Rushmoor Borough Council
Audit and Governance Committee, Tuesday 29 September 2026 at 7.00pm

Reserve Risk Assessment Update Report

Noted Finance 1 paper

AI summaryRushmoor's audit committee notes Ernst & Young reserve risk assessment, which finds that assurance gaps predating 2023/24 cannot be rebuilt in 2025/26 and rates the Revaluation Reserve and Capital Adjustment Account as significant risk.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedErnst & Young reserve risk assessment update received
MoneyNot stated
What happens nextRedo risk assessment in 2026/27Scale fee variation to cover extra work
Who it affectsCouncil 2025/26 audit assurancePath to qualified or unmodified opinions

What was decided

The Audit and Governance Committee noted the Reserve Risk Assessment Update Report from Ernst & Young, the council's external auditor. Report P4

The committee received the finding that the Revaluation Reserve and the Capital Adjustment Account are classed as significant risk, while the General Fund, Capital Grants Unapplied Account and Pooled Investments adjustment account are higher inherent risk, three other reserves are lower inherent risk, and the Pension reserve needs no rebuild because assurance over the 2024/25 closing balance was already obtained. Report P19, P20, P23, P24, P25

The committee received the conclusion that assurance gaps predating 2023/24 cannot be rebuilt in the 2025/26 audit because of the scale of historic balances and insufficient supporting evidence, leaving the council behind the LARRIG 01 timescale. Report P28, P37

Why

Ernst & Young issued disclaimers of opinion for 2023/24 and 2024/25 after the statutory backstop applied, so the council's historic assurance is incomplete. Report P14, P36, P37

The National Audit Office's Local Authority Reset and Recovery Implementation Guidance (LARRIG 06) requires auditors to carry out specific risk assessment procedures over reserves, which may hold the cumulative effect of unaudited transactions over more than one year. Report P14

The assessment looked at the nature and purpose of each reserve, the scale of movements during the disclaimed periods, susceptibility to misstatement including fraud and management bias, the wider financial reporting control environment, and the classification between usable and unusable reserves. Report P16

What happens next

Ernst & Young will seek a variation to the scale fee set in the Audit Planning Report issued on 10 June 2026, to cover the risk assessment, the MHCLG submission and the historical rebuild work. Report P30

Ernst & Young will repeat the risk assessment as part of 2026/27 audit planning to update whether the council can begin the historical rebuild of assurance. Report P28

Management is expected to focus on producing high quality financial statements, working papers and audit evidence for the 2025/26 cycle so the natural rebuild of assurance can begin and any further delay is avoided, which the report flags as critical given the timing of upcoming Local Government Reorganisation. Report P28

Options considered

  • Chosen: Note the Reserve Risk Assessment Update Report

Implications

  • Financial: Ernst & Young will seek a variation to the scale fee for the reserve risk assessment, the MHCLG submission and the historical rebuild work. Report P30
  • Risk: Two reserves are rated significant risk and three are rated higher inherent risk, with the Revaluation Reserve and Capital Adjustment Account both flagged for their reliance on valuations of property, plant and equipment and investment property. Report P19, P20
  • Risk: Pre 2023/24 assurance gaps cannot be rebuilt in 2025/26, so the council remains behind the LARRIG 01 expected timescale for moving from disclaimed to qualified or unmodified opinions. Report P28, P37
  • Other: The report flags the timing of upcoming Local Government Reorganisation as a reason to address underlying issues in the 2025/26 cycle. Report P28

Who and where

  • Rushmoor Borough Council and its management Report P28, P37
  • Ernst & Young as the council's external auditor Report P4, P5
  • Ministry for Housing, Communities and Local Government (MHCLG), which receives the capacity and risk assessment return Report P14, P30
  • Public Sector Audit Appointments Ltd (PSAA), which oversees the auditor appointment Report P11

Timeline

  • 31 March 2026: Council's financial year end Report P1
  • 2026/27 audit planning: Ernst & Young will repeat the reserve risk assessment Report P28
  • 23 April 2026: Ernst & Young issued the Audit Planning Report for the 2025/26 audit Report P4
  • 10 June 2026: Audit Planning Report setting out the scale fee issued Report P30
  • 30 July 2026: Reserve Risk Assessment Update Report dated Report P2
  • 29 September 2026: Audit and Governance Committee meeting held and report noted Report P4
  • 2023/24 and 2024/25: Disclaimer of opinion issued due to application of the backstop Report P36, P37

Plain English for the jargon

  • LARRIG: Local Authority Reset and Recovery Implementation Guidance, issued by the National Audit Office to set out how auditors should rebuild assurance after disclaimed opinions.
  • Disclaimer of opinion: An audit opinion issued when the auditor is unable to form an opinion on the financial statements, here triggered by the statutory backstop deadline.
  • Backstop: Statutory deadline introduced as part of the local audit reset, after which auditors must issue a disclaimer if work is incomplete.
  • Natural rebuild: Process of completing planned audit procedures across successive audit years to rebuild assurance over financial balances.
  • PSAA: Public Sector Audit Appointments Ltd, which appoints auditors to local bodies and sets terms of engagement.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item13

Resolved

RESOLVED : That the Reserve Risk Assessment Update Report be noted.
Word for word from the decision Rushmoor published for this meeting. Source: democracy.rushmoor.gov.uk

Follow this further

Built from Rushmoor's papers

What the report saysPro

Report to Audit and Governance Committee

Rushmoor Borough Council Rebuilding audit assurance: the path to an unqualified opinion Year ended 31 March 2026

30 July 2026 Private and Confidential 30 July 2026

Audit and Governance Committee Rushmoor Borough Council Council Office, Farnborough Road Farnborough, Hants GU14 7 JU

Dear Audit and Governance Committee Rebuilding audit assurance – risk assessment update We attach our risk assessment update for consideration at the forthcoming meeting of the Audit and Governance Committee. The purpose of this paper is to provide the Audit and Governance Committee with further detail on the risk assessment procedures performed in respect of opening reserve balances. These procedures have been undertaken in response to the prior-year disclaimed audit opinions and in accordance with the National Audit Office’s Local Authority Reset and Recovery Implementation guidance. This update should be read in conjunction with our Audit Planning Report for the 2025/26 audit, issued on 23 April 2026. We welcome the opportunity to discuss this report with you at the meeting on 29 September 2026, and to understand whether there are any additional matters which the committee considers may influence our risk assessment. Yours faithfully

Simon Mathers, Partner For and on behalf of Ernst & Young LLP Enc

The UK firm Ernst & Young LLP is a limited liability partnership registered in England and Wales with registered number OC300001 and is a member firm of Ernst & Young Global Limited. A list of members’ names is available for inspection at 1 More London Place, London SE1 2AF, the firm’s principal place of business and registered office. Ernst & Young LLP is a multi-disciplinary practice and is authorised and regulated by the Institute of Chartered Accountants in England and Wales, the Solicitors Regulation Authority and other regulators. Further details can be found at http://www.ey.com/UK/en/Home/Legal. Background and regulatory context Scope of our risk assessment Summary of risk assessment findings

Background and Scope of our risk Summary of risk 1 regulatory context 2 assessment 3 assessment findings

Implications for the 2025/26 audit

Appendix A

Implications for the Appendix A 4 2025/26 audit 5

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Reserve Risk Assessment Update ReportReport 451 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 11 attended
BO
Councillor Bill O'DonovanChair, expected
MT
Councillor Martin TennantVice-Chair, expected
PC
Councillor Peter CullumCommittee Member, expected
CC
Councillor Craig CardCommittee Member, expected
TD
Councillor Thomas DayCommittee Member, expected
TM
Councillor Thomas MitchellCommittee Member, expected
DS
Councillor Dhan SarkiCommittee Member, expected
IS
Councillor Ian SimpsonCommittee Member, expected
SS
Councillor Sarah SpallCommittee Member, expected
PT
Councillor Paul TaylorCommittee Member, expected
LB
Lucy BinghamSecretary, expected

More from Rushmoor Audit and Governance Committee

All decisions
MeetingDecisionOutcome
29 Sep 2026 Internal Audit Progress ReportRESOLVED : That SIAP’s Report No. SIAP26/05 be noted. Noted Open
29 Sep 2026 Corporate Policy and Guidance and the use of the Regulation of Investigatory Powers Act 2000RESOLVED : That the Surveillance and RIPA & IPA Policy and Guidance be approved and the contents of Report No. LEG260... Approved Open
29 Sep 2026 Annual Ombudsman Complaint Review LetterRESOLVED : That: ( i ) the Annual Review Letter be noted; and (ii) the Council commend officers on the positive outco... Noted Open
30 Jul 2026 Freedom of Information - Annual Update Report 2026RESOLVED : That officers: (i) continued the work on reducing the number of overdue FOIs within the system in 2026 and... Decided Open
30 Jul 2026 Corporate Health and Safety Arrangements 2025/26RESOLVED : That the Executive Director’s Report No. ED2613, be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies