DECISION THAT THE EXECUTIVE MANAGER – COMMUNITIES BE DELEGATED AUTHORITY TO GRANT OUTLINE PLANNING PERMISSION, SUBJECT TO THE PRIOR SIGNING OF A S106 AGREEMENT, AND THE FOLLOWING CONDITIONS: 1. The development shall commence within five years from the date of this permission or before the expiration of two years from the date of the approval of the first reserved matters whichever is the later. [To comply with the requirements of section 92 of the Town and Country Planning Act 1990 (as amended) and to ensure the development will be satisfactory]. 2. The first application for approval of reserved matters for the first phase of the development (as detailed pursuant to the phasing programme to be approved pursuant to condition 8) shall be submitted no later than three years from the date of this permission and all subsequent reserved matters applications shall be submitted by no later than 15 years from the date of this permission. [To comply with the requirements of section 92 of the Town and Country Planning Act 1990 (as amended) and to ensure the development will be satisfactory]. 3. The development hereby permitted shall only be undertaken in general accordance with the details as set out in the following: - Parameters Plan 1667-P-1000 rev I and accompanying information (including heights) as set out in the Detailed Description of Development within the EIA Design and Access Statement (Revised Jan 2018 – ref 1667 DAS REV 1) ... view the full minutes text for item 33.
Word for word from the decision Rushcliffe published for this meeting.Source: democracy.rushcliffe.gov.uk
Infrastructure requirements and S106 Draft Heads of Terms Summary 14/01417/OUT Land East and West of Nottingham Road South of Clifton WITHOUT PREJUDICE AND SUBJECT TO CONTRACT work in progress document and subject to change. Position at 8/01/2018
Item/Policy Detail/requirement Financial Developer Borough Trigger contribution position Council sought position Public Open Maintenance - management company On site provision Masterplan Satisfied Submit scheme, including Space/ shows indicative level and triggers for implementation Landscaping provision. general and management before and SuDS approach commencement of acceptable. residential development or associated commercial. Equipped To be determined by scheme and On site provision Community/ Satisfied Submit scheme, including play space agreed at Reserved Matters stage. destination park level and triggers for implementation, Ongoing maintenance needs to be and Local Play general before commencement of achieved. Management company Areas Equipped approach residential development. required. for all ages – acceptable. masterplan shows indicative provision. Allotments Shown in masterplan, would require On site provision Shown on Location Phasing to be agreed - perimeter fencing, planting, haulage masterplan appropriate Submit scheme, including way, water supply and car parking. and will triggers for implementation potentially and details of management, assist in before commencement of management residential development. Education PRIMARY Two potential Developer Masterplan Prior to commencement of The County Council previously scenarios position – amended to development – feasibility requested the provision of two primary provided:- preferred option reflect need study payment of £150,000 schools (one 420 place and one 210 in relation to for a 3 HA Option 1 place with nursery provision) on two 2 Total build cost of viability is the site. Phase 1 land and funding hectare sites. The County Councils £8,482,000( plus second option – Provision is for core building for 3FE preferred approach is now for one three £150,000 feasibility although a justified on primary school to be built form Entry (630 place primary school) study- = higher overall site. with five classrooms fully to serve the development which would £8,632,000 or as figure includes fitted and external shell for require a single three hectare site, alternative benefits in terms remaining classrooms ( on located in association with the first approach to design of the deferral of completion of 478 dwellings)
1 Infrastructure requirements and S106 Draft Heads of Terms Summary 14/01417/OUT Land East and West of Nottingham Road South of Clifton WITHOUT PREJUDICE AND SUBJECT TO CONTRACT work in progress document and subject to change. Position at 8/01/2018
Item/Policy Detail/requirement Financial Developer Borough Trigger contribution position Council sought position phase of development. and cost of the payments. £ 6,524,000 school which Sufficient capacity existing to results in lower Phase 2 – funding for accommodate children from up to 478 initial costs but additional five classrooms to dwellings in existing schools (site is higher cost of total be fitted out ( on completion within Gotham Primary) build - £9,856,000 of 1278 dwellings) £ + £150,000 630,000 NCC have confirmed that there is no feasibility study = longer a requirement for nursery £10,006,000 Phase 3 funding for provision. It is not a statutory duty on additional five classrooms to the LEA to make such provision. be fitted out (on completion of 1878 dwellings) £691,000
Phase 4 – final six classroom to be fitted out and any other outstanding provision on completion of 2478 dwellings £637,000
Option 2 Alternative – it would be possible to build the core area and five classrooms within phase 1 at an cost of £4,533,000 and complete the additional classrooms as extensions
Phase 1 – new build £4,533,000 Phase 2 extension £
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Outline application for the development of a sustainable urban extension comprising residential development up to a maximum of 3000 dwellings; employment development incorporating a maximum of 100,000sqm of B1, B2 & B8 floorspace; retail development (A1 to A5) up to a maximum of 2500sqm of floorspacReport
33Outline application for the development of a sustainable urban extension comprising residential development up to a maximum of 3000 dwellings;This decision
Who was there
13 of 16 attended
RB
Councillor Richard ButlerChairman, present
JS
Councillor John StockwoodVice-Chairman, present
BB
Councillor Brian BuschmanCommittee Member, present
NC
Councillor Neil ClarkeCommittee Member, present
RJ
Councillor Rod JonesCommittee Member, present
JG
Councillor Jean GreenwoodCommittee Member, apologies, sent representative
SH
Councillor Sue HullCommittee Member, present as substitute
MM
Councillor Mrs Marie MalesCommittee Member, present
SM
Councillor Sue MallenderCommittee Member, apologies, sent representative
ME
Councillor Martin EdwardsCommittee Member, present
MJ
Councillor Mrs Jean SmithCommittee Member, present
MM
Councillor Mrs Maureen StockwoodCommittee Member, present as substitute
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.