- (1) That, the recent external inspections, reviews and audits which have taken place and the progress made relating to ongoing recommendations, be noted. (2) That the governance arrangements in place for monitoring and managing the recommendations be noted. (3) That regular reports continue to be submitted to the Audit Committee. (4) That a report be submitted on the different processes Directorates used to monitor/sign off actions to ascertain if learning/good practice could be shared.
Word for word from the decision Rotherham published for this meeting.Source: moderngov.rotherham.gov.uk
External audit and inspection recommendations reports to Audit Committee on 11 January 2022, 28 July 2022, 10 January 2023, and 27 July 2023.
Consideration by any other Council Committee, Scrutiny or Advisory Panel None
Council Approval Required No
Exempt from the Press and Public No External audits, inspections, and reviews update
Background
1.1In line with the Audit Committee terms of reference, the purpose of this report is to provide details of the recent external inspections, reviews and audits across the Council and assurance that ongoing and outstanding recommendations, relating to those that have taken place previously, are being progressed.
1.2The last report was presented to Audit Committee on 27 July 2023. The report referred to external inspections, reviews and audits that had taken place since January 2023, which included nine new external inspections, reviews and audits that had taken place since January 2023, resulting in fourteen recommendations and areas for improvement. Of these six had been implemented and were complete, eight remained ongoing and were in progress and the outcome was not yet known for one of the audit reviews conducted.
1.3Ongoing recommendations/areas for improvement relating to external inspections, reviews and audits that took place prior to January 2023 included twenty-nine that had been implemented and were complete, forty-seven remained ongoing and were in progress, five of which were delayed and four required no further action.
2. Key issues
2.1This report provides an overview of key areas of concern relating to external inspections, reviews, and audits, including action taken or to be taken and the associated governance arrangements. This is intended to provide the Audit Committee with assurance that appropriate arrangements are in place for managing the Council’s response, in line with the Audit Committee’s responsibilities.
2.2Governance arrangements are in place for monitoring and managing external inspection, review, and audit recommendations within each directorate. Regular progress against the recommendations is also reported and considered by the Strategic Leadership Team.
2.3Seven new inspections, reviews, and audits have taken place since July 2023. These resulted in six recommendations or areas for improvement. Of these, one is complete; two are in progress and three are not yet scheduled to start.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Exclusion of the Press and Public- That, under Section 100A(4) of the Local Government Act 1972, the press and public be excluded from the meeting for...
Anti-Money Laundering Policy Review- (1) That the revised Anti-Money Laundering Policy be received and noted. (2) That the actions being undertaken to r...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.