Logic Project
ApprovedExecutive1 paper
Cabinet and Commissioners' Decision Making Meeting (during Government Intervention approved this item on Monday 18 January 2016. Below is the council's own wording, with the papers it was decided on.
- (1) That the revised implementation date of 31 October 2016 for the new Liquidlogic Children’s social care case management and ContrOCC Children’s finance systems be approved. (2) That the Council be recommended to agree an increase £351,610 to the already approved capital allocation for the project in 2016/17 and it be added to the Capital Programme. (3) That an exemption from the obligation to tender for the provision of three data migration consultants be approved and the existing contracts for such consultants already engaged be extended to provide services until implementation is completed. (4) That approval be given to Option 2, detailed within the report, in respect of the appointment of the three additional external consultants, which were commissioned via Dutton International, the council’s contracted recruitment agency. (5) That a further report be submitted to a Cabinet and Commissioners’ Decision Making Meeting in respect of the Liquidlogic Adults social care case management and ContrOCC Adults financial systems, upon completion of the review of the implementation timetable.
Word for word from the decision Rotherham published for this meeting.Source: moderngov.rotherham.gov.uk
Report to Cabinet and Commissioners' Decision Making Meeting (during Government Intervention
Summary
1. In its inspection findings in November 2014, Ofsted identified that Rotherham’s social care case management system did not support good practice. Ofsted found that workers were unable to locate key case documents, chronologies were rarely up to date, and most chronologies had significant gaps.
2. “The local authority’s ability to measure the performance of children’s social care was limited by the capacity of the electronic recording systems, which primarily report on compliance measures such as timescales.” Further to this, Louise Casey published her report; “Report of Inspection of Rotherham Metropolitan Borough Council” in February 2015. This report identified that “The IT systems supporting social workers are not fit for purpose.”
3. In April 2015, a contract for the implementation of a new social care IT system for Children’s and Adults services was awarded to Liquidlogic, following a process of competitive tendering. The contract between Rotherham Metropolitan Borough Council (RMBC) and Liquidlogic was signed on the 30th June 2015. A programme plan was developed which included a proposed implementation date of the 8th February 2016 for the Children’s system, and the 12th April 2016 for the Adults system. Given the industry norms for this type of implementation it is recognised that this was incredibly ambitious. 4. In September 2015, the Programme Sponsor commissioned a report from a consultant from ICT Revolutions. Following this, an internal audit of the new system implementation programme was commissioned by the Council’s internal audit services, and received in January 2016.
5. Both reports made a number of common recommendations, and identified programme critical issues, including issues relating to data migration, staff training and performance reporting.
6. In response to these recommendations, this report recommends the extension of the proposed implementation date, and sets out the resource and budgetary implications of this extension, including the resourcing of additional leadership capacity essential to the successful implementation of the new system.
7. Due to the recommendation to extend the timescales to the implementation date, this report is also to request an exemption under Standing Order 38 from the provisions of Standing Order 48 (requirement to invite between three to six tenders where a contract for work, service or supply of goods or materials is valued at £50,000 or more) with regard to the appointment of consultants to support data migration as part of the Liquidlogic Project.
Recommendations
The Cabinet is asked to:
1. Agree a revised implementation date for the new Liquidlogic Children’s social care case management and ContrOCC Children’s finance systems of 31st October 2016.
2. Agree to an increase of £351,610 to the already approved capital allocation for this project in 2016/17 and to this being added to the Capital Programme.
3. Approve an exemption from the obligation to tender for the provision of three data migration consultants and that the existing contracts for these consultants be extended to provide services until implementation is completed.
4. Approve Option 2, as set out in paragraph 4.4.2, in respect of the appointment of the three additional external consultants, noting that they have been commissioned via Dutton International, the Council’s contracted recruitment agency. The appropriate business case has been completed and authorised.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet and Commissioners' Decision Making Meeting (during Government Intervention at Rotherham and we tell you when its next papers are published, before the meeting rather than after it.
Questions from Members of the Public.Decision Making Meeting had been published on 19 May 2016, complying the access to information rules within the Counc...
Questions from Members of the PublicDecision Making Meeting held on 26 May 2016, regarding his compliance with the council’s Constitution and whether adv...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.