Resolved
- (1) That the update be noted. (2) That a further update be submitted in March, 2023.
Audit Committee noted this item on Tuesday 15 March 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
- (1) That the update be noted. (2) That a further update be submitted in March, 2023.
1.1The Council procures a wide range of goods, works and services ranging from direct front line services through to back-office support. The Council’s annual spend with third parties through procurement and commissioned activity is in excess of £300m.
1.2Given this, it is imperative that the Council has robust procurement practices in place to ensure compliance, that value for money is being achieved, ethical practices are being applied and the contracts entered into are robust, deliver against the Council’s key priorities and strategies and minimise risk wherever possible.
1.3On 23 March 2021 an update on procurement activity was presented to Audit Committee. At this meeting, a request was made for an annual update. This report seeks to provide this update highlighting some of the activity delivered in the last 12 months by the Procurement team to ensure robust procurement activity is undertaken.
2. Key Issues
2.1Procurement Procedure Rules provide the corporate framework that sets out the rules and expectations that all Officers must comply with when entering into arrangements with third-party suppliers to provide goods, works and services ranging from simple low value day-to-day commodities through to multi-million-pound construction projects.
2.2In early 2021 work was undertaken to re-draft these Rules with the aim of making them easier to interpret and navigate, whilst embedding key principles around ethical practices and transparency at their core. In addition, the revised rules sought to embed a number of the operational procedures referred to in the last update to Audit Committee such as the requirement for a pre-procurement business case and tender evaluation report.
2.3These revised rules were approved at Council on 29 September 2021 and were implemented with immediate effect.
2.4Since their implementation, the key focus of activity for the Procurement Team has been to ensure Members and Officers within Service Areas are aware of the procedures, understand them and the reasons why the rules apply as well as building confidence and capacity in navigating them.
2.5Since implementation of the FPPRs the Procurement team have been running training sessions of between 2 to 2.5 hours to embed this learning. The first session commenced 3 November 2021 for Members and then has since been followed for officers. As at 4 March 2022, 179 officers have been trained across the organisation, with a further 70 scheduled to receive training before the end March 2022.
Page 2 of 5 2.6 It is likely that training will continue into the first quarter of 2022/23 with further refresher sessions to follow throughout the year.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
2022 Annual Procurement UpdateReport | 273 KB | DownloadRead as text |
Follow Audit Committee at Rotherham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 24 Sep 2026 | Exclusion of the Press and Public- That, under Section 100A(4) of the Local Government Act 1972, the press and public be excluded from the meeting for... | Decided | Open |
| 24 Sep 2026 | Minutes of the previous meeting held on 28th July, 2026- That the minutes of the previous meeting of the Audit Committee be approved as a correct record of proceedings. | Approved | Open |
| 24 Sep 2026 | External Audit Progress Report and Sector Update- That the progress and sector updates be noted. | Noted | Open |
| 24 Sep 2026 | Code of Corporate Governance- That the refreshed version of the be received and noted. | Noted | Open |
| 24 Sep 2026 | Anti-Money Laundering Policy Review- (1) That the revised Anti-Money Laundering Policy be received and noted. (2) That the actions being undertaken to r... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.