CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Rushcliffe Borough Council
Governance Scrutiny Group, Tuesday 1 November 2022 at 7.00pm

Internal Audit Progress Report

Noted Scrutiny 2 papers

Governance Scrutiny Group noted this item on Tuesday 1 November 2022. Below is the council's own wording, with the papers it was decided on.

Item13

Resolved

RESOLVED that the Group noted the progress report for 2022/23 prepared by the Council’s Internal Auditor.
Word for word from the decision Rushcliffe published for this meeting. Source: democracy.rushcliffe.gov.uk

Follow this further

Built from Rushcliffe's papers

What the report saysPro

Report to Governance Scrutiny Group

INTERNAL AUDIT PROGRESS REPORT Rushcliffe Borough Council SEPTEMBER 2022 1 INTERNAL AUDIT PROGRESS REPORT

CONTENTS

SUMMARY OF 2022/2023 WORK ............................................................................... 2 REVIEW OF 2022/2023 WORK ................................................................................. 3 PROJECT MANAGEMENT ....................................................................................... 4 ENVIRONMENT .................................................................................................. 6 RISK MANAGEMENT ............................................................................................. 9 SECTOR UPDATE ............................................................................................... 11 KEY PERFORMANCE INDICATORS ............................................................................. 14 APPENDIX 1 - DEFINITIONS ................................................................................... 15

1 2 INTERNAL AUDIT PROGRESS REPORT

SUMMARY OF 2022/2023 WORK

INTERNAL AUDIT This report is intended to inform the Audit Committee of progress made against the 2022/2023 internal audit plan. It summarises the work we have done, together with our assessment of the systems reviewed and the recommendations we have raised. Our work complies with Public Sector Internal Audit Standards. As part of our audit approach, we have agreed terms of reference for each piece of work with the risk owner, identifying the headline and sub-risks, which have been covered as part of the assignment. This approach is designed to enable us to give assurance on the risk management and internal control processes in place to mitigate the risks identified.

INTERNAL AUDIT METHODOLOGY Our methodology is based on four assurance levels in respect of our overall conclusion as to the design and operational effectiveness of controls within the system reviewed. The assurance levels are set out in Appendix 1 of this report, and are based on us giving either ‘substantial’, ‘moderate’, ‘limited’ or ‘no’. The four assurance levels are designed to ensure that the opinion given does not gravitate to a ‘satisfactory’ or middle band grading. Under any system we are required to make a judgement when making our overall assessment.

2022/2023 INTERNAL AUDIT PLAN We are now making good progress in the delivery of 2022/2023 audit plan, and we are pleased to present the following reports to this Audit Committee meeting:

 Project Management

 Risk Management

 Environment

Planning and/or fieldwork is underway in respect of the following audits:

 Health and Wellbeing

 Safeguarding

 IT Asset Management

 Main Financial Systems

We anticipate presenting these reports at future Audit Committee meetings.

CHANGES TO THE 2022/2023 INTERNAL AUDIT PLAN No changes to note.

2 3 INTERNAL AUDIT PROGRESS REPORT

REVIEW OF 2022/2023 WORK

AUDIT AUDIT PLANNING FIELDWORK REPORTING DESIGN EFFECTIVENESS COMMITTEE

Fraud Report June 2022 N/A N/A

Project September 2022 M S Management (1)

Environment September 2022 L S M

Risk Management September 2022 S S

Health and TBC Wellbeing

Safeguarding TBC

Main Financial TBC Systems (MFS)

IT Asset TBC Management

Sustainable TBC Warmth Funding

Channel Shift TBC

Project TBC Management (2)

3 4 INTERNAL AUDIT PROGRESS REPORT

PROJECT MANAGEMENT

CRR REFERENCE: Risk 6 – Ability to deliver Bingham Arena and Enterprise Centre project on time and within budget Risk 18 – Failure to deliver the Transformation Strategy Risk 19 – Failure to deliver and manage significant projects

Design Opinion M Moderate Design Effectiveness S Substantial

Recommendations 0 1 2

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Enc. 1 for Internal Audit Progress ReportReport 932 KB DownloadRead as text
PDF
Internal Audit Progress ReportReport 241 KB Download

At this meeting

Whole meeting

Who was there

5 of 17 attended
DV
Councillor Davinder VirdiChairman, present
RA
Councillor Reg AdairCommittee Member, apologies
KB
Councillor Kevin BeardsallCommittee Member, absent
DS
Councillor David SimmsCommittee Member, absent
MM
Councillor Mrs Maureen StockwoodCommittee Member, present
PG
Councillor Penny GowlandVice-Chairman, present
LH
Councillor Lizzie HowittCommittee Member, apologies
KS
Councillor Kevin ShawCommittee Member, present
JS
Councillor John StockwoodCommittee Member, present
LA
Leanne AshmoreOfficer, expected
PL
Peter LinfieldOfficer, in attendance
CC
Charlotte Caven-AtackOfficer, in attendance

All 17 on the meeting page

On this subject at Rushcliffe

Search all
  1. Internal Audit Progress ReportThis decision
  2. Internal Audit Progress Report Quarter 1Agreed
  3. Internal Audit Annual Report 2025/26Noted
  4. Internal Audit Progress ReportDecided
  5. Internal Audit StrategyApproved
  6. Internal Audit Progress ReportDecided

More from Rushcliffe Governance Scrutiny Group

All decisions
MeetingDecisionOutcome
24 Sep 2026 Internal Audit Progress Report Quarter 1It was RESOLVED that the Governance Scrutiny Group: a) considered the Quarter 1 progress report for 2026/27 (Appendix... Agreed Open
24 Sep 2026 Audit Completion Report 2025/26It was RESOLVED that Governance Scrutiny Group: a) approved the findings of Forvis Mazars Audit Completion Report (Ap... Approved Open
24 Sep 2026 Draft Auditor's Annual Report 2025/26RESOLVED that the Governance Scrutiny Group noted the receipt of the Annual Audit Report at Appendix A. Noted Open
24 Sep 2026 Going Concern Assessment 2025/26RESOLVED that the Governance Scrutiny Group noted the positive outcome of the assessment of Rushcliffe Borough Counci... Noted Open
24 Sep 2026 Capital and Investment Strategy - Quarter 1 Report 2026/27RESOLVED that the Governance Scrutiny Group noted the Capital and Investment Strategy update position as at 30 June 2... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies