RESOLVED that: a) the priority focus on the Council’s own direct operations and the mitigation required to achieve carbon neutral status by 2030 be endorsed. b) officers undertake a further review in 2025 regarding the potential adoption of a Borough-wide net zero carbon emissions target c) the proposed process to produce a new carbon management action plan and their interest in attending training be noted. d) officers report back to scrutiny in January 2020 with a draft action plan (including resource implications) to enable members to make their recommendations to Cabinet in March 2020
Word for word from the decision Rushcliffe published for this meeting.Source: democracy.rushcliffe.gov.uk
1.1On 7 March 2019, Rushcliffe Borough Council passed the following motion;
In the light of the recent Intergovernmental Panel on Climate Change (IPCC) report, declaring a climate emergency, Rushcliffe Borough Council will evaluate the implications of the report and review its 2010 Carbon Management Plan. The review should be undertaken by a relevant scrutiny group, and their findings shall be considered by the Cabinet by no later than March 2020. This Council calls upon the designated scrutiny group to consider the Council setting a carbon neutral target to be achieved by 2030.
The commitment to review and implement a refreshed target should also be integrated into the Council’s commitment and leadership to parish councils, business and strategic partners, to deliver widespread carbon reductions across the borough. Rushcliffe Borough Council will continue to call on the Government to provide the necessary powers and resources to make local action on climate change easier.
1.2This report outlines the Council’s current strategic framework and recent performance in reducing carbon emissions from the Council’s direct operations. A presentation will be delivered to the Group by the Community Development Manager and the Environmental Sustainability Officer which will cover the scale of the challenge faced, local emissions, delivery of the existing action plan and the proposed scope, approach and resource considerations of developing a new action plan capable of achieving carbon neutral status by 2030.
Recommendation
It is RECOMMENDED that the Communities Scrutiny Group:
a) Endorses the priority focus on the Council’s own direct operations and the mitigation required to achieve carbon neutral status by 2030
b) Requests that officers undertake a further review in 2025 regarding the potential adoption of a Borough-wide net zero carbon emissions target c) Comments on the proposed process to produce a new carbon management action plan and indicates their interest in attending training
d) Requests that officers report back to scrutiny in January 2020 with a draft action plan (including resource implications) to enable members to make their recommendations to Cabinet in March 2020
Reasons for recommendation
3.1On 26 June 2019, The Climate Change Act 2008 (2050 Target Amendment) Order 2019 was enacted. This Order changes the Climate Change Act 2008 to require that the net UK carbon account for the year 2050 must be 100% lower than the 1990 baseline, i.e net zero emissions.
3.2The UK Committee on Climate Change states: “There is a crucial role for local authorities in reducing emissions to meet national carbon budgets” and “The focus of a local authority low-carbon plan should be emissions drivers over which they have significant influence. In particular … residential and non- residential buildings, surface transport, waste and own estate”.
4. Supporting Information
4.1The Council’s Carbon Management Plan was approved by Cabinet in June 2011, with a target to reduce carbon emissions by 15% by 2015 and a longer term target of 30% by 2020, from our base year of 2008/09, in line with Government guidance at that time.
4.2It was agreed in November 2013 that future actions for the Carbon Management Plan be incorporated into the Climate Change Strategy Action Plan which runs to 2020. A significant part of the Climate Change Strategy Action Plan has now been completed, including:
a. Moving the main council offices to a new building b. Redeveloping leisure provision in West Bridgford c. Working with partners to deliver affordable warmth d. Purchasing cleaner more carbon efficient vehicles.
4.3However, some parts of the Action Plan have not yet been fully delivered, including:
a. Redeveloping leisure provision in Bingham b. Redeveloping the depot (services moving during 2019) c. Staff and user travel plan at the Arena d. Adoption of the local plan (Part 2 planned for adoption during 2019)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.