Resolved
That the Head of Planning’s Report No. PLN1729 be noted .
Development Management Committee noted this item on Wednesday 16 August 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Head of Planning’s Report No. PLN1729 be noted .
Development Management Committee Directorate of Community and 16th August 2017 Environment Planning Report No. PLN1729
Planning (Development Management) summary report for the quarter Apr-Jun 2017
1. Introduction
1.1The purpose of this report is to update Members on the position with respect to Performance Indicators for the Development Management Section of Planning, and the overall workload of the Section. This report covers the quarter from 1st April to 30th June.
2. Planning Applications
2.1The three tables below set out figures relating to Major, Minor and ‘Other’ planning applications for the first quarter. We are required to provide the government with statistical returns in relation to these categories. It should be noted that the returns required by government do not include a number of application types including applications for certificates of lawfulness, applications for prior approval for larger householder extensions, applications for the approval of details pursuant to conditions and applications to fell or carry out works to TPO trees. These applications however constitute a significant source of demand on our service, numbering 103 cases in the quarter, and are included in the total figures reflecting workload set out at 3.1 below.
Major and small scale major Applications determined within 13 weeks/PPA target Decisions in Apr-Jun 2017 Government 2016/2017 quarter Target Total 5* 100% 60% 94% Whilst 2 of the 5 decisions were issued after the 13 week period, both were the subject of agreed extensions of time by the applicants and therefore recorded as in time for government returns.
Minor (Non householder) Applications determined within 8 weeks Decisions in Apr-Jun 2017 Government 2016/2017 quarter Target Total 34 85% 65% 75.7% Whilst 10 of the 34 applications were issued after the 8 week period, five were the subject of agreed extensions of time by the applicants and therefore recorded as in time for government returns.
‘Other’ (Including Householder) Applications determined within 8 weeks Decisions in Apr-Jun 2017 Government 2016/2017 quarter Target Total 118 96.6% 80% 95.4%
2.2The following table sets out figures relating to appeals allowed against the authority’s decision to refuse permission. % of appeals allowed against the authority’s decision to refuse
2016/2017 Government Apr-Jun Appeal Total Target 2017 Decisions 20% 40% max 0% 3
3. Workload
3.1This section deals with workload demand on the Development Management Section in the past three months and the full year.
Departmental Work Demand Apr-Jun 2017 Applications Pre-Application Incoming Applications Appeals Submitted (All Cases Telephone Calls Determined (All Submitted types) types) 282 110 2773 279 2
3.2The following graphs present the time period being taken to determine different types of application.
Major and small-scale majors Total 5
Decision in Weeks 4
0 13 17 18 Weeks to Decision
3.3Performance with regard to Major applications remains buoyant with all five cases either determined within the statutory 13 week period, or the subject of agreed extensions of time. Minor (Non householder) applications Total 34
Decision in Weeks 10
0 2 4 5 6 7 8 9 11 12 14 19 Weeks to Decision
3.4This second graph illustrates the determination times for minor applications, 85% of which were determined within the statutory date or in accordance with agreed extensions of time.
‘Other’ (Including Householder) applications Total 118
Decision in Weeks 60 40 20 0 3 4 5 6 7 8 10 11 12 16 Weeks to Decision
3.5This third graph shows that in the final quarter of this financial year the majority of householder applicants have continued to receive decisions in the third and fourth weeks after their validation date.
4. Fee Income
4.1The total amount of planning fee income received for the quarter was £129,628.
5. Section 106 contributions
5.1Information in this section relates to financial contributions secured by way of section 106 planning obligations.
Apr-Jun 2017 Section 106 contributions received
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Planning (Development Management) Summary Report for the Quarter April: June 2017Report | 89 KB | DownloadRead as text |
Follow Development Management Committee at Rushmoor and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Oct 2026 | Planning ApplicationsThat (i) permission be given to the following application, as set out in Appendix “A” (as required), subject to the c... | Agreed | Open |
| 14 Oct 2026 | Enforcement and possible unauthorised developmentThat the Executive Head of Property and Growth’s Report No. PG2619 be noted. | Noted | Open |
| 14 Oct 2026 | Appeals Progress ReportThat the Executive Head of Property and Growth’s Report No. PG262620 be noted. | Noted | Open |
| 15 Jul 2026 | Planning ApplicationsThat (i) permission be given to the following application, as set out in Appendix “A” (as required), subject to the c... | Noted | Open |
| 17 Jun 2026 | Planning ApplicationsThat (i) the following application be determined by the Executive Head of Property and Growth, in consultation with t... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.