Resolved
- That the update be received and the contents noted.
AI summaryRotherham council's Planning Board received and noted the Whitestone Solar Farm update [D]. The council remains a statutory consultee, while the Secretary of State will decide whether development consent is granted or refused [1.1] [5.9].
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
- That the update be received and the contents noted.
ROTHERHAM METROPOLITAN BOROUGH COUNCIL PLANNING BOARD
PLANNING, REGENERATION AND REPORT TO COMMITTEE TRANSPORT SERVICE 29th OCTOBER 2026
ITEM NO: 1 NO. OF APPENDICES: 2
Ref: RB2025/0603
Report Title Whitestone Solar Farm – Nationally Significant Infrastructure Project
1.0Background and Current Status
1.1Members will recall that the Whitestone Solar Farm proposal is being progressed as a Nationally Significant Infrastructure Project (NSIP), requiring a Development Consent Order (DCO) from the Secretary of State under the Planning Act 2008 rather than determination by RMBC. As a host authority, RMBC is a statutory consultee throughout the NSIP process and not the decision maker.
1.2Following acceptance of the application by the Planning Inspectorate (PINS), Interested Parties were invited to submit Relevant Representations identifying the principal issues they wish the Examining Authority to consider during the examination.
1.3RMBC submitted a Relevant Representation prepared by Stantec which is attached at Appendix 1.
1.4Following the close of the Relevant Representation period, the Examining Authority issued a Rule 6 Letter, published on the Planning Inspectorate website on 6 October 2026, setting out the procedural arrangements for the examination, including the Preliminary Meeting, Initial Assessment of Principal Issues and examination timetable, which is attached at Appendix 2.
2.0Summary of Relevant Representations
2.1The Council's Relevant Representation identifies a number of matters that it considers should be subject to scrutiny during the examination process. The issues raised are extensive and technical in nature and include, but are not limited to:
• Green Belt and Grey Belt considerations.
• Landscape and visual impacts.
• Agricultural land quality and the loss of Best and Most Versatile (BMV) land. • Ecology and biodiversity impacts.
• Heritage and archaeological impacts.
• Highways and transportation matters.
• Public rights of way.
• Flood risk and drainage.
• Noise, vibration and air quality.
• Glint and glare impacts.
• Battery Energy Storage System (BESS) safety and operation.
• Socio-economic considerations.
• Draft Development Consent Order (DCO) provisions and requirements.
• Cumulative impacts and assessment methodology. 2.2 Whilst the Council recognises the contribution the proposal could make towards renewable energy generation and national net zero objectives, it maintains that a number of significant issues remain unresolved and require further assessment through the examination process.
3.0Principal Issues Identified by the Examining Authority
3.1Following consideration of the Relevant Representations received, the Examining Authority has undertaken an Initial Assessment of Principal Issues for examination. The matters identified by the Examining Authority broadly reflect the issues raised by interested parties and include, but are not limited to:
• Green Belt considerations.
• Landscape and visual effects.
• Heritage and archaeology.
• Ecology and biodiversity.
• Agricultural land and soils.
• Traffic and transport.
• Water environment and drainage.
• Glint and glare.
• Population and human health.
• Battery storage and related safety matters. • Need for the development.
• Alternatives and site selection. 3.2 The Initial Assessment of Principal Issues is not intended to be exhaustive, and additional matters may be considered by the Examining Authority as the examination progresses. However, it provides a clear indication of the subjects that are likely to receive particular focus throughout the examination process
4.0The Rule 6 Letter
4.1A Rule 6 Letter is a procedural document issued under Rule 6 of the Infrastructure Planning (Examination Procedure) Rules 2010 and establishes how the examination will be conducted. It includes the draft timetable, hearing notifications, procedural directions, statements of common ground requirements and submission deadlines. 4.2 A copy of the letter is appended for information.
5.0Key Examination Milestones
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Report of the Service Director for Planning, Regeneration and Transport: Whitestone Solar Farm: Nationally Significant Infrastructure Project UpdateReport | 76 KB | DownloadRead as text |
PDF |
Whitestone Appendix 1: RRAppendix | 4.7 MB | Download |
PDF |
Whitestone Appendix 2: Rule 6 letterAppendix | 270 KB | Download |
Follow Planning Board at Rotherham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 29 Oct 2026 | Minutes of the previous meeting held on 8th October 2026- That the minutes of the previous meeting of the Planning Regulatory Board held on Thursday, 8 th October, 2026, be ... | Approved | Open |
| 29 Oct 2026 | Development Proposals- (1 ) That , on the development proposals now considered, the requisite notices be issued and be made available on t... | Approved | Open |
| 8 Oct 2026 | Minutes of the previous meeting held on 17th September, 2026- That the minutes of the previous meeting of the Planning Regulatory Board held on Thursday, 17 th September, 2026, ... | Approved | Open |
| 8 Oct 2026 | Development Proposals- (1) That, on the development proposals now considered, the requisite notices be issued and be made available on the... | Approved | Open |
| 8 Oct 2026 | Updates- (1) That the update be received and the contents noted. (2) That the detail relating to the Rule 6 letter and proce... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.