Item7
Resolved
Decision 14/00706/FULPP Against the Council’s decision to refuse planning permission in January, 2015. The Hearing commenced on 9th December, 2015 and was adjourned to resume on 25th February, 2016, to allow time for the appellants to discuss possible solutions to overcome the highways objections to the scheme with Hampshire Highways Development Planning. The Inspector assessed the ‘Option E’ proposals and considered the scheme to be much preferred and acceptable. Allowed -- Application for costs was made by the Council at the Hearing in the basis that the Council had incurred unnecessary expense in responding to and preparing for the appeal. The Inspector considered that there had been no unreasonable behaviour and the appellants were entitled to pursue alternative proposals. No Costs Award