Resolved
Agreed:- That the progress in relation to developing the new SEN Sufficiency projects be noted.
Rotherham Schools' Forum agreed this item on Friday 26 June 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed:- That the progress in relation to developing the new SEN Sufficiency projects be noted.
TO: Schools Forum
DATE: 26th June 20200
BRIEFING LEAD OFFICER: Mary Jarrett Head of Inclusion Services CYPS [email protected]
TITLE: Up-date on SEN Sufficiency Projects. 1. Background
1.1On 20 May 2019, Cabinet approved a report setting out the Local Authority’s proposals to utilise capital funding to increase the sufficiency of school places for children with Special Education Needs and Disabilities (SEND) in Rotherham.
On 16th September Cabinet approved a capital spending programme of £1.186 million to create 111 additional school places in Rotherham starting from 2020, for children with special education needs and disabilities
This Report provides an up-date with regard to the progress of these Units.
2. Key Issues
2.1The Dedicated Schools Grant (High Needs Budget) in Rotherham has been under significant pressure since the introduction of the SEND Code of Practice in 2015. There is now increased demand for statutory assessments and for placements within specialist education provision. An increase in places in Rotherham for children with autistic spectrum conditions, moderate learning difficulties and social, emotional and mental health issues will reduce the pressure caused both by the predicted rise in numbers of children with education, health and care plans but also on the pressure to place children in high cost independent specialist provision because of a lack of appropriate local resources.
2.2Rotherham’s SEN Sufficiency projections estimate that by September 2020 there will be 2312 children with Education, Health and Care plans in Rotherham rising to 2500 children in 2021.
2.3In order to meet the needs of the growing population of children with identified Special Education Needs in Rotherham and to avoid costly out of area placements the Council has approved a Capital Spending programme of £1.186 million pounds which will provide an additional 111 specialist school placements for children with Special Education Needs. These are in addition to the 125 places which were agreed in phase 1.
2.4This report identifies that most agreed projects will be impacted by the recent Coronavirus management and it is not possible to predict the impact on this on constructions yet. Most projects will be built in August and it is not clear at present whether they can be delivered within timescales. In addition to uncertainty regarding continuation of building works there have been some additional delays and project issues, these are as follows:
The Aspire Primary site at Canalside: It is expected that the Canalside property will be ready by October 2020 creating a delay of one month from projected timescales.
The extensive works planned at Thomas Rotherham College (TRC) are projected to cost £400,000 which is an additional £250,000 to the funding already identified. TRC have offered a contribution of £100,000. The Council Designers are reviewing the plans to see what areas can be revised to accommodate the TRC vision whilst reducing the projected costs to circa £250,000.
Wath Victoria was tendered and was substantially over the budget of £100,000. This is currently being valued engineered by the Council’s Design and Projects Team.
RISK
It should be noted that due to Covid19 there is a significant risk to projects not being completed on time.
3. Key Actions and Timelines
3.1School Proposal and Timescales Maltby Hilltop School SEND Phase 2 (Nexus) Additional Classrooms 6 places Modular Unit £130,000.
The tender report had come in at £182,000. Maltby Hilltop are providing £57,000 with the Council funding the remaining £125,000.
Smaller modular unit repriced by R H Fullwoods as part of value engineering exercise. Tender report £151,036.29. Approved.
Funding: Council £121,000 Maltby Hilltop School £40,000
Planning application submitted 23rd January 2020. RB2020/0131 and was approved on the 17th March 2020.
Timescale:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Update on SEN Sufficiency ProjectsAgenda | 139 KB | DownloadRead as text |
Follow Rotherham Schools' Forum at Rotherham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 18 Sep 2026 | Appointment of ChairThat Mark Windle be appointed Chair of the Rotherham Schools Forum for the next two years (2026/27 and 2027/28 academ... | Decided | Open |
| 18 Sep 2026 | Appointment of Vice ChairThat Lynsey Hadfield be appointed Vice-Chair of the Rotherham Schools Forum for the next two years (2026/27 and 2027/... | Decided | Open |
| 18 Sep 2026 | Minutes of the Previous MeetingThat the minutes of the meeting held on 12 th June 2026 be approved as a correct record for signature by the Chair. | Approved | Open |
| 18 Sep 2026 | Membership and Constitution of the Rotherham Schools Forum· That the renewal of Lynsey Hadfield’s term of office as a Nursery School Head Teacher for a further four-year perio... | Agreed | Open |
| 18 Sep 2026 | Local Area Reform SEND Plan UpdateThat the Schools’ Forum noted the update. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.