It was RESOLVED that a) The report of the Executive Manager – Communities be noted. b) Trent Bridge Community Trust attempt to re-engage with Brookside Primary School in East Leake c) Consideration be given to the Service Level Agreements being extended to include the village of Ruddington. d) The work of the partnership be endorsed.
Word for word from the decision Rushcliffe published for this meeting.Source: democracy.rushcliffe.gov.uk
1.1This report will provide Members with an opportunity to review the partnership with Trent Bridge Community Trust who provide both the Council’s service level agreements for children and young people, namely the Positive Futures and YouNG projects.
1.2Representatives of Trent Bridge Community Trust will provide a presentation to Members on performance covering the period 2017/18 across key service level agreement performance indicators on both SLA’s and outline future plans and initiatives.
1.3Members are requested to comment on performance to date and any areas where the partnership could be strengthened to achieve improved outcomes.
Recommendation
It is RECOMMENDED that Members consider and make comments on the presentation made by Trent Bridge Community Trust and endorse the work of the Positive Futures and YouNG projects.
Reasons for recommendation
3.1Performance review of Positive Futures and the YouNG project at scrutiny and by officers have identified that outputs over the range of targets have consistently been achieved or exceeded.
4. Supporting Information
4.1In June 2016, Council supported the extension of the Positive Futures programme from January 2017 to December 2020 (4 years delivery) at a cost of £110,000 per annum. Council supported targeting Positive Future work at young people aged 9 years and above within the catchment area of East Leake Academy, South Nottinghamshire Academy, South Wolds Academy and Toot Hill School.
4.2In January 2018, Council supported the establishment of the YouNG Project from April 2018 to December 2020 (2 year 9 months delivery) at a cost of £82,000 per annum. Council supported targeting YouNG at young people aged 12 years and above across the entire borough with a particular focus on employability and work experience.
4.3The Council’s Corporate Strategy has a strategic task to “facilitate activities for children and young people to enable them to reach their potential”. By bringing both the Positive Futures and YouNG project SLA’s under one arm’s length body it with a defined management structure it has provided the opportunity for improved co-ordination, economies of scale and increased opportunities for levering in external funding due to the Trent Bridge Community Trust being a registered charity.
5. Alternative options considered and reasons for rejection
5.1Despite some significant successes with the YouNG project, progress and achievement, the desire to establish an independent/ arm’s length body proved difficult to achieve. The Community Development Group met over the course of 2017 to scrutinise the activity of YouNG and a number of options regarding how YouNG could be delivered in the future were considered and evaluated. This coupled with the strong performance of the Positive Future programme was the preferred option of the Community Development Group and was recommended to and approved by Cabinet.
6. Risks and Uncertainties
6.1There is a risk that operational problems may be encountered by Trent Bridge Community Trust delivering either the Positive Futures or YouNG projects, or partner agencies could disengage with the programme which could affect achievement of the outcome targets. This is not identified as a significant risk due to the programme of area-based partnership meetings and employment of experienced staff.
7. Implications
Financial implications
7.1.1. The £110k per annum commitment is funded from the revenue budget underspend position and is appropriated each year from the Council’s Organisation Stabilisation Revenue. The budget for the YouNG Project of £82k per annum is included as part of the revenue budget. Both allocations should be assessed annually as part of the budgetary process taking into account challenges going forward and is subject to the break clause as stated at paragraph 7.2.1
Legal implications
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
South Notts Community Safety UpdateRESOLVED that: a) The report of the Executive Manager – Neighbourhoods be noted b) The work of the South Notts Commun...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.