Internal Audit Progress Report

Noted Finance 2 papers

AI summaryRotherham Audit Committee notes internal audit work from 1st May to 31st July 2026, with 14 audits finalised and new performance measures proposed.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedInternal Audit work and performance objectives noted
Money1,038 total audit daysDays allocated in 2026/27 audit plan
What happens nextNew staff member starts AugustReplaces retiree; addresses plan delivery gap
Who it affectsFive council directoratesOpen recommendations and ongoing audits

What was decided

The Committee noted the Internal Audit work undertaken from 1st May to 31st July 2026, including 14 finalised audits and the key issues arising. Report 2.1

The Committee noted the performance objectives of Internal Audit and the actions being taken by audit management to meet them, including a proposed balanced scorecard approach. Report 7.1, 7.2

The Committee considered Appendix G in private under Paragraph 7 of the Act, relating to crime prevention, investigation or prosecution.

Why

Internal Audit produced a risk-based plan for 2026/27, approved at the 17th March 2026 Committee, with no changes during this period. Report 1.1, 1.2

Performance against draft and final report timeliness targets (88% against 95%) was below target, partly due to a staff retirement in January and ongoing sickness absence. Report 5.1, P31, P32

CIPFA's external review advised updating performance measures to include stakeholder feedback, prompting a review of KPIs and a proposed balanced scorecard. Report 7.1, 7.2

What happens next

A new staff member will commence in August 2026, and a review of KPIs and a balanced scorecard approach is to be discussed with the Committee. Report 5.1, 7.2

Preparation for the next National Fraud Initiative data submission is ongoing in accordance with the national timetable in Autumn 2026. Report 4.2

External assessment review with a neighbouring Council is underway (target 30 September 2026), and assurance framework development continues (target 31 March 2027). Report P75, P77

The money

  • 140 days Adult Care, Housing and Public Health audit allocation Report P34
  • 95 days Childrens and Young Peoples Services audit allocation Report P36
  • 199 days Corporate Services audit allocation Report P37
  • 5 days Policy, Strategy and Engagement initial allocation Report P41
  • 80 days Regeneration and Environment audit allocation Report P41
  • 304 days Corporate and crosscutting reviews total days Report P45
  • 220 days Anti-Fraud and Corruption and Anti Money Laundering work Report P45
  • 1038 days Total Internal Audit Plan 2026/27 days Report P45

Options considered

  • Chosen: Retain current KPIs with adjustments to targets. Draft and final report targets increased to 95% to maintain timeliness focus Report P31, P32, P33
  • Chosen: Adopt a balanced scorecard approach covering quality, conformance and value for money. Recommended by CIPFA external review and aligns with Internal Audit strategy Report 7.1, 7.2
  • Chosen: Continue to report audit plan progress as a table rather than a KPI. Plan and timing of audits should remain flexible to meet stakeholder needs Report P28

Implications

  • Staffing: A new auditor will commence in August 2026, replacing a member of staff who retired in January 2026; an ongoing sickness absence continues to affect audit plan delivery. Report 5.1
  • Risk: Open recommendations totalled 42 as of 31 July 2026, including 2 high priority actions, with Corporate Services carrying the largest share (16). Report 6.3
  • Legal: One closed investigation in the period; no other investigations ongoing. No overpayments or fraud were identified from the 2024/25 National Fraud Initiative exercise. Report 4.1, 4.2
  • Equalities: Audits of safeguarding adults, 16/17 year old homelessness, and disability-related services all received substantial assurance, supporting protection of vulnerable groups. Report P46, P58

Who and where

  • Audit Committee members Report 7.1
  • Internal Audit team Report 5.1, P73
  • Schools in the borough, regarding finance, asset management and procurement queries Report P10
  • Adult Care, Housing and Public Health Directorate Report 6.3, P34
  • Children and Young People's Services Directorate Report 6.3, P36
  • Corporate Services Directorate Report 6.3, P37
  • Policy, Strategy and Engagement Directorate Report 6.3, P41
  • Regeneration and Environment Directorate Report 6.3, P41

Timeline

  • 17th March 2026: Internal Audit Plan 2026/27 presented to Audit Committee Report 1.1
  • 1st May to 31st July 2026: Reporting period for this Internal Audit Progress Report Report P3, 2.1
  • August 2026: New member of audit staff commences employment Report 5.1
  • 24 September 2026: Date of this Audit Committee meeting
  • 30 September 2026: Target completion of external assessment review and HIA PDR input actions Report P75, P79
  • Autumn 2026: Next National Fraud Initiative data submission Report 4.2
  • 31 March 2027: Target completion of assurance framework development action Report P77

Plain English for the jargon

  • NFI: National Fraud Initiative, a biannual data matching exercise conducted by the Cabinet Office
  • QAIP: Quality Assurance and Improvement Programme, the framework for ensuring internal audit quality
  • GIAS: Global Internal Audit Standards (UK Public Sector), the standards governing internal audit practice
  • KPI: Key Performance Indicator, a measurable value showing how effectively objectives are being met
  • BDR: Barnsley, Doncaster and Rotherham, the joint waste partnership arrangement
  • Dols: Deprivation of Liberty Safeguards, legal protections for people who lack capacity to consent to care arrangements
  • PSTN: Public Switched Telephone Network, the traditional copper-wire telephone system
  • DLT: Directorate Leadership Team, the senior management decision-making body for each directorate
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item44

Resolved

- (1) That the Internal Audit work undertaken since the last Audit Committee, 1 st May to 31st July, 2026, and the key issues arising therefrom be noted. (2) That the performance objectives of Internal Audit and the actions being taken by audit management in respect of meeting the performance objectives be noted. (Appendix G was considered in the absence of the press and public in accordance with Paragraph 7 of the Act (information relating to any action taken or to be taken in connection with the prevention, investigation or prosecution of crime).
Word for word from the decision Rotherham published for this meeting. Source: moderngov.rotherham.gov.uk

Follow this further

Built from Rotherham's papers

What the report saysPro

Report to Audit Committee

Appendix A

Internal Audit Progress Report

1st May – 31st July 2026 1. Internal Audit Annual Plan

1.1Internal Audit produced a risk-based Audit Plan for 2026/27 and presented it to the Audit Committee at its meeting on 17th March 2026. The plan is included at Appendix B.

1.2As the year progresses, changes are made to the plan to reflect emerging risks and changing priorities. Additional work requested is added to the plan and is resourced either through contingency or through the removal or deferral of lower risk audits. The audits from the 2025/26 plan that have not yet been finalised have been included in the current plan. There have been no other changes to the plan during this period.

2. Audit work undertaken during the period resulting in an assurance opinion

2.1Internal Audit provides an opinion on the control environment for systems or services which are subject to audit review. These are taken into consideration when forming our overall annual opinion on the Council’s control environment. There are four possible levels of assurance for any area under examination, these being “substantial assurance”, “reasonable assurance” “partial assurance” and “no assurance”. Audit opinions and a brief summary of all audit work concluded since the last Audit Committee are set out in Appendix C. 14 audits have been finalised since the last Audit Committee.

3. Details of other Internal Audit activities undertaken not resulting in an assurance opinion

3.1The table below sets out the work undertaken where audit have not issued an audit report with an opinion. This highlights the range of activities that Internal Audit have also undertaken in the period.

Audit Work Details of Work Undertaken, and Assurance Provided Completed Customer Services Participation in this regular meeting helps to ensure audit are Liaison meeting informed of the latest areas that Customer Services are working on, and where audit may wish to focus on at an early stage before changes to systems or ways of working are implemented. Audit Queries and Several schools’ queries have been received, mainly regarding Advice financial, asset management (inventory) and procurement processes and procedures. Internal Audit attended the Trade Rotherham meeting (schools buy-in system for RMBC services) where audit contributed to discussions on how schools will purchase services from RMBC in the future.

4. Anti-fraud and corruption work and investigations

4.1In addition to the planned audit assurance work, Internal Audit also carries out unplanned responsive work and investigations into any allegations of fraud, corruption or other irregularity. One investigation has been closed in the period. Please see Appendix G for the outcome of this investigation. There are no other investigations ongoing.

4.2The National Fraud Initiative (NFI) is a biannual data matching exercise conducted by the Cabinet Office. No overpayments or fraud were identified from the 2024/25 exercise. Preparation for the next data submission in Autumn 2026 is ongoing in accordance with the national timetable.

5. Internal Audit Performance Indicators, Post Audit Questionnaires and the Quality Improvement and Performance Plan (QAIP)

5.1The performance indicator results for the period are highlighted in Appendix D. These demonstrate good performance over all three indicators. Audit management continue to monitor the timeliness of reports issued following discussion with the relevant services. The number of audits finalised during the 2025/26 year is slightly behind that planned, largely due to the retirement of a member of staff in January and the difficulties in recruiting to this post. The new member of staff will commence in August. In addition, there is an ongoing sickness absence which is affecting audit plan delivery.

5.2The results from the post audit questionnaires received over the period have been positive (Appendix E).

5.3The updated QAIP Action Plan is attached at Appendix F. Good progress has been made implementing the improvement actions.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
IA Progress Report Appendices A+B+C+D+E+FReport 433 KB DownloadRead as text
PDF
Internal Audit Progress ReportReport 253 KB Download

At this meeting

Whole meeting

Who was there

0 of 7 attended
JB
Councillor Jamie BaggaleyChair, expected
RI
Councillor Rukhsana IsmailVice-Chair, expected
RE
Councillor Rob ElliottMember, expected
GM
Councillor Gina MonkMember, expected
AH
Alison HutchinsonGuest, expected
MO
Michael Olugbenga-BabalolaGuest, expected
KS
Katie SteadCouncil Staff, expected

On this subject at Rotherham

Search all
  1. Internal Audit Progress ReportThis decision
  2. Internal Audit Progress ReportNoted
  3. Internal Audit Charter, Internal Audit Quality Assurance and Improvement Plan (QAIP) and External Assessment against the Global Internal Audit Standards (UK Public Sector)Noted
  4. Internal Audit Progress Report for the period 1st November to 31st January 2026Noted
  5. Internal Audit Progress Report for the period 1st August to 31st October 2025Noted
  6. Internal Audit Progress ReportNoted

More from Rotherham Audit Committee

All decisions
MeetingDecisionOutcome
24 Sep 2026 Exclusion of the Press and Public- That, under Section 100A(4) of the Local Government Act 1972, the press and public be excluded from the meeting for... Decided Open
24 Sep 2026 Minutes of the previous meeting held on 28th July, 2026- That the minutes of the previous meeting of the Audit Committee be approved as a correct record of proceedings. Approved Open
24 Sep 2026 External Audit Progress Report and Sector Update- That the progress and sector updates be noted. Noted Open
24 Sep 2026 Code of Corporate Governance- That the refreshed version of the be received and noted. Noted Open
24 Sep 2026 Anti-Money Laundering Policy Review- (1) That the revised Anti-Money Laundering Policy be received and noted. (2) That the actions being undertaken to r... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies