Internal Audit Progress Report Q4

Decided Scrutiny 2 papers

Governance Scrutiny Group decided this item on Thursday 29 June 2023. Below is the council's own wording, with the papers it was decided on.

Item4

Resolved

RESOLVED that Governance Scrutiny Group notes the Quarter 4 progress report for 2022/23 (Appendix A) prepared by the Council’s Internal Auditor.
Word for word from the decision Rushcliffe published for this meeting. Source: democracy.rushcliffe.gov.uk

Follow this further

Built from Rushcliffe's papers

What the report saysPro

Report to Governance Scrutiny Group

OFFICIAL

INTERNAL AUDIT PROGRESS REPORT RUSHCLIFFE BOROUGH COUNCIL JUNE 2023 OFFICIAL 1 INTERNAL AUDIT PROGRESS REPORT

CONTENTS

SUMMARY OF 2022/2023 WORK ............................................................................... 2 REVIEW OF 2022/2023 WORK ................................................................................. 3 REVIEW OF 2023/2024 WORK ................................................................................. 4 CHANNEL SHIFT ................................................................................................. 5 SAFEGUARDING ................................................................................................. 7 SECTOR UPDATE ............................................................................................... 13 KEY PERFORMANCE INDICATORS ............................................................................. 16 APPENDIX 1 ..................................................................................................... 17

1 OFFICIAL 2 INTERNAL AUDIT PROGRESS REPORT

SUMMARY OF 2022/2023 WORK

INTERNAL AUDIT This report is intended to inform the Governance Scrutiny Group of progress made against the 2022/2023 internal audit plan and the 2023/24 internal audit plan. It summarises the work we have done, together with our assessment of the systems reviewed and the recommendations we have raised. Our work complies with Public Sector Internal Audit Standards. As part of our audit approach, we have agreed terms of reference for each piece of work with the risk owner, identifying the headline and sub-risks, which have been covered as part of the assignment. This approach is designed to enable us to give assurance on the risk management and internal control processes in place to mitigate the risks identified.

INTERNAL AUDIT METHODOLOGY Our methodology is based on four assurance levels in respect of our overall conclusion as to the design and operational effectiveness of controls within the system reviewed. The assurance levels are set out in Appendix 1 of this report, and are based on us giving either ‘substantial’, ‘moderate’, ‘limited’ or ‘no’. The four assurance levels are designed to ensure that the opinion given does not gravitate to a ‘satisfactory’ or middle band grading. Under any system we are required to make a judgement when making our overall assessment.

2022/2023 INTERNAL AUDIT PLAN We have substantially completed the work for the 2023/2024 internal audit plan, and we are pleased to present the following reports to this Governance Scrutiny Group meeting:

 Channel Shift

 Safeguarding

 Sustainable Warmth Funding

 Follow Up Report

 Head of Internal Audit Opinion

2023/2024 INTERNAL AUDIT PLAN As part of the 2023/24 internal audit plan we have completed and are pleased to present the following report to the Governance Scrutiny Group:

 Fraud Report.

We have commenced our scoping and planning of audits for 2023/24 reviews and expect to present the following reports the next Governance Scrutiny Group meetings:

 Reconciliations

 Main Financial Systems

 Markets.

2 OFFICIAL 3 INTERNAL AUDIT PROGRESS REPORT

REVIEW OF 2022/2023 WORK

AUDIT AUDIT PLANNING FIELDWORK REPORTING DESIGN EFFECTIVENESS COMMITTEE

Fraud Report June 2022 N/A N/A

Project September 2022 M S Management (1)

Environment September 2022 S M

Risk Management September 2022 S S

Health and November 2022 M M Wellbeing

Safeguarding June 2023 S M

Main Financial February 2023 S S Systems (MFS)

IT Asset November 2022 M S Management

Sustainable June 2023 S S Warmth Funding

Channel Shift June 2023 S S

Project TBC Management (2)

3 OFFICIAL 4 INTERNAL AUDIT PROGRESS REPORT

REVIEW OF 2023/2024 WORK

AUDIT AUDIT PLANNING FIELDWORK REPORTING DESIGN EFFECTIVENESS COMMITTEE

Country Parks February 2024 Income

Fleet Management February 2024 & Air Pollution

Fraud Report June 2023 N/A N/A

Governance of Partnership November 2023 Arrangements

IT General Controls June 2024

Main Financial September 2023 Systems

Markets September 2023

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Enc. 1 for Internal Audit Progress Report Q4Report 1 MB DownloadRead as text
PDF
Internal Audit Progress Report Q4Report 293 KB Download

At this meeting

Whole meeting

Who was there

9 of 18 attended
AE
Councillor Andy EdyveanChair, present
PG
Councillor Penny GowlandVice-Chair, present
TB
Councillor Ted BirchCommittee Member, present
SC
Councillor Steve CalvertCommittee Member, present
HO
Councillor Hari OmCommittee Member, present
NR
Councillor Nigel ReganCommittee Member, present
DS
Councillor David SimmsCommittee Member, present
CT
Councillor Carys ThomasCommittee Member, present
GW
Councillor Gordon WheelerCommittee Member, present
CC
Charlotte Caven-AtackOfficer, expected
PL
Peter LinfieldOfficer, in attendance
LA
Leanne AshmoreOfficer, in attendance

All 18 on the meeting page

On this subject at Rushcliffe

Search all
  1. Internal Audit Progress Report Q4This decision
  2. Internal Audit Progress Report Quarter 1Agreed
  3. Internal Audit Annual Report 2025/26Noted
  4. Internal Audit Progress ReportDecided
  5. Internal Audit StrategyApproved
  6. Internal Audit Progress ReportDecided

More from Rushcliffe Governance Scrutiny Group

All decisions
MeetingDecisionOutcome
24 Sep 2026 Internal Audit Progress Report Quarter 1It was RESOLVED that the Governance Scrutiny Group: a) considered the Quarter 1 progress report for 2026/27 (Appendix... Agreed Open
24 Sep 2026 Audit Completion Report 2025/26It was RESOLVED that Governance Scrutiny Group: a) approved the findings of Forvis Mazars Audit Completion Report (Ap... Approved Open
24 Sep 2026 Draft Auditor's Annual Report 2025/26RESOLVED that the Governance Scrutiny Group noted the receipt of the Annual Audit Report at Appendix A. Noted Open
24 Sep 2026 Going Concern Assessment 2025/26RESOLVED that the Governance Scrutiny Group noted the positive outcome of the assessment of Rushcliffe Borough Counci... Noted Open
24 Sep 2026 Capital and Investment Strategy - Quarter 1 Report 2026/27RESOLVED that the Governance Scrutiny Group noted the Capital and Investment Strategy update position as at 30 June 2... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies