DEVELOPMENT OF REGENERATION POLICY - ADVISORY BOARD ROLE
AgreedCommittee1 paper
Policy and Project Advisory Board agreed this item on Wednesday 21 November 2018. Below is the council's own wording, with the papers it was decided on.
It was agreed that the Farnborough Civic Quarter Masterplan should also be reported to the full Advisory Board. The public engagement on the Farnborough Civic Quarter Masterplan was discussed and officers were encouraged to ensure that public engagement was interactive and well publicised. It was agreed that any strategies supporting or related to regeneration be reported to the full Advisory Board. The Advisory Board supported that all issues relating to regeneration policy and consultation should be reported to the Progress Group and/or the full Advisory Board. It was agreed, as a consequence , that the Farnborough Regeneration Task and Finish Group and the Aldershot Regeneration Task and Finish Group should be dissolved as the issues were of significant importance and of interest to all Members of the Advisory Board. Action to be taken By whom When Work programme to be updated ... view the full minutes text for item 19.
Word for word from the decision Rushmoor published for this meeting.Source: democracy.rushmoor.gov.uk
1.1Earlier this year the Policy and Projects Advisory Board (PPAB) set up a number of task and finish groups. Given the importance of the Council’s regeneration programme, the Board established a Farnborough Town Centre Task and Finish Group (Cllrs Marina Munro, Martin Tennant, Liz Corps, Paul Taylor, Clive Grattan, and Barry Jones) and an Aldershot Town Centre Task and Finish Group (Cllrs Sophia Choudhary, Martin Tennant, Peter Crerar, Maurice Sheehan, Alex Crawford & Sue Dibble)
1.2At that time, the PPAB was unclear as to how the regeneration programme was to be taken forward given the proposed establishment of the investment partnership and supporting governance arrangements. It was agreed that initially regeneration related matters would be considered first by the Progress Group/PPAB and passed on to the relevant Task and Finish Groups as required with further consideration on the respective PPAB’s and Task and Finish Group roles taking place after the regeneration update seminar for all members held earlier in the autumn.
1.3Since the seminar, the PPAB Progress Group has considered a paper that set out member involvement in regeneration including executive, programme governance and other oversight. These arrangements are set out in the following table.
Group Membership Purpose Regeneration Steering Cllrs David Clifford, Overseeing delivery and Group Ken Muschamp & providing direction of Martin Tennant the whole regeneration Executive Leadership programme. Team Cabinet Cabinet Decision making (or recommendation to Council) as required to enable the schemes to proceed eg land transfers, submission of planning applications, acquisitions. Performance/delivery of the whole programme as part of quarterly performance monitoring. Overview and Scrutiny Overview and Scrutiny To hold Cabinet to account for performance. Rushmoor Development Rushmoor Board To bring forward Partnership LLP Members: Cllrs Martin specific development Tennant & David schemes (currently 4) in Clifford, Executive accordance with the Director Karen Edwards RDP business plan as agreed by Council (annually). Licensing, Audit and Licensing, Audit and To receive the reports General Purposes General Purposes + of the LLP to ensure Chief Executive delivery in accordance with the business plan All Member seminars All Members Twice yearly Consultation on major All Members would be As required by planning applications invited applicants e.g. Galleries, Farnborough Town Centre
1.4The Progress Group then considered the key regeneration matters which they might wish to have a role either as a board, via a task and finish group or as individual members. As a result of that discussion the group requested that a paper be brought to this meeting setting out a recommended approach for PPAB member involvement in the key regeneration work expected to come forward over the next 12 months
2.0KEY REGENERATION MATTERS FOR NEXT 12 MONTHS
2.1Key regeneration related matters anticipated over the next 12 months considered of interest to the PPAB in its advisory role are as follows:
Aldershot town centre strategy Farnborough Civic Quarter consultation and subsequent masterplan The Galleries scheme and other major planning applications by third parties Rushmoor Development Partnership (RDP) site proposals for the RDP business plan o Civic Quarter o Union Street East, Aldershot; o Parsons Barracks car park; o Farnborough Main car park Farnborough growth package (highways and transport) Strategies supporting or related to regeneration e.g. parking, housing electric vehicles, open spaces
3.0PROPOSED APPROACH
3.1Aldershot Town Centre Strategy - A report was considered by the PPAB on 19 September asking Members to provide their views on potential activities to include in the strategy.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Appointments to elections group 2026/27RESOLVED : That the following members be appointed to serve on the Elections Group for the 2026/27 Municipal Year: Ca...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.