Resolved
- 1. That the tender submitted by the preferred developer, dated 18 April 2016, be accepted for the site cluster programme. 2. That the Assistant Director of Legal Services be authorised to finalise the development agreement. 3. That all predevelopment costs associated with securing planning permission and enabling construction works to commence be funded by the Council. 4. That a further report be submitted for approval of the development programme, development agreement and financial arrangements following the conclusion of negotiations with the preferred developer.