AI summaryCabinet retains the Ratcliffe on Soar Local Development Order unchanged after its three-year review, with continued monitoring and no new amendments at present.
Written from the decision and the officer reportPDF Pro
OutcomeDecidedNo amendments after three-year review
MoneyNot stated
What happens nextContinued monitoring, five-yearly reviewsFuture amendments if justified
Who it affectsSite owner, Freeport, residentsRatcliffe on Soar redevelopment
What was decided
Cabinet agreed the Ratcliffe on Soar Local Development Order should remain in force in its current form, with no amendments at this stage. Report P6
Cabinet agreed continued monitoring of the LDO, with any future amendments considered should circumstances or evidence justify changes. Report P7
The decision completes the third anniversary review of the LDO required by Condition 1. Report 1.2, 4.5
Why
No evidence has emerged that the LDO is failing to operate as intended, and no further operational concerns have been identified since adoption. Report 3.2, 4.18
Amendments approved in May 2026 already addressed the main issues identified, including enabling data centres on the southern part of the site, earlier environmental mitigation works, and plot-by-plot Local Labour Agreements. Report 3.2, 4.6, 4.7, 4.8, 4.9
The policy basis remains valid, aligning with national policy on advanced manufacturing, low carbon energy, and digital infrastructure, and with the site's proposed allocation in the emerging Greater Nottingham Strategic Plan. Report 3.3, 4.14, 4.15, 4.19
What happens next
The LDO will continue to be monitored, with the next formal review at five-yearly intervals, and the next one due after the current third anniversary review. Report 1.2, 4.4, P7
Uniper is conducting its own review of the LDO; any resulting request for amendments would be considered by the Council and would require public consultation. Report 4.17
The Greater Nottingham Strategic Plan is undergoing public examination, and any implications for the LDO can be considered if the Inspectors reach different conclusions. Report 4.15
Options considered
Chosen: Retain the LDO in its current form. No justification for change; amendments already address identified issues; policy basis remains valid. Report P6, P31
Rejected: Amend the LDO. No justification has been identified for further amendments at this stage. Report P31
Rejected: Revoke the LDO. Would remove the established planning framework for the site and be inconsistent with the emerging Greater Nottingham Strategic Plan allocation. Report P31
Implications
Financial: The review work involved only Council officer time, with no further work arising at this stage. Report P34
Legal: Approval of an LDO and any amendments is an executive function, to be taken by Cabinet, confirmed by external legal advice. Report P36, P37
Equalities: The LDO supports the inclusive growth theme of the East Midlands Freeport, with potential benefits for job quality and accessibility. Report P38
Risk: The risk that the former power station site remains undeveloped is mitigated by retaining the LDO, which provides planning certainty. Report P32
Other: The minimum 10% Biodiversity Net Gain requirement under the LDO remains unaltered. Report P41
Other: There are no crime and disorder implications, and Local Government Reorganisation is not applicable. Report P39, P43
Who and where
Uniper, the site owner, which is redeveloping the former power station Report 4.6, 4.11, 4.12
The East Midlands Freeport, which the LDO is designed to support Report 1.1, 4.3
Future developers of plots on the Ratcliffe on Soar site Report 4.2
Local residents, who may benefit from new jobs and improved infrastructure Report P45
Timeline
13 July 2023: Rushcliffe Borough Council adopted the Ratcliffe on Soar Local Development Order. Report 1.1, 4.1
November 2025 to January 2026: Public consultation held on the proposed amendments to the LDO. Report 4.7
12 May 2026: Cabinet approved the amendments to the LDO, enabling data centres on the southern part, earlier environmental mitigation, and plot-by-plot Local Labour Agreements. Report 1.3, 4.7
2026-10-13: Cabinet considered and completed the third anniversary review of the LDO, retaining it unchanged. Report 4.5
2029: Demolition of the former power station is currently expected to be completed. Report 4.12
Every five years after the third anniversary: Subsequent reviews of the LDO are required by Condition 1, with the LDO otherwise in force for 25 years from adoption. Report 1.2, 4.4
Plain English for the jargon
Local Development Order (LDO): A order made by a local planning authority that grants planning permission for specified types of development within a defined area, in this case equivalent to outline planning consent.
Certificate of Compliance: An application equivalent to the approval of reserved matters under an outline planning consent, used to secure detailed approval for proposals under the LDO.
Greater Nottingham Strategic Plan (GNSP): The emerging local plan covering Greater Nottingham, currently undergoing public examination, which proposes to allocate the Ratcliffe on Soar site.
East Midlands Freeport: A designated Freeport area in the East Midlands, for which the LDO was prepared and whose inclusive growth aims the LDO supports.
Local Labour Agreement (LLA): An agreement on local employment arrangements on the site, which under the May 2026 amendment can be agreed on a plot-by-plot basis.
Biodiversity Net Gain (BNG): A requirement for development to deliver a measured improvement in biodiversity, with the LDO setting a minimum 10% gain.
LPA: Local Planning Authority, here Rushcliffe Borough Council.
LGR: Local Government Reorganisation, the restructuring of local authorities, assessed as not applicable in this case.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item24
Resolved
It was RESOLVED that : a) the should remain in force in its current form and that no amendments are required at the present time; b) the operation and effectiveness of the Local Development Order should continue to be monitored, with any future amendments being considered should circumstances or evidence justify such changes.
Word for word from the decision Rushcliffe published for this meeting.Source: democracy.rushcliffe.gov.uk
1.1On 13 July 2023, the Council adopted a Local Development Order (LDO) for the former Ratcliffe on Soar Power Station to streamline the planning process and establish the types of development that are permitted on the site. The LDO allows for the creation of an industrial park focused on advanced manufacturing (including technologies that support the transition to net zero), green and low- carbon energy generation, data centres, and energy storage. The LDO grants planning permission, equivalent to the granting of outline planning consent, for the site’s development in accordance with the conditions applied to the Order and the other provisions contained within it. The use of LDOs was encouraged by Government for Freeport sites in order to help accelerate development and provide greater planning certainty.
1.2Condition 1 of the LDO requires the Council to undertake a review on the third anniversary of its adoption, and at five-yearly intervals thereafter, to consider the continued suitability of the Order in the light of changing planning policy and market conditions. Following each review, the Council must determine whether the LDO should be retained without amendment, retained with revisions, or revoked.
1.3In advance of the third anniversary review, the LDO was amended in May 2026 following a request from the site owner, Uniper. The amendments enabled data centre development on the southern part of the site, provided greater flexibility regarding the delivery of environmental mitigation works, and clarified the operation of Local Labour Agreements on site.
1.4This report reviews whether there is any justification, having regard to the operation of the LDO to date, changes in planning policy, and other material considerations, to revoke or further amend the LDO. The report concludes that there is no substantive justification for doing so and recommends that the LDO be retained in its current form. 2. Recommendation
It is RECOMMENDED that Cabinet:
a) agrees that the Ratcliffe on Soar Local Development Order should remain in force in its current form and that no amendments are required at the present time; and
b) agrees that the operation and effectiveness of the Local Development Order should continue to be monitored, with any future amendments being considered should circumstances or evidence justify such changes.
Reasons for recommendation
3.1Condition 1 of the Ratcliffe on Soar Local Development Order (LDO) requires the Council to undertake a review on the third anniversary of its adoption and determine whether the Order should be retained, amended or revoked.
3.2There is no evidence to suggest that the LDO is failing to operate as intended or that further amendments are currently required. The amendments approved in May 2026 addressed the principal issues identified since the LDO was adopted and no further operational concerns have been identified.
3.3Furthermore, the policy justification for the LDO remains valid. The development permitted by the LDO continues to align with national policy objectives and the site's proposed allocation within the emerging Greater Nottingham Strategic Plan. Accordingly, retaining the LDO in its current form is considered the most appropriate course of action at this stage.
4. Supporting Information
Background
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.