INTERNAL AUDIT PROGRESS REPORT Rushcliffe Borough Council SEPTEMBER 2022 1 INTERNAL AUDIT PROGRESS REPORT
CONTENTS
SUMMARY OF 2022/2023 WORK ............................................................................... 2 REVIEW OF 2022/2023 WORK ................................................................................. 3 PROJECT MANAGEMENT ....................................................................................... 4 ENVIRONMENT .................................................................................................. 6 RISK MANAGEMENT ............................................................................................. 9 SECTOR UPDATE ............................................................................................... 11 KEY PERFORMANCE INDICATORS ............................................................................. 14 APPENDIX 1 - DEFINITIONS ................................................................................... 15
1 2 INTERNAL AUDIT PROGRESS REPORT
SUMMARY OF 2022/2023 WORK
INTERNAL AUDIT This report is intended to inform the Audit Committee of progress made against the 2022/2023 internal audit plan. It summarises the work we have done, together with our assessment of the systems reviewed and the recommendations we have raised. Our work complies with Public Sector Internal Audit Standards. As part of our audit approach, we have agreed terms of reference for each piece of work with the risk owner, identifying the headline and sub-risks, which have been covered as part of the assignment. This approach is designed to enable us to give assurance on the risk management and internal control processes in place to mitigate the risks identified.
INTERNAL AUDIT METHODOLOGY Our methodology is based on four assurance levels in respect of our overall conclusion as to the design and operational effectiveness of controls within the system reviewed. The assurance levels are set out in Appendix 1 of this report, and are based on us giving either ‘substantial’, ‘moderate’, ‘limited’ or ‘no’. The four assurance levels are designed to ensure that the opinion given does not gravitate to a ‘satisfactory’ or middle band grading. Under any system we are required to make a judgement when making our overall assessment.
2022/2023 INTERNAL AUDIT PLAN We are now making good progress in the delivery of 2022/2023 audit plan, and we are pleased to present the following reports to this Audit Committee meeting:
Project Management
Risk Management
Environment
Planning and/or fieldwork is underway in respect of the following audits:
Health and Wellbeing
Safeguarding
IT Asset Management
Main Financial Systems
We anticipate presenting these reports at future Audit Committee meetings.
CHANGES TO THE 2022/2023 INTERNAL AUDIT PLAN No changes to note.
2 3 INTERNAL AUDIT PROGRESS REPORT
REVIEW OF 2022/2023 WORK
AUDIT AUDIT PLANNING FIELDWORK REPORTING DESIGN EFFECTIVENESS COMMITTEE
Fraud Report June 2022 N/A N/A
Project September 2022 M S Management (1)
Environment September 2022 L S M
Risk Management September 2022 S S
Health and TBC Wellbeing
Safeguarding TBC
Main Financial TBC Systems (MFS)
IT Asset TBC Management
Sustainable TBC Warmth Funding
Channel Shift TBC
Project TBC Management (2)
3 4 INTERNAL AUDIT PROGRESS REPORT
PROJECT MANAGEMENT
CRR REFERENCE: Risk 6 – Ability to deliver Bingham Arena and Enterprise Centre project on time and within budget Risk 18 – Failure to deliver the Transformation Strategy Risk 19 – Failure to deliver and manage significant projects
Design Opinion M Moderate Design Effectiveness S Substantial
Recommendations 0 1 2
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Enc. 1 for Internal Audit Progress ReportReport | 932 KB | DownloadRead as text |
PDF |
Internal Audit Progress ReportReport | 241 KB | Download |
Follow Governance Scrutiny Group at Rushcliffe and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 24 Sep 2026 | Internal Audit Progress Report Quarter 1It was RESOLVED that the Governance Scrutiny Group: a) considered the Quarter 1 progress report for 2026/27 (Appendix... | Agreed | Open |
| 24 Sep 2026 | Audit Completion Report 2025/26It was RESOLVED that Governance Scrutiny Group: a) approved the findings of Forvis Mazars Audit Completion Report (Ap... | Approved | Open |
| 24 Sep 2026 | Draft Auditor's Annual Report 2025/26RESOLVED that the Governance Scrutiny Group noted the receipt of the Annual Audit Report at Appendix A. | Noted | Open |
| 24 Sep 2026 | Going Concern Assessment 2025/26RESOLVED that the Governance Scrutiny Group noted the positive outcome of the assessment of Rushcliffe Borough Counci... | Noted | Open |
| 24 Sep 2026 | Capital and Investment Strategy - Quarter 1 Report 2026/27RESOLVED that the Governance Scrutiny Group noted the Capital and Investment Strategy update position as at 30 June 2... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.